Royal Ornamental Iron, Inc. v. Devon Bank

336 N.E.2d 105, 32 Ill. App. 3d 101, 1975 Ill. App. LEXIS 2935
CourtAppellate Court of Illinois
DecidedSeptember 4, 1975
Docket58253
StatusPublished
Cited by15 cases

This text of 336 N.E.2d 105 (Royal Ornamental Iron, Inc. v. Devon Bank) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Royal Ornamental Iron, Inc. v. Devon Bank, 336 N.E.2d 105, 32 Ill. App. 3d 101, 1975 Ill. App. LEXIS 2935 (Ill. Ct. App. 1975).

Opinion

Mr. JUSTICE MEJDA

delivered the opinion of the court:

Plaintiff, Royal Ornamental Iron, Inc., an Illinois corporation (Royal), commenced an action to foreclose a. mechanic’s lien on real estate owned by Devon Bank, as trustee under Trust No. 1237 (Devon Bank). Defendants answered the complaint and Devon Bank filed a counterclaim against Royal for alleged breach of contract. At trial, plaintiff Royal waived its claim for lien and sought a money judgment upon its contract. Following a trial without a jury, judgment was entered against plaintiff Royal, dismissing its complaint with prejudice and awarding judgment against it in favor of Devon Bank on the counterclaim in the sum of $17,710. Plaintiff has appealed from the judgment. The central issue is whether die judgment is contrary to the manifest weight of the evidence.

Plaintiff is in the ornamental iron business. Devon Bank holds tide to the real estate in Lincolnwood, Illinois, under an Illinois land trust. The beneficial interest in the trust is owned 50 percent by defendant Marshall D. Leib and 50 percent by Toulin, Inc. Devon Bank, as owner of the real estate, undertook to construct a bank and office building which was to consist of a basement, a ground floor and mezzanine to be occupied by the Bank of Lincolnwood, and a multistory office tower to be occupied by others. No general contractor was employed or involved. Leib was the architect in charge of construction.

On September 22, 1965, Royal entered into a written contract with Devon Bank, executed by Leib and Toulin as its agents, wherein Royal agreed to furnish and install specified ornamental and other work of metal. The contract provided that Devon Bank pay for the performance of the contract the lump sum of $15,500, with further itemization of the work and prices (excluding alternates not applicable here) as follows:

Breakdown of Prices: Stairwell # 1 $5,000.00 Stairwell # 2 3,600.00 Stairwell # 3 550.00 Stairwell # 4 300.00 Stairwell # 5 400.00 Stairwell # 6 400.00 Ornamental Railing and gate at roof garden 1,150.00 Ladders (all) 300.00 Railings in Bank area 2,700.00 Aluminum grating over electric vault 1,000.00 Woven wire partition at elevator penthouse 100.00 Total $15,500.00 Alternates: * * e

The relevant terms and provisions of the contract documents include:

(1) “At the earliest date after signing of contract, the Architect shall present an ‘Operations Schedule’ setting up sequence of operations and time table for each principal item of new work . . the schedule “shall be furnished as a guide . . . and shall be binding on them [the contractors] in their respective works; Failure to maintain schedule . . . shall constitute default”;
(2) Payment to each contractor shall be made on monthly certificates (up to 90S of the value of the work in place and of materials suitably stored on the site; except when so certified by the Architect, the Owner shall have the right to withhold payment to a contractor);
(3) Work is to commence immediately upon signing the contract or ás required by the Architect’s work sdhédule so that the building can be completed by July 14, 1966; and
(41 If a contractor persistently or repeatedly refused to supply sufficient labor and/or materials for proper progress or to correct work rejected by the Architect, then, upon certification by the Architect, the Owner may, upon five days’ written notice to the contractor, charge the same with his pro ráta share of damages, such as rent loss, financing interest arid carryirig charges incurred, for the length of time such delinquency continues.

Devon Bank in its counterclaim sought damages by Royal’s alleged delay in performance and also, by way of setoff against the contract amount, credit for expenditures made to correct and complete Royal’s work under the contract. Royal claimed that it was entitled to recover the contract amount less credits for work not done or done incorrectly. It alleged and presented evidence that although Devon Bank breached the contract by failure to pay its invoices when due, and failure to submit an operations schedule, Royal substantially performed its obligations under the contract.

Although there is evidence to show that the work completed by Royal was in some respects defective and incomplete, it clearly shows that all of the work specified was completed by August 11, 1966, with the exception of aluminum grating and woven wire partition, which were not installed by Royal.

No operations schedule was received by Royal. The construction had progressed to the point where on February 26, 1966, Royal could commence fabrication of the stairs and was so notified within a few days. Shop details were' prepared by Royal and submitted to Leib who approved them on March 15, 1966. Stairwell No. 2 was installed in mid-April, and stairwell No. 1 was installed by mid-May of 1966. Due to defects, stairwell No. 1 was not completed until approximately July 22, 1966. The evidence shows that stairwells Nos. 3, 4, 5 and 6 had been installed .by June 30, 1966. The evidence further shows that the remaining items, except for the aluminum grating and woven wire partition, bad been installed between August 1 and August 11, 1966.

Witnesses for Devon Bank testified that stairwells Nos. 1 and 2 would have been fabricated within 2 to 3 weeks after field measurements had been taken. In its brief Devon Bank argues that the delay in that installation “was of great significance to the progress of the job” in that failure to have stairs in place constituted a safety hazard to other contractors and personnel. Witnesses for Devon Bánk further testified that the installation of the stairs was defective. The evidence shows that although certain defects were remedied by Royal, others were remedied by Devon Bank. Witnesses for Devon Bank further testified that although stairwells Nos. 3, 4, 5 and 6 were installed, certain defects had to be remedied after installation.

As to the roof railings and gate, witnesses for Devon Bank testified that these items could have been installed as early as the end of May 1966; that installation was not completed until between August 1 and August 11, 1966; that Royal had previously been requested to install these items (no date was specified.as to the requests); and that the failure to install these items. within the “construction schedule” prevented the roofers from completing their work which in turn prevented any finishing work to be done on the inside of the building. On August 1, 1966, a memorandum was sent by the architect to Royal advising that the railings had to be installed by August 8 because the roofers were coming on the job.

As to the ornamental railings in the Bank area, witnesses for Devon Bank testified that this phase of the contract should have commenced by February 26, 1966, when the concrete and structural steel were in place; that those railings which were installed were in place by approximately May 15, 1966; that they were defective and had to be removed or repaired, and were finally installed by another contractor; and that the windows were not installed until .after the railings were in place which delayed completion of the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mormat Electrical & Construction Services, LLC v. Hunter Construction Services, Inc.
2019 IL App (5th) 170316 (Appellate Court of Illinois, 2019)
Mani Electrical Contractors v. Kioutas
611 N.E.2d 1167 (Appellate Court of Illinois, 1993)
Seidmon v. Harris
526 N.E.2d 543 (Appellate Court of Illinois, 1988)
Centerre Trust Co. v. Continental Insurance
521 N.E.2d 219 (Appellate Court of Illinois, 1988)
Herbert W. Jaeger & Associates v. Slovak American Charitable Ass'n
507 N.E.2d 863 (Appellate Court of Illinois, 1987)
Deerfield Electric Co. v. Herbert W. Jaeger & Associates, Inc.
392 N.E.2d 914 (Appellate Court of Illinois, 1979)
Drovers National Bank v. Great Southwest Fire Insurance
371 N.E.2d 855 (Appellate Court of Illinois, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
336 N.E.2d 105, 32 Ill. App. 3d 101, 1975 Ill. App. LEXIS 2935, Counsel Stack Legal Research, https://law.counselstack.com/opinion/royal-ornamental-iron-inc-v-devon-bank-illappct-1975.