Concrete Structures v. Clark

2023 IL App (1st) 230015-U
Appellate Court of Illinois·Decided December 6, 2023·No. 1-23-0015·Unpublished·Cited by 1 cases

Opinion

2023 IL App (1st) 230015-U THIRD DIVISION

December 6, 2023

No. 1-23-0015

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

IN THE

APPELLATE COURT OF ILLINOIS FIRST DISTRICT

CONCRETE STRUCTURES/SACHI, J.V., CONCRETE ) Appeal from the Circuit Court STRUCTURES OF THE MIDWEST, INC., and SACHI ) of Cook County. CONSTRUCTION, INC., )

)

Plaintiffs-Appellants, )

)

v. ) No. 2017 CH 13778 )

CLARK/BULLEY/OVC/POWER, PRAIRIE DISTICT 3 ) PARTNERS, METROPOLITAN PIER AND ) EXPOSITION AUTHORITY, CLARK ) CONSTRUCTION GROUP, LLC, et al., ) Honorable ) Anthony C. Kyriakopoulos, Defendants-Appellees. ) Judge Presiding.

JUSTICE R. VAN TINE delivered the judgment of the court.

Presiding Justice Reyes and Justice D.B. Walker concurred in the judgment.

ORDER

¶1 Held: We affirm the circuit court’s denial of prejudgment interest and attorney fees where the request for those was premised on plaintiff’s execution of a public lien.

¶2 This construction dispute arises from a general contractor’s failure to compensate a subcontractor for concrete work that the subcontractor performed for the construction of a large hotel connected to Chicago’s McCormick Place convention center. The construction project was funded by a local government entity existing under the laws of the state of Illinois. After the general contractor ignored multiple requests for payment from the subcontractor, the subcontractor recorded a public lien in the amount outstanding against the general contractor, local government entity, and other parties, and filed suit against them shortly thereafter. The circuit court ordered arbitration. At arbitration, the panel awarded the subcontractor the amount outstanding on the invoice along with other compensation, and found that the subcontractor was the prevailing party. The circuit court affirmed this award. Subsequently, the subcontractor requested the circuit court to grant it prejudgment interest and attorney fees. The circuit court denied this request. On appeal, the subcontractor argues that the court erred in denying the request because section 23 of the Mechanics Lien Act (Act) (770 ILCS 60/23 (West 2022)) allows prejudgment interest and attorney fees on public liens. For the following reasons, we affirm the circuit court’s judgment.

¶3 BACKGROUND

¶4 In January 2015, the Metropolitan Pier and Exposition Authority (MPEA), a local government entity, contracted with Prairie District 3 Partners (PD3) to design and build a 41-story hotel on land owned by MPEA. PD3 hired Clark/Bulley/OVC/Power (CBOP) to act as general contractor for the project. In June 2015, CBOP contracted with Concrete Structures/Sachi, J.V. (Concrete Structures) to perform concrete work on the project.

¶5 CBOP did not pay Concrete Structures for its work. After multiple unsuccessful payment demands, Concrete Structures served a mechanics lien in the amount of $9,247,203 against the hotel project, MPEA, PD3, and CBOP, pursuant to section 23 of the Act. Within 90 days, Concrete

Structures filed a four-count complaint against those parties and others. Count I requested an accounting under section 23 of the Act; count II alleged a breach of contract claim against CBOP; count III asserted a bond claim against Concrete Structures’ insurers; and count IV alleged an unjust enrichment claim against MPEA, PD3, CBOP, and those parties’ joint venturers. Pursuant to the arbitration clause in its contract with Concrete Structures, CBOP moved to compel arbitration on counts II and IV. The circuit court granted CBOP’s motion and stayed counts I and III pending arbitration.

¶6 The matter proceeded to arbitration before a three-member panel of the American Arbitration Association. By that time, CBOP had paid the subcontract balance down to $2,178,720. However, Concrete Structures requested more than $28,000,000 in damages, which included the outstanding balance, plus approximately $10,000,000 in labor productivity damages and increased subcontractor costs, among others. CBOP counterclaimed more than $3,500,000 in damages due primarily to the extended duration of the concrete work. The arbitration panel issued Concrete Structures an interim award of $10,629,741, which included the outstanding balance and $6,448,344 in labor productivity damages. The panel also awarded damages incurred due to extended project hours and other delays. The panel did not award CBOP any damages.

¶7 In its final arbitration decision, the panel awarded Concrete Structures $27,026.75 in attorney fees, which was only a fraction of what Concrete Structures requested, reasoning that most of Concrete Structures’ attorney fees were paid by CBOP’s insurance carrier. It also awarded Concrete Structures 5% prejudgment interest for the period of time between the issuance of the interim award and the final award. Thus, the final award amounted to $10,656,767.75 plus 5% interest.

¶8 Concrete Structures filed a motion to confirm the arbitration award, which the circuit court granted. CBOP paid Concrete Structures the arbitration award in full. Concrete Structures, CBOP, and MPEA then filed cross-motions for summary judgment on counts I (accounting pursuant to section 23 of the Act) and III (payment bond claim against Concrete Structures’ insurers), both of which the circuit court had stayed pending arbitration. The court denied Concrete Structures’ motion for summary judgment, declined to award it further prejudgment interest and attorney fees, and granted CBOP’s and MPEA’s motions as to both counts. However, count III remains pending in the circuit court because Concrete Structures filed a motion to reconsider the grant of summary judgment. The court’s order included Rule 304(a) (eff. Mar. 8, 2016) language, which allowed Concrete Structures to appeal the summary judgment ruling as to count I.

¶9 Because CBOP already paid the entirety of the arbitration award, the sole question before us is whether the circuit court erred in its refusal to award Concrete Structures prejudgment interest and attorney fees under section 23 of the Act.

¶ 10 ANALYSIS

¶ 11 On appeal, Concrete Structures argues that the circuit court erred in refusing to consider and award prejudgment interest and attorney fees. Concrete Structures contends that section 23 of the Act, which deals with public liens, permits an award of prejudgment interest and attorney fees. Defendants argue that section 23 does not allow prejudgment interest and attorney fees, as it is the only section of the Act that applies to public liens, and it does not mention prejudgment interest and attorney fees.

¶ 12 Summary judgment is appropriate only when the pleadings, depositions, and affidavits show that there is no genuine issue of material fact. 735 ILCS 5/2-1005(c) (West 2022); Onsen v. Commonwealth Edison Co., 261 Ill. App. 3d 271, 272 (1994). Summary judgment is proper when

the parties agree on the material facts, but disagree on the correct construction of a statute. Onsen, 261 Ill. App. 3d at 272. We review the circuit court’s grant of summary judgment de novo. Construction Systems, Inc. v. FagelHaber, LLC, 2019 IL App (1st) 172430, ¶ 21 (citing Williams v. Manchester, 228 Ill. 2d 404, 417 (2008)). De novo review means we engage in the same analysis as the circuit court. Pan v. King, 2022 IL App (1st) 211482, ¶ 16.

¶ 13 Section 1(a) of the Act reads, in relevant part:

Free access — add to your briefcase to read the full text and ask questions with AI

Concrete Structures v. Clark, 2023 IL App (1st) 230015-U (Ill. Ct. App. 2023).

2023 IL App (1st) 230015-U (Concrete Structures v. Clark) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Concrete Structures/Sachi, J.V. v. Clark/Bulley/OVC/Power
2024 IL App (1st) 240082 (Appellate Court of Illinois, 2024)