Alexander Lumber Co. v. Coberg

190 N.E. 99, 356 Ill. 49
CourtIllinois Supreme Court
DecidedFebruary 23, 1934
DocketNo. 21944. Reversed and remanded.
StatusPublished
Cited by21 cases

This text of 190 N.E. 99 (Alexander Lumber Co. v. Coberg) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alexander Lumber Co. v. Coberg, 190 N.E. 99, 356 Ill. 49 (Ill. 1934).

Opinion

Mr. Chief Justice Orr

delivered the opinion of the court:

This case requires us to construe section 23 of the Mechanic’s Lien act, and is here by reason of a certificate of importance granted by the Appellate Court for the Second District.

The pertinent facts as found by the master in chancery and approved by the circuit court of DuPage county and the Appellate Court are not in dispute.

In April, 1928, the board of education of school district No. 46, DuPage county, entered into a written contract with the appellant, John C. Coberg, for the construction of a building referred to as the Washington school for the sum of $93,810. In July, 1928, the same board entered into another written contract with appellant for the erection of a second building, known as the Hawthorne school, for the sum of $27,275. The contracts provided that appellant should provide all work, including labor and all material for the masonry, carpentry, roofing, sheet metal, lathing, plastering, painting and glazing. In the same month appellant by verbal contract sub-let a portion of the contract for the Hawthorne school to W. C. McDonald, who agreed to furnish all labor and material for carpenter work, for caulking of windows, and glass, and to furnish black-boards, for a consideration of $7950. McDonald abandoned his contract in February, 1929, and the work was subsequently finished by appellant, who had overpaid McDonald under his contract. In July, 1928, McDonald entered into a verbal contract with appellee the Plammerschmidt & Franzen Company for the required millwork at an agreed price of $2050. The material called for under this contract was manufactured, delivered to and incorporated in the Hawthorne building during January, 1929. The contract price for this material lacked $1433.33 °f being paid in its entirety. In September, 1929, the company served a notice of claim for lien on the funds remaining ip possession of the school board. This notice was addressed to the school board and served upon its secretary. At that time the school board retained a balance of $2062.17 due upon the contract of appellant for the erection of the Hawthorne school.

In May, 1928, appellant by written contract sub-let to McDonald a portion of the contract for construction of the Washington school. McDonald agreed to furnish all material and perform all work, including the carpentry work, black-boards, cork-boards, glass, glazing and rough hardware, in accordance with a contract between appellant and the school board, for the consideration of $22,035. McDonald abandoned this work in February, 1929, and it was subsequently finished by appellant, who had overpaid McDonald under his contract. In May, 1928, McDonald entered into a verbal contract with appellee the Alexander Lumber Company for the building materials needed in both the Washington and Hawthorne schools. Material was delivered under this contract for the Washington school, starting in September, 1928, and ending in February, 1929. The agreed price for this material, all of which was used in the building, was $42,602.28. ■ On this contract there is now due the Alexander Lumber Company the sum of $1583.62. Delivery under McDonald’s contract to the Hawthorne school started in October, 1928, and ended in February, 1929. The agreed price for this material, all used in the building, was $1381.72. On this contract there is now due the Alexander Lumber Company the sum of $565-05.

In February and September, 1929, the Alexander Lumber Company served notices of claims for liens on funds in possession of the school board remaining unpaid to appellant or McDonald for the construction of the Washington and the Hawthorne schools. The notices were addressed to the board and served upon it by delivering copies to its secretary. In September, 1929, the board had in its possession a balance of $1869.46 due appellant on the Washington school contract and $2062.17 due him on the Hawthorne school contract. Subsequent to February 5, 1929, appellant verbally promised to pay for the material delivered by the Alexander Lumber Company to McDonald. That promise was subsequent to the delivery of all of the material by that company for both schools. The consideration for this verbal promise was that the Alexander Lumber Company would take no further steps for the enforcement of its claim of lien against the funds then remaining in the hands of the school board and due appellant. The master found that the Alexander Lumber Company was entitled to recover from appellant the balances due for materials to construct the two schools, but that the trial court had no jurisdiction in the present proceeding to enter a personal judgment against appellant for the sum of those balances.

The Alexander Lumber Company filed its bill of complaint in September, 1929, against appellant seeking to enforce its claim of lien. The Hammerschmidt & Franzen Company by leave of court intervened. Appellant answered the original bill of complaint and the intervening petition, saying that the Alexander Lumber Company was not entitled to a lien upon the funds in possession of the school board because the statutes of this State do not give to a person furnishing materials to a sub-contractor a lien upon funds due to the contractor. The school board filed a petition in the nature of a bill of interpleader and was allowed to turn the sum of $3931.63 into court and be dismissed from the action. The trial court sustained the master’s report and entered a decree dismissing the bill for want of equity and directed that the money deposited in court by the school board be paid to appellant. The Appellate Court, on appeal, reversed the decree of the trial court, with directions to it to enter a decree holding that the two appellee companies were entitled to a lien upon'the moneys to the extent of their respective proved claims.

The pertinent part of section 23 is: “Any person who shall furnish material, apparatus, fixtures, machinery or labor to any contractor having a contract for public improvement for any county, township, school district, city or municipality in this State, shall have a lien on the money, bonds or warrants due or to become due such contractor under such contract: Provided, such person shall, before payment or delivery thereof is made to such contractor, notify the official or officials of the county, township, school district, city or municipality whose duty it is to pay such contractor of his claim by a written notice: And, provided further, that such lien shall attach only to that portion of such money, bonds or warrants against which no voucher or other evidence of indebtedness has been issued and delivered to the contractor by or on behalf of the county, township, school district, city or municipality as the case may be at the time of such notice.” In construing this section it is the duty of the court to ascertain the legislative intent, (Decatur Lumber Co. v. Crail, 350 Ill. 319,) and in so doing we must accept the plain language of the section as it is written. (People v. Stewart, 281 Ill. 365.) It is the prime duty of the judicial interpreter to clothe the language of the legislature with its plain and natural meaning. (Armour & Co. v. Industrial Board, 275 Ill. 328.) Mechanics’ liens are purely statutory. They were unknown to the common law or to equity, and this court has uniformly held that statutes creating such liens must be strictly construed. (Hoier v. Kaplan, 313 Ill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Concrete Structures v. Clark
2023 IL App (1st) 230015-U (Appellate Court of Illinois, 2023)
Luise, Inc. v. Village of Skokie
781 N.E.2d 353 (Appellate Court of Illinois, 2002)
R.W. Dunteman Co. v. C/G Enterprises Inc.
692 N.E.2d 306 (Illinois Supreme Court, 1998)
Struebing Construction Co. v. Golub-Lake Shore Place Corp.
666 N.E.2d 846 (Appellate Court of Illinois, 1996)
A.Y. McDonald Manufacturing Co. v. State Farm Mutual Automobile Insurance
587 N.E.2d 623 (Appellate Court of Illinois, 1992)
Aluma Systems, Inc. v. Frederick Quinn Corp.
564 N.E.2d 1280 (Appellate Court of Illinois, 1990)
J&W Allen Construction Co. v. Kramer
41 Ill. Ct. Cl. 133 (Court of Claims of Illinois, 1989)
Anderson "Safeway" Guard Rail Corp. v. Champaign Asphalt Co.
266 N.E.2d 414 (Appellate Court of Illinois, 1971)
Board of Education of School District No. 108 v. Collom
222 N.E.2d 804 (Appellate Court of Illinois, 1966)
Lehmann Tire & Supply, Inc. v. Mashuda Construction Co.
109 N.W.2d 650 (Wisconsin Supreme Court, 1961)
Hankenson v. BOARD OF EDUCATION OF WAUKEGAN TP. HIGH SCH. DIST.
141 N.E.2d 5 (Illinois Supreme Court, 1957)
Hankenson v. Board of Education
141 N.E.2d 5 (Illinois Supreme Court, 1957)
Koenig v. McCARTHY CONSTR. CO., INC.
100 N.E.2d 338 (Appellate Court of Illinois, 1951)
Christopher v. West
98 N.E.2d 722 (Illinois Supreme Court, 1951)
Chicago Pump Co. v. Lakeside Engineering Corp.
15 N.E.2d 929 (Appellate Court of Illinois, 1938)
Hays v. Illinois Terminal Transportation Co.
2 N.E.2d 309 (Illinois Supreme Court, 1936)
Edward Solomon, Inc. v. Padorr
282 Ill. App. 269 (Appellate Court of Illinois, 1935)
Standard Oil Co. v. Kapschull, Davis Co.
276 Ill. App. 281 (Appellate Court of Illinois, 1934)
Sinclair Refining Co. v. Mann
274 Ill. App. 136 (Appellate Court of Illinois, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
190 N.E. 99, 356 Ill. 49, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alexander-lumber-co-v-coberg-ill-1934.