Hennepin Public Water District v. Petersen Construction Co.

297 N.E.2d 131, 54 Ill. 2d 327, 1973 Ill. LEXIS 345
CourtIllinois Supreme Court
DecidedJune 4, 1973
Docket44543
StatusPublished

This text of 297 N.E.2d 131 (Hennepin Public Water District v. Petersen Construction Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hennepin Public Water District v. Petersen Construction Co., 297 N.E.2d 131, 54 Ill. 2d 327, 1973 Ill. LEXIS 345 (Ill. 1973).

Opinion

MR. JUSTICE WARD

delivered the opinion of the court:

The plaintiff, Hennepin Public Water District, brought an action in the circuit court of Putnam County for liquidated damages in the amount of $24,610.25 against the defendants, Petersen Construction Co. (hereafter, Petersen) and the Continental Casualty Co. (hereafter, Continental). The suit was based on a bid bond which had been submitted by Petersen as the principal and Continental as the surety when Petersen had bid on two construction projects announced by the plaintiff. After answering the complaint, Continental filed a third-party action against Petersen, seeking indemnity for any damages Continental might incur as a result of the plaintiff’s suit. The case was tried before a jury and a verdict was returned on the principal action in favor of Petersen and Continental. The jury did not return a verdict in the third-party action by Continental against Petersen but the trial court, acting upon Continental’s post-trial motion for attorneys’ fees and other expenses incurred by Continental in its defense of the plaintiff’s action, entered a judgment against Petersen in the amount of $3,058.70. The appellate court affirmed the judgments of the trial court upon appeals by the plaintiff and by Petersen from the judgment in favor of Continental. 131 Ill. App. 2d 927.

In 1966 the plaintiff advertised for bids on two construction projects. The first project involved the construction of a sewage treatment plant and the second the construction of well equipment and an administration building. Petersen submitted bids on both projects to the plaintiff on July 28, 1966, which was the last date on which bids might be submitted. Petersen’s bid on the first project was in the amount of $383,365 and on the second project was $108,840. The bid forms used were part of a single volume of documents furnished by the plaintiff and referred to as the contract documents. The contract documents were in three parts: the proposal section, the agreement section and the contract specifications. The proposal section included forms which were to be used by the bidder to state the amount of its bid. Petersen completed the proposal forms and returned the contract documents to the plaintiff. It accompanied its bid with a bid bond, with Continental as the surety, representing 5% of the bid submitted. The bids were opened on July 28, 1966, and Petersen’s bids were the lowest received on each of the construction projects.

The proposal provided that the successful bidder within 10 days after the awarding of the contract was to execute certain agreement forms in the proposal section of the contract documents and was to furnish a performance bond. These agreement forms would have been filled in by the plaintiff prior to their being executed by the successful bidder. The proposal stated that the bidder, upon his failure or refusal to execute and deliver the contract and submit performance bond within the 10 days, would forfeit to the plaintiff as liquidated damages the security deposited with the bid. The plaintiff’s action against Petersen and Continental was grounded on this provision of the proposal and claimed a failure to execute the agreement and furnish the bond.

The proposal section included the following provisions:

“Financing Improvements—
The Owner proposes to complete financing arrangements for this improvement within a period of sixty (60) days after construction bids are received. The bid securities of all bidders, except the security submitted with the lowest acceptable bid, will be returned within a fifteen (15) day period following the time of receipt of the bids. The bid security accompanying the lowest acceptable Proposal will be returned on request after the Owner has made a conditional award to the successful bidder if a satisfactory Performance Bond has been delivered to the Owner. The conditional award will not be in effect until the Owner has been successful in raising the required funds for payment of construction. Provided it proves impossible to raise the required funds, the conditional award will be cancelled by the Owner and the Owner shall not then be liable for any payments whatsoever to the Contractor. Extension of time beyond the sixty (60) day period of the conditional award may be made only by mutual agreement between the Owner, the Contractor and the Contractor’s Surety.”
“Construction Funds—
The Hennepin Public Water District proposes to complete the sale of water and sewer revenue bonds to finance this project within a period of sixty (60) days after construction bids are received. Provided it proves impossible to raise the required funds to finance this project, the conditional award will be cancelled by the Hennepin Public Water District and the District shall not then be liable for any payments whatsoever to the Contractor. Extension of time beyond the 60 day period of the conditional award may be made only by mutual agreement between the Owner, the Contractor and the Contractor’s Surety.”

The plaintiff notified Petersen of the tentative award to it of the contract on the first project on September 7, 1966, and of the tentative award on the second project on September 26, 1966. However, the agreement forms, completed by the plaintiff, were not tendered or delivered to Petersen for execution until October 3, 1966, which was 67 days after the date, July 28, on which all bids were required to have been received. On September 26, 1966, which was the 60th day after all bids had been received, the plaintiff completed its financing arrangements for the projects when it concluded the sale of bonds it had issued to finance the construction.

We consider that the appellate court in affirming the judgment in favor of Petersen and Continental against the plaintiff correctly interpreted the intention of the parties as expressed in the contract documents.

The provisions “Financing Improvements” and “Construction Funds” appearing in the proposal section expressly state the intention of the plaintiff that its financing arrangements for the construction would be completed within 60 days after the bids had been received, that is, within 60 days after July 28. As the appellate court observed, the two provisions contemplated and proposed that the awards of the contracts were to be made prior to the expiration of this 60-day period. Language in both provisions provides for the cancellation by the plaintiff, without liability, of the conditional awards should it be impossible for the plaintiff to raise the funds required for financing within 60 days, evidencing that the awards were to be made within the 60-day period. Too, the “Financing Improvements” provision, which is devoted to the 60 days allowed the plaintiff to complete its financing, calls for the return of the bid security to the successful bidder when the bidder has furnished a performance bond. This indicates the contemplation of the awarding of the contracts within the 60-day period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson "Safeway" Guard Rail Corp. v. Champaign Asphalt Co.
266 N.E.2d 414 (Appellate Court of Illinois, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
297 N.E.2d 131, 54 Ill. 2d 327, 1973 Ill. LEXIS 345, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hennepin-public-water-district-v-petersen-construction-co-ill-1973.