Advance Iron Works, Inc v. Schaefges Brothers, Inc

2022 IL App (1st) 201043-U
CourtAppellate Court of Illinois
DecidedJanuary 20, 2022
Docket1-20-1043
StatusUnpublished

This text of 2022 IL App (1st) 201043-U (Advance Iron Works, Inc v. Schaefges Brothers, Inc) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advance Iron Works, Inc v. Schaefges Brothers, Inc, 2022 IL App (1st) 201043-U (Ill. Ct. App. 2022).

Opinion

2022 IL App (1st) 201043-U No. 1-20-1043 Order filed January 20, 2022 Fourth Division

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________ IN THE APPELLATE COURT OF ILLINOIS FIRST DISTRICT ______________________________________________________________________________ ADVANCE IRON WORKS, INC., ) Appeal from the ) Circuit Court of Plaintiff and Counterdefendant-Appellant and ) Cook County. Cross-Appellee, ) ) v. ) No. 13 CH 21554 ) SCHAEFGES BROTHERS, INC., ) ) Honorable Defendant and Counterplaintiff-Appellee and ) Michael F. Otto, Cross-Appellant. ) Judge, presiding.

JUSTICE LAMPKIN delivered the judgment of the court. Presiding Justice Reyes and Justice Rochford concurred in the judgment.

ORDER

¶1 Held: (1) The jury’s verdict in favor of the general contractor on the subcontractor’s breach of contract claim was not against the manifest weight of the evidence, which showed that the general contractor had performed its obligations under the contract and the subcontractor breached the contract by failing to perform. (2) The jury’s verdict in favor of the subcontractor on the general contractor’s counterclaim for damages was not against the manifest weight of the evidence, which showed that the general contractor failed to prove the damages it sustained as a result of the subcontractor’s breach. No. 1-20-1043

¶2 This is an appeal and cross-appeal from a jury verdict in a breach of contract case that the

subcontractor, plaintiff/counterdefendant Advance Iron Works, Inc. (plaintiff), filed against the

general contractor, defendant/counterplaintiff Schaefges Brothers, Inc. (defendant). The jury

returned a verdict (1) in favor of defendant on plaintiff’s breach of contract claim, finding that

plaintiff had failed to perform under the contract, and (2) in favor of plaintiff on defendant’s

counterclaim for damages allegedly incurred by hiring replacement subcontractors. The trial court

entered judgment on the jury’s verdict.

¶3 On appeal, plaintiff argues that it is entitled to a new trial because the verdict is against the

manifest weight of the evidence. Plaintiff also argues that the trial court abused its discretion by

barring plaintiff’s expert witness from testifying against certain opinions of defendant’s expert and

excluding evidence regarding a contract provision between defendant and the owner of the project.

¶4 On cross-appeal, defendant argues that it is entitled to either a new trial or judgment in its

favor on its damages counterclaim because the jury’s verdict ignored defendant’s damages as

established by the evidence.

¶5 For the reasons that follow, we affirm the judgment of the circuit court.1

¶6 I. BACKGROUND

¶7 This dispute arose from a contract between plaintiff, a steel fabrication and erection

subcontractor, and defendant, the general contractor awarded a contract by the Chicago Park

1 In adherence with the requirements of Illinois Supreme Court Rule 352(a) (eff. July 1, 2018), this appeal has been resolved without oral argument upon the entry of a separate written order.

-2- No. 1-20-1043

District (Park District) to build two boathouse buildings. Under their signed written subcontract,

plaintiff agreed to detail, fabricate and erect the steel for the two buildings for $554,000, plus

compensation for changes or additions in the scope of work authorized in writing by defendant.

The architect had made several design changes that affected the steel work, and plaintiff sought a

price adjustment for the extra work. Plaintiff began a portion of the work while the parties tried to

negotiate the price adjustment. After several weeks, the parties failed to reach an agreement on the

price adjustment, and plaintiff informed defendant that plaintiff was placing a “hold” on

performing any additional work due to nonpayment of its invoices. Shortly thereafter, defendant

terminated the parties’ contract, stating that plaintiff failed to comply with the terms and

obligations of the contract and, therefore, was in material breach thereof. Defendant hired two

replacement subcontractors and completed the boathouse project.

¶8 In September 2013, plaintiff sued defendant, alleging defendant breached the parties’

contract by failing to pay for the work plaintiff performed under the contract, by interfering with

plaintiff’s ability to perform the remainder of the contract, and by terminating the contract without

proper cause. Plaintiff alleged it substantially performed under the parties’ contract. Plaintiff

further alleged it suffered damages in the amount of $234,161, which included $63,006 for work

performed prior to the termination of the contract, late payment charges of 2 percent per month,

and $171,155 for lost profits due to lost work production. Plaintiff alternatively raised a claim for

unjust enrichment against defendant where plaintiff performed work valued at $63,006 without

defendant providing compensation for that benefit.

-3- No. 1-20-1043

¶9 Defendant filed an answer, affirmative defenses and a counterclaim against plaintiff to

recover the damages defendant sustained when it incurred increased costs after it was forced to

hire replacement subcontractors. In its answer, defendant denied breaching the contract and

contended that it terminated plaintiff for nonperformance. Defendant raised the affirmative

defenses that plaintiff breached the contract by (1) failing to comply with its scope of work and

fabricate, furnish and install all required structural steel as required by the contract, (2) failing to

provide accurate and complete information in its change order requests, which delayed the

progress of the project and caused defendant to sustain monetary damages that otherwise would

not have been incurred, (3) failing to provide additional supporting information as requested by

defendant and the Park District, which was a condition precedent to the change order requests

being approved and which delayed the progress of the project and caused defendant to sustain

monetary damages, (4) failing to obey and respond to defendant’s directives, which established

milestone dates for the completion of plaintiff’s scope of work and delayed the progress of the

project and caused defendant to sustain damages, and (5) stopping work prior to September 1,

2012, which delayed the progress of the project and caused defendant to sustain damages.

¶ 10 In response, plaintiff denied defendant’s affirmative defenses and denied liability for any

of defendant’s alleged damages.

¶ 11 The parties tried their claims before a jury for nine days in November 2019, and

approximately seven of those days were devoted to testimony. The court and jury heard extensive

testimony from five witnesses on the contested factual issues. Hundreds of pages of project and

-4- No. 1-20-1043

post-project correspondence, documents, emails and standards were discussed before the jury, and

the majority of those documents were admitted into evidence.

¶ 12 The evidence presented to the jury showed that, on April 2, 2012, the Park District issued

for bidding architect drawings for a boathouse construction project to a select prequalified pool of

general contractors and subcontractors. Defendant solicited proposals from a series of trades,

including steel fabrication.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Palm v. 2800 Lake Shore Drive Condominium Assn'n
2013 IL 110505 (Illinois Supreme Court, 2013)
Mohanty v. St. John Heart Clinic, S.C.
866 N.E.2d 85 (Illinois Supreme Court, 2006)
Hollis v. R. Latoria Construction, Inc.
485 N.E.2d 4 (Illinois Supreme Court, 1985)
Knight v. Haydary
585 N.E.2d 243 (Appellate Court of Illinois, 1992)
W. E. Erickson Construction, Inc. v. Congress-Kenilworth Corp.
477 N.E.2d 513 (Appellate Court of Illinois, 1985)
Brooks v. City of Chicago
435 N.E.2d 1182 (Appellate Court of Illinois, 1982)
Lee v. Grand Trunk Western Railroad
492 N.E.2d 1364 (Appellate Court of Illinois, 1986)
Thornton v. GARCINI
928 N.E.2d 804 (Illinois Supreme Court, 2010)
Dubey v. Public Storage, Inc.
918 N.E.2d 265 (Appellate Court of Illinois, 2009)
Schuchman v. Stackable
555 N.E.2d 1012 (Appellate Court of Illinois, 1990)
Villa v. Crown Cork & Seal Co.
560 N.E.2d 969 (Appellate Court of Illinois, 1990)
Simmons v. Garces
763 N.E.2d 720 (Illinois Supreme Court, 2002)
In Re Marriage of Carpenter
677 N.E.2d 463 (Appellate Court of Illinois, 1997)
Finley v. New York Central Railroad
167 N.E.2d 212 (Illinois Supreme Court, 1960)
Tri-G, Inc. v. Burke, Bosselman & Weaver
856 N.E.2d 389 (Illinois Supreme Court, 2006)
Vacala v. Village of La Grange Park
636 N.E.2d 812 (Appellate Court of Illinois, 1994)
W.W. Vincent & Co. v. First Colony Life Insurance
814 N.E.2d 960 (Appellate Court of Illinois, 2004)
Mayfair Construction Co. v. Waveland Associates Phase I Limited Partnership
619 N.E.2d 144 (Appellate Court of Illinois, 1993)
Neibert v. Schwenn Agri-Production Corp.
579 N.E.2d 389 (Appellate Court of Illinois, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
2022 IL App (1st) 201043-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advance-iron-works-inc-v-schaefges-brothers-inc-illappct-2022.