W. E. Erickson Construction, Inc. v. Congress-Kenilworth Corp.

477 N.E.2d 513, 132 Ill. App. 3d 260
CourtAppellate Court of Illinois
DecidedMay 2, 1985
Docket83-2197
StatusPublished
Cited by46 cases

This text of 477 N.E.2d 513 (W. E. Erickson Construction, Inc. v. Congress-Kenilworth Corp.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. E. Erickson Construction, Inc. v. Congress-Kenilworth Corp., 477 N.E.2d 513, 132 Ill. App. 3d 260 (Ill. Ct. App. 1985).

Opinion

PRESIDING JUSTICE JIGANTI

delivered the opinion of the court:

Plaintiffs, W. E. Erickson Construction, Inc., and Wilbert E. Erickson (jointly Erickson) brought this action to recover a sum allegedly due under a contract entered into with defendants, Congress-Kenilworth Corporation, James Adams and John Stafford (jointly C-K) for the construction of a concrete water slide, known as “Thunder Mountain Rapids” in Crestwood. C-K filed a counterclaim for damages, among other things, for construction defects. Following a bench trial, judgment was rendered for Erickson on count II of its amended complaint (breach of contract) in the amount of $202,000. The remaining counts I and III (preliminary injunction/appointment of receiver), IV (account stated), V (quantum meruit) and VI (accord and satisfaction) of Erickson’s amended complaint and C-K’s counterclaim were dismissed for want of equity. The trial court also awarded attorney fees to C-K from a fund held by the receiver, which previously had been appointed. Erickson appeals from the award of damages, the dismissal of counts I, III, IV, V and VI of its amended complaint and the award of attorney fees to C-K. C-K filed a cross-appeal which it has not pursued in this appeal.

The parties here are no strangers to this court. In an earlier appeal, we reversed an order appointing a receiver for C-K. (See W. E. Erickson Construction, Inc. v. Congress-Kenilworth Corp. (1983), 112 Ill. App. 3d 847, 445 N.E.2d 1209.) Much of the background surrounding this controversy is contained in that opinion and will not be repeated here. In summary, Erickson, a general contractor, entered into a contract with C-K for the construction of a concrete water slide for a total cost not to exceed $535,000, exclusive of additional costs and interest. The contract provided that Erickson would be paid the cost of the work performed by subcontractors, a contractor’s fee of 15% of the project cost, exclusive of concrete, carpentry, architectural and engineering costs, Erickson’s labor for concrete and carpentry work, and overhead, as well as additional amounts attributable to the costs of extra or modified work, permits, engineering fees, certain sewer and sanitary work, and interest at the rate of 2% over prime for overdue balances. Work commenced on April 15, 1981, and was completed on July 3, 1981. The project was open to the public the next day on July 4,1981. To date, Erickson has been paid $150,000 on the contract.

Under its amended count II, Erickson sought damages under the contract in the amount of approximately $550,000, the value of the contract Erickson claimed for its full performance under the contract. The trial court, however, found Erickson was entitled to $352,000 on its contract claim, and, after deducting $150,000 already paid to Erickson, awarded a judgment to Erickson for $202,000.

Erickson argues that the trial court erred in the assessment of damages awarded to it under the contract. Erickson maintains that the trial court, by entering judgment for it under its contract count, had found that Erickson had substantially performed under the contract. However, Erickson contends, the trial court did not award it damages for its substantial performance under the contract. Rather, Erickson asserts, the trial court erroneously entered judgment for it only in the amount of its out-of-pocket expenses for subcontractor labor and materials. C-K argues that the judgment entered was proper. C-K asserts that the trial court had found that Erickson had failed to substantially perform under the contract and, therefore, Erickson was not entitled to damages under the contract. Alternatively, C-K maintains that if the trial court had found that Erickson had rendered substantial performance, the award entered was still proper as it represented the value of the contract fully performed as proved by Erickson. The first issue to be resolved is whether Erickson substantially performed under the contract.

Under the doctrine of substantial performance, the general rule regarding building contracts is that a builder is not required to perform perfectly, but rather is only held to a duty of substantial performance in a workmanlike manner. (Brewer v. Custom Builders Corp. (1976), 42 Ill. App. 3d 668, 673, 356 N.E.2d 565.) A purchaser who receives substantial performance of the building contract must pay the price bargained for, less an offset for defects in what he received as compared to what strict performance would have given him. (Park v. Sohn (1982), 89 Ill. 2d 453, 464-65, 433 N.E.2 651; Mayfield v. Swafford (1982), 106 Ill. App. 3d 610, 612, 435 N.E.2d 953; Brewer v. Custom Builders Corp. (1976), 42 Ill. App. 3d 668, 673-74, 356 N.E.2d 565; Restatement (Second) of Contracts sec. 347 (1979).) A contractor whose work amounts to less than substantial performance may not recover on the contract. Under such circumstances, a contractor may recover under a quasi-contractual theory for the reasonable value of its services rendered less any damages suffered by the purchaser. (Brewer v. Custom Builders Corp. (1976), 42 Ill. App. 3d 668, 673, 356 N.E.2d 565; J. Calamari & J. Perillo, Contracts sec. 11 — 26, at 426-28 (2d ed. 1979).) The question of whether substantial performance has been given varies on the facts presented in each case. (Brewer v. Custom Builders Corp. (1976), 42 Ill. App. 3d 668, 673, 356 N.E.2d 565.) The trial court’s finding will not be disturbed on appeal unless the holding of the trial court is against the manifest weight of the evidence. V & V Cement Contractors, Inc. v. LaSalle National Bank (1983), 119 Ill. App. 3d 154,157, 456 N.E.2d 655.

Judgment was rendered for Erickson on its contract count, count II of its amended complaint, in the amount of $202,000, plus statutory-interest and costs. That count alleged C-K’s breach of contract for nonpayment and sought approximately $550,000 in damages, the value of the contract for Erickson’s full performance. The trial court found that while there existed defects in construction of the water slide they were insufficient in themselves to sustain a finding that the water slide was constructed in a “wholly unworkmanlike manner.” However, the court found that with respect to the selection of architects and in the subcontractor-bidding process, Erickson “wholly failed to perform.” Notwithstanding this conclusion, the court then went on to enter judgment on amended count II (the breach of contract).

C-K asserts that the finding of these deficiencies in Erickson’s performance by the trial court indicates that the trial court had concluded that Erickson had not substantially performed under the contract. Contrary to C-K’s contention, we believe that as the trial court had entered judgment on its contract count, the trial court necessarily found that Erickson had substantially performed under the contract. This conclusion is supported by the trial court’s dismissal of Erickson’s amended count V, which sought recovery on a noncontractual theory of recovery, quantum meruit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. U.S. Bank Trust, N.A.
2025 IL App (1st) 230439-U (Appellate Court of Illinois, 2025)
Bank of America, NA v. Narayana
2024 IL App (1st) 240628-U (Appellate Court of Illinois, 2024)
Advance Iron Works, Inc v. Schaefges Brothers, Inc
2022 IL App (1st) 201043-U (Appellate Court of Illinois, 2022)
Paliatka v. Bush
2018 IL App (1st) 172435 (Appellate Court of Illinois, 2018)
Peru Federal Savings Bank v. Weiden
2016 IL App (3d) 140205 (Appellate Court of Illinois, 2016)
CitiMortgage, Inc v. Parille
2016 IL App (2d) 150286 (Appellate Court of Illinois, 2016)
Cervac v. Littman (In re Littman)
517 B.R. 847 (N.D. Illinois, 2014)
Patrick Engineering, Inc. v. The City of Naperville
2012 IL 113148 (Illinois Supreme Court, 2012)
O'Rourke v. Palisades Acquisition Xvi, LLC
635 F.3d 938 (Seventh Circuit, 2011)
U.S. Neurosurgical, Inc. v. City of Chicago
572 F.3d 325 (Seventh Circuit, 2009)
O'Connor Construction Co. v. Belmont Harbor Home Development, LLC
909 N.E.2d 294 (Appellate Court of Illinois, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
477 N.E.2d 513, 132 Ill. App. 3d 260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-e-erickson-construction-inc-v-congress-kenilworth-corp-illappct-1985.