MCM Management Corp. v. Hudson Insurance Company

CourtDistrict Court, N.D. Illinois
DecidedDecember 12, 2022
Docket1:21-cv-04255
StatusUnknown

This text of MCM Management Corp. v. Hudson Insurance Company (MCM Management Corp. v. Hudson Insurance Company) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MCM Management Corp. v. Hudson Insurance Company, (N.D. Ill. 2022).

Opinion

UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION

MCM MANAGEMENT CORP. ) ) Plaintiff, ) No. 21 C 4255 ) v. ) Judge Jorge L. Alonso ) HUDSON INSURANCE COMPANY, ) ) Defendant. )

MEMORANDUM OPINION AND ORDER

Believing it was owed money under a surety contract, plaintiff MCM Management Corp. (“MCM”) filed in the Circuit Court of Cook County a complaint asserting claims for breach of contract and declaratory judgment. Plaintiff sought damages for defendant’s alleged breach of performance and payment bonds and sought a declaration that defendant was liable under the bonds. Defendant Hudson Insurance Company (“Hudson”) removed the case to this Court.1 0F Defendant has filed a motion for summary judgment. For the reasons set forth below, the Court grants defendant’s motion for summary judgment. I. BACKGROUND The following facts are undisputed unless otherwise noted.2 1F

1 The Court has jurisdiction over this case pursuant to 28 U.S.C. § 1332(a)(1). The amount in controversy exceeds $75,000.00. [Docket 1 at ¶ 6; Docket 36-1 at 33]. Plaintiff MCM is a citizen of Michigan, its state of incorporation and the location of its principal place of business. [Docket 1 at ¶ 8]. Defendant Hudson is a citizen of Delaware (its state of incorporation) and New York (the location of its principal place of business). [Docket 1 at ¶ 9].

2 Local Rule 56.1 outlines the requirements for the introduction of facts parties would like considered in connection with a motion for summary judgment. The Court enforces Local Rule 56.1 strictly. See FTC v. Bay Area Business Council, Inc., 423 F.3d 627, 633 (7th Cir. 2005) (“Because of the important function local rules like Rule 56.1 serve in organizing the evidence In late 2017, in connection with a demolition project on the south side of Chicago, plaintiff MCM entered an agreement with HRE Crawford, LLC (which is not a party) to provide demolition and removal services. A few months later, on February 26, 2018, MCM entered into a subcontract with Jenkins Environmental, Inc. (“JEI”), under which subcontract JEI agreed to

perform all of MCM’s work under MCM’s contract with HRE Crawford, LLC. JEI, in turn, entered into sub-subcontracts. First, JEI entered into one sub-subcontract (“First Sub-subcontract”) with Marine Technology Solutions, LLC (“MTS”) for $609,325.00. Under that First Sub-subcontract, MTS agreed to provide oversight and support services for environmental remediation work. Second, on March 31, 2018, JEI entered into a second sub- subcontract (“Second Sub-subcontract”) with MTS for $299,662.00. Under that Second Sub- subcontract, MTS agreed to perform “Remediation Physical Set-up.” Defendant Hudson issued performance and payment bonds for the Second Sub- subcontract. Specifically, defendant issued Performance Bond No. 10072088 (the “Performance Bond”) and Payment Bond No. 10072088 (the “Payment Bond”). The Performance Bond and

and identifying disputed facts, we have consistently upheld the district court’s discretion to require strict compliance with those rules.”). At the summary judgment stage, a party cannot rely on allegations; he or it must put forth evidence. Fed.R.Civ.P. 56(c)(1)(A); see also Grant v. Trustees of Indiana Univ., 870 F.3d 562, 568 (7th Cir. 2017) (“As the ‘put up or shut up’ moment in a lawsuit,’ summary judgment requires a non-moving party to respond to the moving party’s properly-supported motion by identifying specific, admissible evidence showing that there is a genuine dispute of material fact for trial.”). Where one party supports a fact with admissible evidence (i.e., not complaint allegations) and the other party fails to controvert the fact with citation to admissible evidence (i.e., not complaint allegations), the Court deems the fact admitted. See Curtis v. Costco Wholesale Corp., 807 F.3d 215, 218-19 (7th Cir. 2015); Ammons v. Aramark Uniform Servs., Inc., 368 F.3d 809, 817-18 (7th Cir. 2004). This does not, however, absolve the party putting forth the fact of the duty to support the fact with admissible evidence. See Keeton v. Morningstar, Inc., 667 F.3d 877, 880 (7th Cir. 2012). the Payment Bond bonded only the Second Sub-subcontract, i.e., only the Remediation Physical Set-up. That is why each bond lists the amount as “$299,622.00.” The Performance Bond and the Payment Bond are form contracts by the American Institute of Architects. Each lists MTS as “SUBCONTRACTOR” and as “PRINCIPAL.” Each

bond lists JEI as Construction Manager and lists defendant as “SURETY.” (Performance Bond at 1/Docket 36-1 at 33; Payment Bond at 4/Docket 36-1 at 36). The Performance Bond states, in relevant part: 3. If there is no Construction Manager Default, the Surety’s obligation under this Bond shall arise after:

3.1 The Construction Manager has notified the Subcontractor and the Surety at the address described in Paragraph 10 below that the Construction Manager is considering declaring a Subcontractor Default and has requested and attempted to arrange a conference with the Subcontractor and Surety to be held not later than 10 days after receipt of such notice to discuss methods of performing the Subcontract. If the Construction Manager, the Subcontractor and the Surety agree, the Subcontractor shall be allowed a reasonable time to Perform the Subcontract, but such an agreement shall not waive the Construction Manager’s right, if any, to subsequently declare a Subcontractor Default; and

3.2 The Construction Manager has declared a Subcontractor Default and formally terminated the Subcontractor’s right to complete the Subcontract. Such Subcontractor Default shall be declared earlier than fifteen days after the Subcontractor and the Surety have received notice as provided in Subparagraph 3.1; and

3.3 The Construction Manager has agreed to pay the Balance of the Subcontract Amount to the Surety in accordance with the terms of the Subcontract or to a Contractor selected to perform the Subcontract in accordance with the terms of the contract with the Construction Manager.

4. When the Construction Manager has satisfied the conditions of Paragraph 3, the Surety shall promptly and at the Surety’s expense take one of the following actions:

4.1 Arrange for the Subcontractor, with consent of the Construction Manager, to perform and complete the Subcontract; or 4.2 Undertake to perform and complete the Subcontract itself, through its agents or through independent contractors; or

4.3 Waive its right to perform and complete, arrange for completion, or obtain a new contractor and with Reasonable promptness under the circumstances:

1. After investigation, determine the amount for which it is liable to the Construction Manager, and, as soon as practicable after the amount is determined, tender payment therefore to the Construction Manager; or 2. Deny liability in whole or in part and notify the Construction Manager citing reasons therefore.

5 If the Surety does not proceed as provided in paragraph 4 with reasonable promptness, the Surety shall be deemed to be in default on this Bond ten days after receipt of an additional written notice from the Construction Manager to the Surety demanding that the Surety perform its obligations under this Bond and the Construction Manager shall be entitled to enforce any remedy available to the Construction Manager.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doris Keeton v. Morningstar, Incorp
667 F.3d 877 (Seventh Circuit, 2012)
Clyde Ammons v. Aramark Uniform Services, Inc.
368 F.3d 809 (Seventh Circuit, 2004)
People Ex Rel. Department of Public Health v. Wiley
843 N.E.2d 259 (Illinois Supreme Court, 2006)
VEE SEE CONSTRUCTION CO. v. Luckett
430 N.E.2d 91 (Appellate Court of Illinois, 1981)
Quake Construction, Inc. v. American Airlines, Inc.
565 N.E.2d 990 (Illinois Supreme Court, 1990)
Outboard Marine Corp. v. Liberty Mutual Insurance
607 N.E.2d 1204 (Illinois Supreme Court, 1992)
Dragon Construction, Inc. v. Parkway Bank & Trust
678 N.E.2d 55 (Appellate Court of Illinois, 1997)
Gallagher v. Lenart
874 N.E.2d 43 (Illinois Supreme Court, 2007)
Midwest Concrete Products Co. v. La Salle National Bank
418 N.E.2d 988 (Appellate Court of Illinois, 1981)
Travelers Insurance v. Eljer Manufacturing, Inc.
757 N.E.2d 481 (Illinois Supreme Court, 2001)
Centerre Trust Co. v. Continental Insurance
521 N.E.2d 219 (Appellate Court of Illinois, 1988)
Hunt Construction Group, Inc. v. National Wrecking Corporation
542 F. Supp. 2d 87 (District of Columbia, 2008)
Enterprise Capital, Inc. v. San-Gra Corp.
284 F. Supp. 2d 166 (D. Massachusetts, 2003)
Susan Spitz v. Proven Winners North America
759 F.3d 724 (Seventh Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
MCM Management Corp. v. Hudson Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcm-management-corp-v-hudson-insurance-company-ilnd-2022.