Petroline Co. v. Advanced Environmental Contractors, Inc.

711 N.E.2d 1146, 305 Ill. App. 3d 234, 238 Ill. Dec. 485
CourtAppellate Court of Illinois
DecidedApril 27, 1999
Docket1-98-2026
StatusPublished
Cited by21 cases

This text of 711 N.E.2d 1146 (Petroline Co. v. Advanced Environmental Contractors, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petroline Co. v. Advanced Environmental Contractors, Inc., 711 N.E.2d 1146, 305 Ill. App. 3d 234, 238 Ill. Dec. 485 (Ill. Ct. App. 1999).

Opinion

JUSTICE COUSINS

delivered the opinion of the court:

The plaintiff subcontractor was hired to provide equipment that was to be installed on a piece of property owned by defendants in this case. The subcontractor was not fully paid, so it filed a mechanic’s lien against the property. It provided 90 days’ notice to the owners under section 24 of the Mechanics Lien Act (770 ILCS 60/24 (West 1996)), but did not provide such notice to the mortgagee (whose interest was recorded).

The subcontractor filed suit against the owners to foreclose the lien within the statutory limitations period. The trial court dismissed the action, however, on the basis that the subcontractor’s failure to give the mortgagee 90 days’ notice prevented the formation of an enforceable lien.

The subcontractor appealed, arguing that the lack of notice to the lender only made the lien unenforceable against the lender, not unenforceable against the owners.

We reverse and remand.

BACKGROUND

In 1993, defendants Yong Choi and Kil Jee Choi (owners) bought a piece of property on North Cicero Avenue. They financed the purchase by mortgaging the property to defendant Shui Chow (lender). The purchase and the mortgage were promptly recorded.

The owners hired defendant Advanced Environmental Contractors, Inc. (contractor), to install underground petroleum storage tanks and other equipment on the property. The contractor bought equipment from the plaintiff, Petroline Co. (subcontractor). The subcontractor completed delivery on November 17, 1994. At this time, $14,107.25 of the $63,499 bill remains unpaid.

The subcontractor served a 90-day notice on the owner that it was filing a mechanic’s lien, as required by section 24 of the Mechanics Lien Act (the Act), which provides in pertinent part:

“Sub-contractors, or party furnishing labor or materials, may at any time after making his or her contract with the contractor, and shall within 90 days after the completion thereof *** cause a written notice of his or her claim and the amount due or to become due thereunder, to be sent by registered or certified mail, with return receipt requested, and delivery limited to addressee only, to or personally served on the owner of record or his agent or architect, or the superintendent having charge of the building or improvements and to the lending agency if known[.]” 770 ILCS 60/24 (West 1996).

The subcontractor did not, however, give notice to the lender.

The subcontractor recorded its lien within four months of delivery of the equipment and then filed suit to foreclose the lien (along with other relief) within two years of delivery as required by section 7 of the Act. 770 ILCS 60/7 (West 1996). Both the contractor, who had filed in bankruptcy, and the lender were joined as defendants.

The subcontractor’s initial complaint had three counts: mechanic’s lien foreclosure, an action at law under section 28 of the Act, and quantum meruit. The trial court struck the second count with leave to replead and dismissed the third count without prejudice. The subcontractor then filed a first amended complaint for mechanic’s lien foreclosure. The court dismissed this complaint on the motion of the owners because the subcontractor had not provided section 24 notice to the lender. The court denied a motion to reconsider, explaining that “[p]laintiffs were unable to plead notice on owner and lender or allege facts to obviate the need to serve such notice.” The court then certified the issue for interlocutory review pursuant to Supreme Court Rule 304(a) (134 Ill. 2d R. 304(a)).

The subcontractor now appeals, arguing that its failure to give the lender section 24 notice only means that its hen cannot have priority over the mortgage, not that the lien cannot be enforced against the owners.

ANALYSIS

The paramount objective in construing a statute is to give effect to the intent of the legislature. People ex rel. Nelson v. Olympic Hotel Building Corp., 405 Ill. 440, 444, 91 N.E.2d 597, 599 (1950). In order to determine legislative intent, courts construe a statute as a whole. Pliakos v. Illinois Liquor Control Comm’n, 11 Ill. 2d 456, 459-60, 143 N.E.2d 47, 49 (1957). The purpose of the legislature should be gathered from the entire statute rather than any particular section of it. People ex rel. Nelson, 405 Ill. at 444, 91 N.E.2d at 599.

We analyze this case keeping in mind that the purpose of the Mechanics Lien Act is “to protect those who in good faith furnish material or labor for the construction of a building.” Norman A. Koglin Associates v. Valenz Oro, Inc., 277 Ill. App. 3d 142, 146, 659 N.E.2d 971, 975 (1995). In particular, the mechanic’s lien provisions concerning subcontractors “are designed to ensure that subcontractors will have some recourse against the ultimate beneficiaries of the subcontractors’ labors—the project owner—if the general contractor fails to meet its obligations to the subcontractor.” S.J. Groves & Sons Co. v. Midwest Steel Erection Co., 666 F. Supp. 129, 131 (N.D. Ill. 1986).

Certain of the portions of the Act relevant to this case apply to both contractors and subcontractors. For example, the Act requires that a lien be recorded, or suit be filed, within four months of the work done if the lien is to be effective against third parties. 770 ILCS 60/7 (West 1996). There is a two-year limitations period for suits under the Act. 770 ILCS 60/9 (West 1994). The Act requires that interested parties be joined in a suit to foreclose a lien. 770 ILCS 60/11 (West 1996). If the contract on which a lien is based is entered into prior to the recording of a mortgage, it takes priority over the mortgage. 770/ILCS 60/1 (West 1996). But if the mortgage is recorded before the contract and there is a deficiency, a special procedure is followed. The court calculates what percent of the value of the land was present before the contract and what percent of the value was added by the improvements. For instance, perhaps the value was $4,000 before the contractor’s work and $5,000 afterwards, but the foreclosure sale only nets $3,000. The mortgagee’s claim is preferred to 80% of the money from the foreclosure sale, i.e., $2,400. The lienholder’s claim is preferred to 20% of the money from the sale, i.e., $600. 770 ILCS 60/16 (West 1996). See generally Moulding-Brownell Corp. v. E.C. Delfosse Construction Co., 304 Ill. App. 491, 26 N.E.2d 709 (1940).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Construction Systems, Inc. v. FagelHaber, LLC
2019 IL App (1st) 172430 (Appellate Court of Illinois, 2019)
Christopher B. Burke Engineering, LTD. v. Heritage Bank of Central Illinois
2015 IL App (3d) 140064 (Appellate Court of Illinois, 2015)
Christopher B. Burke Engineering, LTD. v. Heritage Bank of Central Illinois
2015 IL App (3d) 140064 (Appellate Court of Illinois, 2015)
Parkway Bank and Trust Co. v. Meseljevic
940 N.E.2d 215 (Appellate Court of Illinois, 2010)
Parkway Bank and Trust Company v. Meseljevic
Appellate Court of Illinois, 2010
LaSalle Bank National Ass'n v. Cypress Creek 1, LP
925 N.E.2d 233 (Appellate Court of Illinois, 2010)
Speedy Gonzalez Landscaping, Inc. v. O.C.A. Construction, Inc.
896 N.E.2d 494 (Appellate Court of Illinois, 2008)
Bale v. Barnhart
Appellate Court of Illinois, 2003
Philip v. Daley
Appellate Court of Illinois, 2003
Seasons-4, Inc. v. Hertz Corp.
Appellate Court of Illinois, 2003
In Re Davicter Enterprises, Inc.
248 B.R. 794 (S.D. Illinois, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
711 N.E.2d 1146, 305 Ill. App. 3d 234, 238 Ill. Dec. 485, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petroline-co-v-advanced-environmental-contractors-inc-illappct-1999.