LaSalle Bank National Ass'n v. Cypress Creek 1, LP

925 N.E.2d 233, 398 Ill. App. 3d 592
CourtAppellate Court of Illinois
DecidedJanuary 15, 2010
Docket3-08-0114
StatusPublished
Cited by6 cases

This text of 925 N.E.2d 233 (LaSalle Bank National Ass'n v. Cypress Creek 1, LP) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LaSalle Bank National Ass'n v. Cypress Creek 1, LP, 925 N.E.2d 233, 398 Ill. App. 3d 592 (Ill. Ct. App. 2010).

Opinions

JUSTICE O’BRIEN

delivered the opinion of the court:

Plaintiff-appellee and cross-appellant LaSalle Bank National Association filed this action to foreclose a mortgage it held on a parcel of real estate that was being developed for senior apartments. Defendants-appellants and cross-appellees Edon Construction Co. and Eagle Concrete filed mechanic’s hens for work they had done on the apartment buildings. The property was sold pursuant to a sheriff’s sale, and in allocating the sale proceeds, the trial court apportioned the funds between LaSalle as mortgagee and Edon and Eagle as mechanic’s lien claimants, and subrogated LaSalle to the position of mechanic’s lien claimant for various costs it funded during construction. On appeal, Edon and Eagle challenge the allocation and LaSalle cross-appeals the trial court’s denial of its request for attorney fees. We affirm in part, reverse in part, and remand.

FACTS

LaSalle Bank made a loan to Cypress Creek, LLI} which sought to develop a 13.79-acre parcel of land into senior apartments. The loan, in the amount of $8,018,151, was secured by a mortgage and security agreement. Section 4.3 of the mortgage provided, in pertinent part:

“In any suit to foreclose the lien hereof ***, there shall be allowed and included as additional indebtedness in the decree for sale or other judgment or decree, all expenditures and expenses which may be paid or incurred by or on behalf of the Mortgagee for attorneys’ fees *** as the Mortgagee may deem reasonably necessary *** to prosecute such suit.”

The mortgage was recorded on June 13, 2003.

In December 2004, Eagle Concrete contracted with Cypress Creek to perform concrete work for the project for $632,000. In January 2005, Edon entered into a written contract with Cypress Creek to provide rough carpentry for the project. Cypress Creek defaulted on the mortgage in June 2005. In July 2005, LaSalle filed the instant complaint to foreclose the mortgage. Eagle recorded a $63,478 mechanic’s lien on November 4, 2005. Edon recorded a mechanic’s hen in the amount of $285,826.80, on November 21, 2005. Eagle filed its complaint for foreclosure of its mechanic’s lien on March 30, 2006. A judgment of foreclosure and sale was entered against Cypress Creek in April 2006, finding that the balance due on the mortgage was $8,621,110, and reserving a determination as to priorities between LaSalle as the mortgagee and the various mechanic’s lien claimants, including Edon and Eagle. Thereafter, the order of judgment was amended to reflect payment on the judgment of $5,577,540, with an amount due of $3,043,570. The property was sold at a sheriffs sale in May 2006 to LaSalle for $1,300,000. In August 2006, Edon filed a complaint to foreclose its mechanic’s lien, which was consolidated with the mortgage foreclosure proceeding.

A trial ensued in September 2007. Edon, Eagle, and three other mechanic’s lien claimants not parties to this appeal challenged confirmation of the sale and argued for priority of their liens over the mortgage. Various experts testified as to the value of the real estate and the improvements. Other testimony included that of John Marynell, a senior vice president at LaSalle, who testified that LaSalle had funded the construction draws while the work was progressing, including $1,446,266 in construction costs, $99,917 in engineering costs, $2,842 for environmental reports, and $8,538 for utilities. Marynell also testified that LaSalle paid the perfected mechanic’s lien for $30,202 of Basic Development, a defendant not involved in this appeal. In total, LaSalle paid $1,587,765 in construction and development costs.

The trial court confirmed the sale and entered an order allocating the sale proceeds as follows:

Expense of sale $1,542.00
Receiver’s fees and expenses 746243.94
Remaining proceeds:
LaSalle Bank $471,614.06
Edon Construction 50,000
Eagle Concrete 10,000
Gallagher Construction 7,300
All American Roofing 7,300
Another Plumbing 6,000
$1,300,000.

The court’s apportionment was based on the following:

Value of land before improvements:
Value of enhancements: Lien claimants
+ bank subrogation
+ land value = total value
$1,360,000
$480,934
1,587,765
$2,068,699
1,360,000
$3,428,699.

LaSalle was subrogated as to the following amounts for a total of $1,587,765:

Construction costs
Engineering costs
Environmental reports
Utilities
Basic Development’s lien
$1,446,266
99,917
2,842
8,538
30,202
$2,068,699/$3,428,699 = 60% to enhancers of property (lien claimants) $l,300,000/$3,428,699 = 40% to mortgagee
Value of improvements: $522,214* x 60% = $331,328.40 Eagle: $63,478**/$2,068,699 = 3% = approximately $10,000 Edon: $285,827**/$2,068,699 = 15% = approximately $50,000 LaSalle subrogation: $l,587,765/$2,068,699 = 76% = $256,514
Value of land: $522,214 x 40% = $215,100 to LaSalle
Remaining $ from sale proceeds
** contract price

Edon and Eagle filed motions for modification of the judgment, challenging the trial court’s priority determinations. The trial court denied the motions in January 2008. Thereafter, Edon appealed the trial court’s allocation of the sale proceeds, and Eagle joined Edon in its appeal. LaSalle cross-appealed the trial court’s denial of its request for attorney fees.

The first issue for our consideration is whether the trial court erred in apportioning the sheriff’s sale proceeds. Edon and Eagle present two arguments that the apportionment was in error. First, they argue that as mechanic’s lien claimants, they have full priority over a mortgagee and that the trial court should have satisfied their liens in total before disbursing any funds to LaSalle as mortgagee.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LaSalle Bank National Ass'n v. Cypress Creek 1, LP
950 N.E.2d 1109 (Illinois Supreme Court, 2011)
Village of Woodridge v. Board of Education
933 N.E.2d 392 (Appellate Court of Illinois, 2010)
LaSalle Bank National Ass'n v. Cypress Creek 1, LP
925 N.E.2d 233 (Appellate Court of Illinois, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
925 N.E.2d 233, 398 Ill. App. 3d 592, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lasalle-bank-national-assn-v-cypress-creek-1-lp-illappct-2010.