Concrete Structures v. Clark

2023 IL App (1st) 230015-U
CourtAppellate Court of Illinois
DecidedDecember 6, 2023
Docket1-23-0015
StatusUnpublished
Cited by1 cases

This text of 2023 IL App (1st) 230015-U (Concrete Structures v. Clark) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Concrete Structures v. Clark, 2023 IL App (1st) 230015-U (Ill. Ct. App. 2023).

Opinion

2023 IL App (1st) 230015-U THIRD DIVISION December 6, 2023 No. 1-23-0015

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________

IN THE APPELLATE COURT OF ILLINOIS FIRST DISTRICT ______________________________________________________________________________ CONCRETE STRUCTURES/SACHI, J.V., CONCRETE ) Appeal from the Circuit Court STRUCTURES OF THE MIDWEST, INC., and SACHI ) of Cook County. CONSTRUCTION, INC., ) ) Plaintiffs-Appellants, ) ) v. ) No. 2017 CH 13778 ) CLARK/BULLEY/OVC/POWER, PRAIRIE DISTICT 3 ) PARTNERS, METROPOLITAN PIER AND ) EXPOSITION AUTHORITY, CLARK ) CONSTRUCTION GROUP, LLC, et al., ) Honorable ) Anthony C. Kyriakopoulos, Defendants-Appellees. ) Judge Presiding.

JUSTICE R. VAN TINE delivered the judgment of the court. Presiding Justice Reyes and Justice D.B. Walker concurred in the judgment.

ORDER

¶1 Held: We affirm the circuit court’s denial of prejudgment interest and attorney fees where the request for those was premised on plaintiff’s execution of a public lien. 1-23-0015

¶2 This construction dispute arises from a general contractor’s failure to compensate a

subcontractor for concrete work that the subcontractor performed for the construction of a large

hotel connected to Chicago’s McCormick Place convention center. The construction project was

funded by a local government entity existing under the laws of the state of Illinois. After the general

contractor ignored multiple requests for payment from the subcontractor, the subcontractor

recorded a public lien in the amount outstanding against the general contractor, local government

entity, and other parties, and filed suit against them shortly thereafter. The circuit court ordered

arbitration. At arbitration, the panel awarded the subcontractor the amount outstanding on the

invoice along with other compensation, and found that the subcontractor was the prevailing party.

The circuit court affirmed this award. Subsequently, the subcontractor requested the circuit court

to grant it prejudgment interest and attorney fees. The circuit court denied this request. On appeal,

the subcontractor argues that the court erred in denying the request because section 23 of the

Mechanics Lien Act (Act) (770 ILCS 60/23 (West 2022)) allows prejudgment interest and attorney

fees on public liens. For the following reasons, we affirm the circuit court’s judgment.

¶3 BACKGROUND

¶4 In January 2015, the Metropolitan Pier and Exposition Authority (MPEA), a local

government entity, contracted with Prairie District 3 Partners (PD3) to design and build a 41-story

hotel on land owned by MPEA. PD3 hired Clark/Bulley/OVC/Power (CBOP) to act as general

contractor for the project. In June 2015, CBOP contracted with Concrete Structures/Sachi, J.V.

(Concrete Structures) to perform concrete work on the project.

¶5 CBOP did not pay Concrete Structures for its work. After multiple unsuccessful payment

demands, Concrete Structures served a mechanics lien in the amount of $9,247,203 against the

hotel project, MPEA, PD3, and CBOP, pursuant to section 23 of the Act. Within 90 days, Concrete

2 1-23-0015

Structures filed a four-count complaint against those parties and others. Count I requested an

accounting under section 23 of the Act; count II alleged a breach of contract claim against CBOP;

count III asserted a bond claim against Concrete Structures’ insurers; and count IV alleged an

unjust enrichment claim against MPEA, PD3, CBOP, and those parties’ joint venturers. Pursuant

to the arbitration clause in its contract with Concrete Structures, CBOP moved to compel

arbitration on counts II and IV. The circuit court granted CBOP’s motion and stayed counts I and

III pending arbitration.

¶6 The matter proceeded to arbitration before a three-member panel of the American

Arbitration Association. By that time, CBOP had paid the subcontract balance down to $2,178,720.

However, Concrete Structures requested more than $28,000,000 in damages, which included the

outstanding balance, plus approximately $10,000,000 in labor productivity damages and increased

subcontractor costs, among others. CBOP counterclaimed more than $3,500,000 in damages due

primarily to the extended duration of the concrete work. The arbitration panel issued Concrete

Structures an interim award of $10,629,741, which included the outstanding balance and

$6,448,344 in labor productivity damages. The panel also awarded damages incurred due to

extended project hours and other delays. The panel did not award CBOP any damages.

¶7 In its final arbitration decision, the panel awarded Concrete Structures $27,026.75 in

attorney fees, which was only a fraction of what Concrete Structures requested, reasoning that

most of Concrete Structures’ attorney fees were paid by CBOP’s insurance carrier. It also awarded

Concrete Structures 5% prejudgment interest for the period of time between the issuance of the

interim award and the final award. Thus, the final award amounted to $10,656,767.75 plus 5%

interest.

3 1-23-0015

¶8 Concrete Structures filed a motion to confirm the arbitration award, which the circuit court

granted. CBOP paid Concrete Structures the arbitration award in full. Concrete Structures, CBOP,

and MPEA then filed cross-motions for summary judgment on counts I (accounting pursuant to

section 23 of the Act) and III (payment bond claim against Concrete Structures’ insurers), both of

which the circuit court had stayed pending arbitration. The court denied Concrete Structures’

motion for summary judgment, declined to award it further prejudgment interest and attorney fees,

and granted CBOP’s and MPEA’s motions as to both counts. However, count III remains pending

in the circuit court because Concrete Structures filed a motion to reconsider the grant of summary

judgment. The court’s order included Rule 304(a) (eff. Mar. 8, 2016) language, which allowed

Concrete Structures to appeal the summary judgment ruling as to count I.

¶9 Because CBOP already paid the entirety of the arbitration award, the sole question before

us is whether the circuit court erred in its refusal to award Concrete Structures prejudgment interest

and attorney fees under section 23 of the Act.

¶ 10 ANALYSIS

¶ 11 On appeal, Concrete Structures argues that the circuit court erred in refusing to consider

and award prejudgment interest and attorney fees. Concrete Structures contends that section 23 of

the Act, which deals with public liens, permits an award of prejudgment interest and attorney fees.

Defendants argue that section 23 does not allow prejudgment interest and attorney fees, as it is the

only section of the Act that applies to public liens, and it does not mention prejudgment interest

and attorney fees.

¶ 12 Summary judgment is appropriate only when the pleadings, depositions, and affidavits

show that there is no genuine issue of material fact. 735 ILCS 5/2-1005(c) (West 2022); Onsen v.

Commonwealth Edison Co., 261 Ill. App. 3d 271, 272 (1994). Summary judgment is proper when

4 1-23-0015

the parties agree on the material facts, but disagree on the correct construction of a statute. Onsen,

261 Ill. App. 3d at 272.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Concrete Structures/Sachi, J.V. v. Clark/Bulley/OVC/Power
2024 IL App (1st) 240082 (Appellate Court of Illinois, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
2023 IL App (1st) 230015-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/concrete-structures-v-clark-illappct-2023.