A.Y. McDonald Manufacturing Co. v. State Farm Mutual Automobile Insurance

587 N.E.2d 623, 225 Ill. App. 3d 851, 167 Ill. Dec. 354, 1992 Ill. App. LEXIS 191
CourtAppellate Court of Illinois
DecidedFebruary 13, 1992
Docket4-91-0255
StatusPublished
Cited by23 cases

This text of 587 N.E.2d 623 (A.Y. McDonald Manufacturing Co. v. State Farm Mutual Automobile Insurance) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A.Y. McDonald Manufacturing Co. v. State Farm Mutual Automobile Insurance, 587 N.E.2d 623, 225 Ill. App. 3d 851, 167 Ill. Dec. 354, 1992 Ill. App. LEXIS 191 (Ill. Ct. App. 1992).

Opinion

PRESIDING JUSTICE GREEN

delivered the opinion of the court:

On October 13, 1987, plaintiff A.Y. McDonald Manufacturing Company brought suit in the circuit court of McLean County pursuant to the Mechanics Liens Act (Act) (Ill. Rev. Stat. 1989, ch. 82, par. 1 et seq.) seeking to foreclose a mechanic’s lien against property owned by defendant State Farm Mutual Automobile Insurance Company (State Farm). Also named as defendants were the general contractor and various subcontractors involved in a contract for the improvement of real estate belonging to State Farm. Plaintiff filed a motion for a summary judgment determining it had a valid lien against State Farm. Plaintiff did not request a determination as to the amount of the lien. Defendants filed motions requesting a summary judgment against plaintiff in bar of action. After a hearing, the court entered an order on March 8, 1991, denying plaintiff’s motion and entering judgment in bar of action against plaintiff and in favor of all defendants.

The circuit court concluded that plaintiff’s claim for lien was invalid because the notice which it had given State Farm pursuant to section 24 of the Act (Ill. Rev. Stat. 1989, ch. 82, par. 24) was inadequate for failure to name the party (subcontractor) with which plaintiff had contracted. Plaintiff has appealed maintaining the court erred in ruling its notice was insufficient in form. Plaintiff also disputes the other grounds which defendants maintain support the summary judgment for them. These claims are that (1) the service of the foregoing notice was insuffident and untimely; (2) the Act does not provide lien rights to a third-tier subcontractor; and (3) any lien plaintiff might otherwise have was defeated because nothing was due to the subcontractor with whom it had contracted. We agree with plaintiff and reverse and remand with directions to enter a summary judgment determining that plaintiff has a valid lien against the premises involved and to proceed with the case from that point.

Summary judgment shall be granted when “the pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” (Ill. Rev. Stat. 1989, ch. 110, par. 2—1005(c).) This is an appropriate case for entry of a summary judgment as the issues concern conclusions of law arising from undisputed facts which we now set forth.

State Farm entered into a contract with defendant Mellon-Stuart Company (general contractor) for construction of major improvements on State Farm’s property in Bloomington, Illinois. The general contractor entered into a subcontract with defendant Natkin and Company, the first subcontractor (Natkin). Natkin then entered into a contract with defendant Pioneer Sheet Metal, the second subcontractor (Pioneer). Pioneer then entered into a contract with plaintiff, the third subcontractor, for plumbing materials and supplies for use on State Farm’s project.

Between July 7, 1986, and February 4, 1987, plaintiff supplied plumbing materials which were incorporated into improvements on State Farm’s property. On February 5, 1987, Natkin terminated its contract with Pioneer, allegedly due to the latter’s breach of its subcontract. On February 19, 1987, plaintiff recorded its statement of claim for lien as required by section 28 of the Act (Ill. Rev. Stat. 1989, ch. 82, par. 28). It then sent a copy of that document to State Farm by regular mail. In pertinent part, that document stated:

“[McDonald] *** claims a mechanic’s lien for (1) materials in and about the improvement of the following described real estate ***. Which said real estate at the time of making of the contract hereinafter mentioned was, and now is, owned by State Farm Mutual Automobile Insurance Company. That on the 7th day of May, A.D. 1986, claimant and said owner and its agents entered into contract which was (2) not in writing, wherein it was provided that claimant should (3) provide materials and supplies in the construction of improvements and structures on the above-described premises on an open account on said above described real estate, and that said owner or its agent should pay claimant therefor the sum of [$38,642.32] ***.”

State Farm acknowledged receipt of this document.

Plaintiffs first two contentions concern the question of whether, by sending the foregoing document to State Farm, it complied with the requirements of section 24 of the Act, which provides as follows:

“Sub-contractors, or party furnishing labor or materials *** shall *** cause a written notice of his or her claim and the amount due or to become due thereunder, to be sent by registered or certified mail, with return receipt requested, and delivery limited to addressee only, to or personally served on the owner of record or his agent or architect ***. ***
The form of such notice may be as follows: To (name of owner): You are hereby notified that I have been employed by (the name of contractor) to (state here what was the contract or what was done, or to be done, or what the claim is for) under his or her contract with you, on your property at (here give substantial description of the property) and that there was due to me, or is to become due (as the case may be) therefor, the sum of $.....” Ill. Rev. Stat. 1989, ch. 82, par. 24.

The circuit court’s conclusion that the foregoing notice was invalid for failure to name the contractor with whom the plaintiff had contracted was based in part upon the decision in LaCrosse Lumber Co. v. Grace Methodist Episcopal Church (1913), 180 Ill. App. 584. That case involved a subcontractor’s notice to the owner of a claim for lien under statutory language substantially the same as that in the current section 24 of the Act. (See Ill. Rev. Stat. 1909, ch. 82, par. 38.) In holding that a notice which failed to name the contractor was invalid, that court stated that the name of the contractor was “a very material” part of the requirements of notice to owners. LaCrosse, 180 Ill. App. at 590.

Plaintiff argues the statutory requirements of section 24 are that notice (1) be in writing, (2) contain the name of the claimant, (3) specify the amount due, and (4) be delivered to the owner of record — all elements with which its notice complied. (See Ill. Rev. Stat. 1989, ch. 82, par. 24.) Defendants implicitly acknowledge that as LaCrosse is an appellate opinion issued prior to 1935, it is not authoritative precedent. See Hughes v. Medendorp (1938), 294 Ill. App. 424, 427-28, 13 N.E.2d 1015, 1017; United Mine Workers of America Union Hospital v. United Mine Workers of America District No. 50 (1972), 52 Ill. 2d 496, 499, 288 N.E.2d 455, 457.

Defendants assert Hill Behan Lumber Co. v. Irving Federal Savings & Loan Association (1984), 121 Ill. App. 3d 511, 459 N.E.2d 1066, rejuvenates LaCrosse as authoritative precedent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matteo Construction Co. v. Teckler Blvd Development Site, LLC
2020 IL App (2d) 190766 (Appellate Court of Illinois, 2020)
GX Chicago, LLC v. Galaxy Environmental, Inc.
2015 IL App (1st) 133624 (Appellate Court of Illinois, 2015)
BX Chicago, LLC v. Galaxy Environmental, Inc.
2015 IL App (1st) 133624 (Appellate Court of Illinois, 2015)
Doors Acquisition, LLC v. Rockford Structures Construction Co.
2013 IL App (2d) 120052 (Appellate Court of Illinois, 2013)
People v. Henry
924 N.E.2d 1126 (Appellate Court of Illinois, 2010)
Speedy Gonzalez Landscaping, Inc. v. O.C.A. Construction, Inc.
896 N.E.2d 494 (Appellate Court of Illinois, 2008)
Cordeck Sales v. Construction Systems
Appellate Court of Illinois, 2008
Cordeck Sales, Inc. v. Construction Systems, Inc.
887 N.E.2d 474 (Appellate Court of Illinois, 2008)
Seasons-4, Inc. v. Hertz Corp.
Appellate Court of Illinois, 2003
Baumhoefener Nursery, Inc. v. a & D Partnership, II
618 N.W.2d 363 (Supreme Court of Iowa, 2000)
Petroline Co. v. Advanced Environmental Contractors, Inc.
711 N.E.2d 1146 (Appellate Court of Illinois, 1999)
McManamon v. Retirement Board of Policemen's Annuity & Benefit Fund
699 N.E.2d 1075 (Appellate Court of Illinois, 1998)
Struebing Construction Co. v. Golub-Lake Shore Place Corp.
666 N.E.2d 846 (Appellate Court of Illinois, 1996)
Continental Mobile Telephone Company, Inc. v. Illinois Commerce Commission
645 N.E.2d 516 (Appellate Court of Illinois, 1994)
J & B Steel Contractors, Inc. v. C. Iber & Sons, Inc.
617 N.E.2d 405 (Appellate Court of Illinois, 1993)
Stoebner v. Horizon Fabricators, Inc.
153 B.R. 840 (D. Minnesota, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
587 N.E.2d 623, 225 Ill. App. 3d 851, 167 Ill. Dec. 354, 1992 Ill. App. LEXIS 191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ay-mcdonald-manufacturing-co-v-state-farm-mutual-automobile-insurance-illappct-1992.