This text of Delta Consulting v. R. Randle Construct (Delta Consulting v. R. Randle Construct) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delta Consulting v. R. Randle Construct, (7th Cir. 2008).

Opinion

In the

United States Court of Appeals For the Seventh Circuit

No. 07-3660

D ELTA C ONSULTING G ROUP, INCORPORATED ,

Plaintiff-Appellee, v.

R. R ANDLE C ONSTRUCTION, INCORPORATED AND R ONALD S. R ANDLE , Defendants-Appellants.

Appeal from the United States District Court for the Southern District of Illinois. No. 06 C 504—Michael J. Reagan, Judge.

A RGUED O CTOBER 23, 2008—D ECIDED F EBRUARY 5, 2009

Before B AUER, W OOD , and T INDER, Circuit Judges. B AUER, Circuit Judge. R. Randle Construction, Inc., and Ronald S. Randle (collectively, “Randle”) entered into two construction contracts with Belleville Township High School District 201 (School District) to perform 2 No. 07-3660

work as a general contractor on the Belleville East High School Project (Project). Disputes over the Project arose between Randle and the School District, which caused delays, which in turn, caused Randle to suffer finan- cial losses. Randle hired Delta Consulting Group, Inc. (Delta) to prepare and present a Request for Equitable Adjustment (REA) to the School District, to recover the damages attributable to the School District. Delta ex- pressed that the REA’s preparation, which included the necessary services, could typically be accomplished with the approximate preliminary budget of $34,000.00. Delta’s proposal stated that the figure represented an estimate of the amount normally required for these types of jobs. Randle paid Delta a $5,000.000 retainer. Using documents and information provided by Randle, Delta produced an REA representing damages for ap- proximately $1.6 million. The REA consisted of three phases: (1) Familiarization and Initial Assessment, which included a review of Randle’s documentation, site visits, key personnel interviews and assessment of claim issues; (2) Detailed Analysis and Report, which included extensive analysis of issues, a schedule analysis and a calculation of damages reflected in an REA; and (3) Dis- pute Resolution, which included Delta’s attendance at dispute resolution proceedings. Delta submitted the REA to the School District in an effort to recover Randle’s damages. The School District, through its representative, Landmark Contract Manage- ment, Inc. (Landmark), reviewed the REA and concluded that the accompanying documents and analysis did not support $1.6 million in damages. At Randle’s request, No. 07-3660 3

Delta undertook additional services to revise the REA using additional documentation from Randle; Delta submitted a second REA for approximately $1.7 million.1 On February 25, 2004, Delta and Randle met with Landmark to discuss the resubmitted REA. Landmark reviewed the claims with Delta and questioned the lack of documentation to support the School District’s liability for Randle’s damages. Although Delta attempted to address Landmark’s concerns, Landmark again found that the documentation did not adequately support the REA claim. On March 5, 2004, Randle met with Landmark to discuss the resubmitted REA; frustrated with Delta’s previous interactions with Landmark, Randle did not invite Delta to this meeting. Landmark repeated its con- cerns that the documentation submitted by Delta did not support the REA claim. Randle abruptly ended the meeting and claimed that he would sue the School District. Throughout this process, Randle received Delta’s in- voices for the REA services and continuously paid the invoices through March 9, 2004.2 Delta ultimately billed Randle $144,174.35; Randle paid $62,622.19 without objection (excluding the $5,000 retainer).

1 Sometime after the submission of the revised REA, the School District offered, and Randle rejected, $100,000.00 to settle the claim. 2 Although the date is unknown, the district court determined that Randle terminated Delta’s services sometime after its last payment on March 9, 2004. 4 No. 07-3660

Randle hired a private firm and sued the School District for damages caused by the delay of the Project. Delta accepted Randle’s request that Delta refrain from pursuing immediate collection on the unpaid invoices until Randle’s claim had been litigated. Ultimately, Randle settled its claim with the School District for $450,000.00. In October 2004, Randle’s accountants conducted an audit of Randle’s financial statements. As part of the audit, Randle, through its agent, sent Delta a letter to confirm that $89,302.16 was the amount due to Delta as of September 30, 2004. Delta responded that the correct amount due was $81,552.16. Randle did not object after receiving Delta’s response until roughly a year later. When Delta sought payment on the unpaid invoices, Randle responded that it was not satisfied with Delta’s performance and should not be charged for inadequate work. Delta sued Randle to recover $81,552.16 in unpaid invoices (ultimately seeking $76,552.16 after applying the initial retainer), plus 9% interest as permitted by law. Randle claimed that Delta failed to adequately present the REA and counterclaimed for breach of contract. On August 23, 2007, the district court granted Delta’s summary judgment motion in its entirety. Specifically, the district court held that the communications between Delta and Randle, which included Randle’s failure to object to Delta’s statement of account within a reason- able time and Randle’s partial payment of the account over the preliminary estimate, established an account stated. The district court also awarded summary judg- ment in favor of Delta on Randle’s counterclaim; Randle No. 07-3660 5

impliedly waived its right to damages for Delta’s alleged breach by paying, and not contesting, $62,622.19. On October 25, 2007, the district court further ordered: (1) that prejudgment interest at the Illinois statutory rate of 5% be awarded to Delta; and (2) that postjudgment interest at the Illinois statutory rate of 9% be awarded to Delta until Randle pays the judgment. This timely appeal followed.

DISCUSSION Randle argues that, as a matter of law, the district court erred in holding that an account stated existed against Randle, where genuine issues of material fact are present as to the amount owed to Delta. Randle also claims that genuine issues of material fact exist to preclude summary judgment on the waiver of its breach of contract counterclaim. Randle further argues that the district court improperly struck a portion of this counter- claim. Finally, Randle argues that the district court applied the incorrect rate to the postjudgment interest award. We review de novo the district court’s decision to grant summary judgment, construing all the facts and inferences in favor of Randle, the nonmoving party. See Springer v. Durflinger, 518 F.3d 479, 483-84 (7th Cir. 2008). We also apply the substantive law of Illinois, the state in which this diversity case was filed. See Global Relief Found., Inc. v. New York Times Co., 390 F.3d 973, 981 (7th Cir. 2004). Summary judgment is appropriate when the pleadings, depositions, answers to interrogatories, and admissions 6 No. 07-3660

on file, together with any affidavits, show that there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(c). “The initial burden is on the moving party . . . to demonstrate that there is no material question of fact with respect to an essential element of the non-moving party’s case.” Cody v. Harris, 409 F.3d 853, 860 (7th Cir. 2005).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Thomas J. Sumner
265 F.3d 532 (Seventh Circuit, 2001)
Mark Cody v. Taft Harris and Dontron, Inc.
409 F.3d 853 (Seventh Circuit, 2005)
Robert L. Holbrook v. Norfolk Southern Railway Company
414 F.3d 739 (Seventh Circuit, 2005)
Springer v. Durflinger
518 F.3d 479 (Seventh Circuit, 2008)
Ryder v. Bank of Hickory Hills
585 N.E.2d 46 (Illinois Supreme Court, 1992)
W. E. Erickson Construction, Inc. v. Congress-Kenilworth Corp.
477 N.E.2d 513 (Appellate Court of Illinois, 1985)
Motive Parts Co. of America, Inc. v. Robinson
369 N.E.2d 119 (Appellate Court of Illinois, 1977)
Protestant Hospital Builders Club v. Goedde
424 N.E.2d 1302 (Appellate Court of Illinois, 1981)
Wald v. Chicago Shippers Ass'n
529 N.E.2d 1138 (Appellate Court of Illinois, 1988)
Meeker v. Fowler
341 N.E.2d 412 (Appellate Court of Illinois, 1976)
Toth v. Mansell
566 N.E.2d 730 (Appellate Court of Illinois, 1991)
Gallagher v. Lenart
874 N.E.2d 43 (Illinois Supreme Court, 2007)
In Re Marriage of Angiuli
480 N.E.2d 513 (Appellate Court of Illinois, 1985)
Galesburg Clinic Ass'n v. West
706 N.E.2d 1035 (Appellate Court of Illinois, 1999)
Royal Ornamental Iron, Inc. v. Devon Bank
336 N.E.2d 105 (Appellate Court of Illinois, 1975)
PPM Finance, Inc. v. Norandal USA, Inc.
392 F.3d 889 (Seventh Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Delta Consulting v. R. Randle Construct, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delta-consulting-v-r-randle-construct-ca7-2008.