O'Connor Construction Co. v. Belmont Harbor Home Development, LLC

909 N.E.2d 294, 391 Ill. App. 3d 533
CourtAppellate Court of Illinois
DecidedMay 19, 2009
Docket1-07-2346
StatusPublished
Cited by4 cases

This text of 909 N.E.2d 294 (O'Connor Construction Co. v. Belmont Harbor Home Development, LLC) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Connor Construction Co. v. Belmont Harbor Home Development, LLC, 909 N.E.2d 294, 391 Ill. App. 3d 533 (Ill. Ct. App. 2009).

Opinion

JUSTICE CUNNINGHAM

delivered the opinion of the court:

Plaintiff-appellant, O’Connor Construction Company, Incorporated (O’Connor), a subcontractor on the construction of a Chicago residential condominium building, appeals from the amount of damages it was awarded in April 2007, following a bench trial in the circuit court of Cook County on O’Connor’s first amended three-count complaint and from the denial of its posttrial petition for attorney fees. In the first count of the complaint O’Connor sought to foreclose on a mechanics lien against all defendants-appellees (all defendants). 1 The trial court awarded damages to O’Connor in the amount of $50,876.50 plus costs and interest of $16,585.74, calculated at the rate of 10% per annum. This amount was in addition to the $175,189.50 already paid to O’Connor by defendant Park Plaza for part of the work. The second count of the complaint sought damages for breach of contract against defendants-appellees Belmont Harbor Home Development, LLC (Belmont Harbor), and Park Plaza Construction, LLC (Park Plaza). The trial court found a breach of contract by Park Plaza and awarded O’Connor $50,876.50 plus costs and interest of $8,292.87, calculated at 5% per annum. This was the same preinterest amount awarded for count I, which foreclosed on a mechanics lien.

On appeal O’Connor asserts that it was entitled to an award of $179,804.94 for damages and interest on count I of its complaint for its mechanics lien foreclosure, and an award of $157,702.22 for damages and interest on count II of its complaint for breach of contact. Because the trial court found for O’Connor on its breach of contract claim asserted in count II, the trial court found that O’Connor’s alternative third count based on theories of quantum meruit and unjust enrichment was obviated, and so the court found for Belmont Harbor and Park Plaza on count III. O’Connor does not appeal from the ruling related to count III. O’Connor subsequently filed a posttrial motion and application for attorney fees plus costs pursuant to section 17 of the Mechanics Lien Act (Act) (770 ILCS 60/17 (West 1996)). The trial court refused to award attorney fees but did award fees and costs for mechanics-lien-related filings and recording fees, and costs for the witnesses who testified for O’Connor. On appeal, O’Connor contends that it was entitled to attorney fees of $49,450 based on a rate of $125 per hour.

O’Connor also contends that the trial court failed to apply the proper measure of damages for breach of contract by Park Plaza in relation to count II, because the trial court found that O’Connor had substantially performed its obligations under the contract. O’Connor further contends that the trial court abused its discretion in denying attorney fees permitted under the Act (770 ILCS 60/0.01 et seq. (West 1996)). O’Connor alleges that the trial court erroneously determined that defendant Park Plaza had a good-faith basis, although ultimately erroneous, for failing to make final payments to O’Connor under the contract. O’Connor asserts that this determination by the trial court resulted in a lower amount of damages awarded on counts I and II of the complaint.

We affirm the trial court’s determination that O’Connor should prevail on its mechanics lien and breach of contract counts and the award to O’Connor of its costs and fees related to the mechanics lien count. We also affirm the trial court’s findings regarding O’Connor’s alterative theories in count III. We vacate the remaining judgment of the trial court regarding the amount of damages and interest to be awarded to O’Connor on counts I and II, the mechanics lien and breach of contract claims. We further hold that the trial court’s outright rejection of O’Connor’s request for attorney fees was erroneous.

BACKGROUND

The relevant facts are recited in the unchallenged findings of fact of the trial court, as set out in its written judgment order. On November 1, 2001, Belmont Harbor, the owner of the property in question, through its managing partner, John McCauley, entered into a written contract with B2BilT, Inc. B2BilT was to be general contractor for the construction of a 7-story condominium building with 24 units (20 single units and 2 double units) at 508 West Melrose Street in Chicago. B2BilT subsequently contracted with O’Connor, for O’Connor to perform the “rough” carpentry and “finish” carpentry for the condominiums. According to the testimony of O’Connor employee Matthew O’Connor, the rough carpentry included roof blocking, window blocking, interior blocking, and installing windows and door bases. The finish or trim carpentry included installing wood trim in the common lobby areas on each floor and, in each unit, installing window extension jambs, interior and entry doors, cabinets, and wood trim.

When B2BilT went out of business in September 2002 during construction, Park Plaza was formed as a limited liability corporation to take its place. By assignment from B2BilT, Park Plaza assumed the duties of general contractor under the original general contract and also assumed B2BilT’s rights and obligations under the original contract with O’Connor, along with B2BilT’s rights and obligations under numerous contracts with other subcontractors. The trial court found that at the time of these assignments of contracts, the work was already behind schedule and that by allowing O’Connor to continue to perform and be paid for the work beyond the original completion date of November 1, 2002, the parties mutually waived that completion date.

John McCauley, the managing member of Belmont Harbor, admitted on cross-examination that Park Plaza, the successor general contractor, was required by the contract to supply the bulk of the materials for the work before O’Connor could perform. The original contract price quoted by O’Connor was $320,000 and the projected completion date for O’Connor’s work was November 1, 2002. As is customary in the industry, any additional work required by O’Connor would be authorized by the general contractor through change orders. Subsequently, 58 additional change orders were agreed to by the parties, increasing the total contract amount due to O’Connor from $320,000 to $351,989. The contract also specified that O’Connor would perform the carpentry work on a floor-by-floor basis. The owner of O’Connor, Timothy O’Connor, testified that he arrived at the original quoted contract price by determining that the cost of materials would be $10,200 and labor costs would be approximately $309,800.

As the work proceeded, O’Connor submitted eight applications for payment to Park Plaza and was paid what it requested, totaling $175,189.50. But in April 2003, Park Plaza instructed the subcontractors, including O’Connor, that the work would no longer be completed floor by floor, but instead the work on each unit would be completed as each unit was sold. By this time the rough carpentry for the building had been completed, so O’Connor began to trim, finish and complete the carpentry work in individual units as they were sold. Also, Park Plaza’s project manager, Kevin Bachman, testified that, based upon his observation of the completion of one unit by O’Connor, 50 hours were required to perform the finish carpentry work for each unit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Concrete Structures v. Clark
2023 IL App (1st) 230015-U (Appellate Court of Illinois, 2023)
CITY OF McHENRY v. Suvada
920 N.E.2d 1173 (Appellate Court of Illinois, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
909 N.E.2d 294, 391 Ill. App. 3d 533, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oconnor-construction-co-v-belmont-harbor-home-development-llc-illappct-2009.