Centerre Trust Co. v. Continental Insurance

521 N.E.2d 219, 167 Ill. App. 3d 376, 118 Ill. Dec. 151, 1988 Ill. App. LEXIS 337
CourtAppellate Court of Illinois
DecidedMarch 16, 1988
Docket5-86-0832
StatusPublished
Cited by3 cases

This text of 521 N.E.2d 219 (Centerre Trust Co. v. Continental Insurance) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Centerre Trust Co. v. Continental Insurance, 521 N.E.2d 219, 167 Ill. App. 3d 376, 118 Ill. Dec. 151, 1988 Ill. App. LEXIS 337 (Ill. Ct. App. 1988).

Opinion

JUSTICE KARNS

delivered the opinion of the court:

Centerre Trust Company of St. Louis appeals a judgment of the circuit court of Jefferson County in which Centerre was held to have waived its right to liquidated damages arising from a breach of a construction contract. The trial court held that the making of final payment waived liquidated damages under the contract and that Centerre’s conduct in light of its liquidated damage claim also evidenced an intent to relinquish its right to claim liquidated damages and therefore constituted a waiver under the principles of common law.

On November 3, 1979, the Grove Partnership entered into a contract with U.D.E., Inc. (hereinafter contractor), for the construction of a facility then known as the Jefferson Memorial Hospital, later known as the Mt. Vernon Hospital Project. Art Lewis and Glen Lewis executed the contract on behalf of Grove Partnership and one of the Lewises executed the contract on behalf of the contractor. Theodore Hoener was the project architect.

Funding for the project was provided by a $9.375 million revenue bond issue underwritten by Hereth, Orr and Jones. To obtain tax-exempt status for the bonds, a nonprofit corporation known as the Jefferson County Health Authority (the Authority) was organized to hold legal title to the project. Another entity, Mt. Vernon Hospital, Inc., was organized to operate the hospital and the Authority, as landlord, executed a lease with Mt. Vernon Hospital, Inc.

Centerre Trust was chosen as trustee for the bondholders and executed an indenture of mortgage and deed of trust with the Authority. Centerre agreed, pursuant to the trust agreement, to collect the revenue from the sale of the bonds and the revenue derived by the Authority from rent for the hospital and to distribute principal and interest to the bondholders as the bonds were retired. Centerre further agreed to distribute construction funds to the contractor as the work progressed, in accordance with the lease and the trust.

Pursuant to the lease, a bond was obtained to insure the contractor’s performance. At the time, only $1.5 million of work remained to be performed under the contract and this was the amount of the bond issued by defendant, Continental Insurance Company. A dual obligee rider was also issued making Centerre a direct beneficiary of the performance bond.

Article 3 of the construction contract provides that “substantial completion” of the work was to be achieved by January 1, 1981 (the “substantial completion date”). Article 3 further provides that the contractor must pay the owner liquidated damages in the amount of $3,000 per day for each calendar day that transpired between the substantial completion date and the date of actual completion, such liquidated damages to be paid to the owner within 60 days after the date of actual completion.

The Mt. Vernon Hospital Project was actually completed on May 27, 1981, almost five months after the substantial completion deadline. The record shows that Centerre continued disbursing construction funds to the contractor after January 1, 1981, even though it knew that a claim for liquidated damages had arisen. The final payment of $50,000 was made on May 21, 1981.

On April 18, 1983, Centerre filed suit against Continental based on the dual obligee rider to the performance bond, seeking $438,000 in damages. After a bench trial, the circuit court of Jefferson County ruled that Centerre had waived its claim to liquidated damages by virtue of section 9.9.4 of the “General Conditions.” Section 9.9.4 states:

“The making of final payment shall constitute a waiver of all claims by the Owner except those arising from:
.1 unsettled liens,
.2 faulty or defective work appearing after substantial completion,
.3 failure of the work to comply with the requirements of the Contract Documents, or
.4 terms of any special warranties required by the Contract Documents.”

The trial court ruled that by making the final $50,000 payment, Centerre waived its claim to liquidated damages.

The trial court also ruled that Centerre’s conduct after January 1, 1981, constituted a common law waiver.

On January 26, 1981, after Centerre became aware of its liquidated damages claim, it was advised by counsel for the revenue bond underwriters to withhold all contract balances still in Centerre’s control to cover its claim for liquidated damages. On February 12, 1981, Centerre agreed to withhold all contract balances it was then holding. On April 27, 1981, Centerre entered into an agreement with the contractor whereby it agreed to release the contract balances it was then holding provided that the contractor would loan such payments to the operating capital account of the project. This agreement was prompted by the severe financial difficulties the project was encountering, and the contractor eventually loaned over $1 million to the project before the contractor went bankrupt. The contractor also agreed to subordinate its repayment rights to Centerre’s obligation to pay the revenue bond holders. In September 1981, Centerre wrote a letter to the contractor and Mt. Vernon Hospital discussing the serious financial difficulties. The letter made no mention of Centerre’s claim for liquidated damages.

Based on these factors, the trial court ruled that Centerre’s conduct evinced an intentional relinquishment of a known right and, as such, effected a common law waiver of that right. The trial court also stated that such conduct waived section 7.6.2 of the “General Conditions,” which stated:

“No action or failure to act by the Owner, Architect or Contractor shall constitute a waiver of any right or duty afforded any of them under the Contract, nor shall any such action or failure to act constitute an approval of or acquiescence in any breach thereunder, except as may be specifically agreed in writing.”

The trial court reasoned that as Centerre’s conduct effectively waived this provision of the contract, its final payment to the contractor effectively waived its claim to liquidated damages under section 9.9.4 of the “General Conditions,” and such conduct also waived Centerre’s claim under principles of common law.

Centerre’s first argument on appeal is that the trial court erred in ruling that Centerre had waived liquidated damages under section 9.9.4 of the contract. Centerre maintains that its obligation to make final payment to the contractor arose before the contractor’s obligation to remit the liquidated damages.

Article 3 of the contract provides that if the work was not substantially complete by January 1, 1981, the “substantial completion date,” then

Free access — add to your briefcase to read the full text and ask questions with AI

Related

County of Dauphin v. Fid. & Deposit Co. of Md.
770 F. Supp. 248 (M.D. Pennsylvania, 1991)
Illinois State Toll Highway Authority v. Gust K. Newberg, Inc.
531 N.E.2d 982 (Appellate Court of Illinois, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
521 N.E.2d 219, 167 Ill. App. 3d 376, 118 Ill. Dec. 151, 1988 Ill. App. LEXIS 337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/centerre-trust-co-v-continental-insurance-illappct-1988.