Anderson "Safeway" Guard Rail Corp. v. Champaign Asphalt Co.

266 N.E.2d 414, 131 Ill. App. 2d 924, 1971 Ill. App. LEXIS 1374
CourtAppellate Court of Illinois
DecidedFebruary 2, 1971
Docket11243
StatusPublished
Cited by26 cases

This text of 266 N.E.2d 414 (Anderson "Safeway" Guard Rail Corp. v. Champaign Asphalt Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anderson "Safeway" Guard Rail Corp. v. Champaign Asphalt Co., 266 N.E.2d 414, 131 Ill. App. 2d 924, 1971 Ill. App. LEXIS 1374 (Ill. Ct. App. 1971).

Opinion

Mr. JUSTICE CRAVEN

delivered the opinion of the court:

This is a consolidation of two separate actions by a material supplier of a subcontractor for an accounting of sums due plaintiff, for a decree that the subcontractor pay the sums due, and for declaration of a lien for such sums upon money, bonds or warrants of the Department of Public Works and Buildings of the State of Illinois allegedly due general contractors for public highway construction.

The trial court granted the motion for summary judgment of defendant, Champaign Asphalt Company, a general contractor, against the material supplier, and found no just reason for delay or enforcement or appeal therefrom. Appeal is taken from the summary judgment order.

Plaintiff, Anderson “Safeway” Guard Rail Corporation, the material suppher, alleged in one action that it orally agreed to supply defendant, A. K. Thompson Engineering Corporation, a subcontractor of Champaign Asphalt, and Frank C. Feutz Co., general contractors, with such steel beam guard rail and accessories as would be required in interstate highway construction let by the Illinois Department of Pubhc Works and Buildings to the general contractors and referred to as Project 89. Plaintiff claimed that it furnished such guard rails and accessories valued at $12,217.55 but was not paid for the same. Plaintiff further alleged that it filed and served a notice of hen with the Director of the Illinois Department of Pubhc Works and Buildings against moneys, bonds and warrants due or to become due Champaign Asphalt and Feutz in connection with such highway construction, and that at the time of service of said notice the State had in its possession a part of the moneys due the general contractor under its contract in an amount unknown to plaintiff.

The second action was identical, except that it was against an additional defendant, Lehigh Paving Company, as an’ additional general contractor, on a different portion of highway construction referred to as Project 87. This suit claimed $3500, exclusive of interest and costs, was due.

The actions were consolidated. Champaign Asphalt Company filed a motion for summary judgment on the ground that it had paid its subcontractor, A. K. Thompson Engineering Corporation, in full for all guard rails and accessories supplied by plaintiff before the notice of hen was filed. Defendant contends that the hen of a material suppher to a subcontractor, under Illinois Revised Statutes, 1969, ch. 82, par. 23, against pubhc moneys due or to become due a general contractor under an Illinois pubhc contract is limited to the amount owed by the general contractor to the subcontractor at the time the notice of hen is filed.

Defendant’s motion for summary judgment was supported by affidavits of Paul W. Mast, office manager of Dwight Shoemaker Bridge Company, a subsidiary of Champaign Asphalt Company, stating that the general contractor had completed its payments to its subcontractor by March 13, 1969. The notices of hen were dated and served on the Department on April 10, 1969. This affiant further stated that no moneys were due from the State on April 10, 1969, or later became due in connection with any portion of the general contractor’s construction contract, subcontracted to the subcontractor, Thompson, to whom plaintiff supplied the materials. Attached to the affidavits were cancelled checks of Shoemaker Bridge Company paid on behalf of Champaign Asphalt Company and invoices of Thompson. The affidavit further stated that the invoices constituted a “full and complete biffing” by Thompson “for all obligations including the furnishing and installation of steel beam guard rail and accessories required of A. K. Thompson under the above subcontract.” It further stated that Champaign Asphalt did not contract with plaintiff or in any way agree to pay plaintiff, and that no moneys were due or about to become due on April 10, 1969, from the State of Illinois to Champaign Asphalt or Dwight for the portion of Champaign Asphalt’s contract with Thompson.

Plaintiff’s complaints were verified. By counter-affidavit, plaintiff’s attorney stated that the verified complaints were made on personal knowledge of William E. Behm who verified them, and that Behm, if sworn as a witness, could and would testify completely to the facts therein stated. The counter-affidavit further stated that certain material facts were known only to A. K. Thompson Engineering Corporation and Frank C. Feutz Co., the affidavits of officers of which the affiant was unable to procure by reason of the hostility of said persons toward plaintiff. It further stated that plaintiff verily believed that, if sworn, such officers would testify that A. K. Thompson Engineering Corporation had not been paid in full for its work with the general contractors to an amount exceeding the sums for which hen was claimed.

Summary judgments are authorized to be granted by a court under the Illinois Civil Practice Act in a case upon motion made therefor by one of the parties if the pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law. (Ill. Rev. Stat. 1969, ch. 110, par. 57.) Such judgments are favored where the issues involved are simple in nature and the legal consequences of settled facts are conclusive. The entry of such judgment, in a proper case, has the salutary effect also of diminishing congestion of trial calendars and reducing expense to the community and the litigants of unnecessary trials. Allen v. Meyer (1958), 14 Ill.2d 284,152 N.E.2d 576.

Where a genuine issue of material fact exists, summary judgment is not proper. However, merely alleging the existence of an issue of material fact does not create such an issue. Giampa v. Sunbeam Corp. (1st Dist. 1966), 68 Ill.App.2d 425,216 N.E.2d 233.

In this case, there was no allegation in the complaint that the general contractor owed any moneys to its subcontractor on the work for which plaintiff supplied material at the time the notice of hen was served on the State.

The issue of law in this case was decided in Koenig v. McCarthy Constr. Co. (2nd Dist. 1951), 344 Ill.App, 93, 100 N.E.2d 338, and reiterated in Tison & Hall Concrete Products Co. v. A. E. Asher, Inc. (5th Dist. 1967), 86 Ill.App.2d 34, 229 N.E.2d 137. We see no reason to differ with the rule so decided. A supplier of materials to a subcontractor of a general contractor is limited by the statute to a lien on public funds in the possession of the State in the amount owed by the general contractor to the subcontractor on the particular portion of the contract for which the supplier furnished materials at the time notice is given to the State of his claim for lien. To hold otherwise “would be tantamount to imposing a limitless liability upon the original contractor for public improvements, for he would be liable for all the financial follies, and excessive contracts entered into by his subcontractors * * *." Koenig, supra, 100 N.E.2d at 342.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Concrete Structures v. Clark
2023 IL App (1st) 230015-U (Appellate Court of Illinois, 2023)
Speedy Gonzalez Landscaping, Inc. v. O.C.A. Construction, Inc.
896 N.E.2d 494 (Appellate Court of Illinois, 2008)
Chandler v. Doherty
Appellate Court of Illinois, 1998
In Re Petroleum Piping Contractors, Inc.
211 B.R. 290 (N.D. Indiana, 1997)
People ex rel. Adams Electrical Cooperative v. Village of Camp Point
286 Ill. App. 3d 247 (Appellate Court of Illinois, 1997)
Outboard Marine Corp. v. Liberty Mutual Insurance
607 N.E.2d 1204 (Illinois Supreme Court, 1992)
Aluma Systems, Inc. v. Frederick Quinn Corp.
564 N.E.2d 1280 (Appellate Court of Illinois, 1990)
J&W Allen Construction Co. v. Kramer
41 Ill. Ct. Cl. 133 (Court of Claims of Illinois, 1989)
Streams Club, Ltd. v. Thompson
536 N.E.2d 459 (Appellate Court of Illinois, 1989)
Guyton v. Roundy
477 N.E.2d 1266 (Appellate Court of Illinois, 1985)
Schroeder v. Reddick Fumigants, Inc.
471 N.E.2d 621 (Appellate Court of Illinois, 1984)
Mouhelis v. Thomas
419 N.E.2d 956 (Appellate Court of Illinois, 1981)
Stephens v. Northern Indiana Public Service Co.
409 N.E.2d 423 (Appellate Court of Illinois, 1980)
Cantu v. Utility Dynamics Corp.
387 N.E.2d 990 (Appellate Court of Illinois, 1979)
Kubisen v. Chicago Health Clubs
388 N.E.2d 44 (Appellate Court of Illinois, 1979)
Wicks v. Bank of Belleville
371 N.E.2d 1007 (Appellate Court of Illinois, 1977)
Witek v. Leisure Technology Midwest, Inc.
350 N.E.2d 242 (Appellate Court of Illinois, 1976)
Smith v. Ashley
332 N.E.2d 32 (Appellate Court of Illinois, 1975)
Windlow v. Wagner
329 N.E.2d 911 (Appellate Court of Illinois, 1975)
Hennepin Public Water District v. Petersen Construction Co.
297 N.E.2d 131 (Illinois Supreme Court, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
266 N.E.2d 414, 131 Ill. App. 2d 924, 1971 Ill. App. LEXIS 1374, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anderson-safeway-guard-rail-corp-v-champaign-asphalt-co-illappct-1971.