Watson v. Auburn Iron Works, Inc.

318 N.E.2d 508, 23 Ill. App. 3d 265, 1974 Ill. App. LEXIS 1825
CourtAppellate Court of Illinois
DecidedOctober 16, 1974
Docket73-110
StatusPublished
Cited by37 cases

This text of 318 N.E.2d 508 (Watson v. Auburn Iron Works, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Watson v. Auburn Iron Works, Inc., 318 N.E.2d 508, 23 Ill. App. 3d 265, 1974 Ill. App. LEXIS 1825 (Ill. Ct. App. 1974).

Opinion

Mr. JUSTICE SEIDENFELD

delivered the opinion of the court:

Plaintiff Hugh Watson, d/b/a Empire Steel, sued defendant Auburn Iron Works (here referred to as Auburn) claiming a mechanic’s lien on property known as “Walnut Creek” in Count I, and seeking a money judgment from numerous other open jobs between the parties in Count II. During the trial, the court allowed the plaintiff to file a third amended complaint adding the general contractor, K. M. Knight Construction Co., as a party defendant. Following the trial, the court entered judgment on Count I against Auburn, the general contractor and other parties interested in the property in the amount of $4,027.29 and disallowed a counterclaim which had been filed by Auburn. The court entered judgment on Count II in favor of Watson against Auburn in the amount of $9,187.15. The defendants appeal.

Watson and Auburn had a long-standing working relationship prior to this dispute. Auburn would bid the jobs and orally sublet the steel erecting to Watson. In this case, Auburn submitted a bid for nine buildings in the “Walnut Creek” project. The bid contemplated that Auburn would fabricate the steel and Watson would erect the steel and bar joists. Watson’s price quoted to Auburn was on the basis of the original bid for nine buildings.

However, the contract actually entered into by Auburn and K. M. Knight Construction Company, the general contractor, was for steel work for only three buildings at a price of $58,890. Nonetheless Auburn and Watson orally agreed that Watson should do the steel erecting, receiving payment by monthly installments for floors completed. Watson testified that he believed the contract price to be $33,000, plus extras. Anthony Petro, the owner of Auburn, however, set the contract price at approximately $25,000.

Watson began performance on April 7, 1970. He testified to his belief that well after the start of the performance the three buildings were to be only the first phase of the nine-building project but that he was thereafter informed that the three buildings were all that were contemplated. Watson continued to do substantial work until June 8,1971, when further work was suspended pending receipt of payment for work completed. He had received no monthly installments to that date.

Anthony Petro, president of Auburn, testified by contrast that nonpayment was not the main reason why plaintiff walked off the job. He testified that Watson told him that he was tired of the job and wanted out and had complained that the job conditions were not right, and, also, that Watson told him that he had been unsuccessful in obtaining the approval of the general contractor and the architect for the performance of extras. At the time of the suspension of work, Watson had completed only 20% of the work with expenditures of $9,898.50.

While Watson was off the job, Auburn hired another erector who worked until plaintiff resumed work on July 22, after receiving a partial payment of $2,500. Watson’s only other receipts of payment were $1,500 on August 18 and $3,000 on September 2.

On September 10, Auburn was notified by telegram that the erection was not acceptable, and on October 6, notice was given that the erector’s portion of the contract was terminated. Nonetheless, Watson worked until October 7, when the general contractor dismissed him from work. There was disputed testimony as to the quality of plaintiff’s work.

After October 7, another company was called in to complete the steel erection. The total paid to steel erectors for the job, other than that paid to the plaintiff, amounted to $25,376.

The trial commenced in January of 1972. The general contractor was subpoenaed to testify as a witness and during this portion of the case, defendants moved to dismiss for failure to join the contractor as a party defendant. The motion was denied and at this time plaintiff was allowed to file a third amended complaint and issue summons against the general contractor as a defendant. All defendants were allowed 28 days to plead concerning the amended complaint and the trial was reconvened on April 19, 1972.

As to Count I, defendants contend that plaintiffs had no damages, that the court erred in failing to dismiss the complaint upon defendants’ motion for failure to join the general contractor as a party defendant before substantial progress in the trial, and in then proceeding with the trial, and that the court erred in denying Auburn’s counterclaim based upon its charge that Watson had wrongfully walked off the job and in allowing the mechanic’s lien. The sole issue raised as to Count II is the refusal of the court to detail its verdict which defendants claim cannot be explained on the evidence, and this issue is also raised as to Count I.

Defendants argue that under any legal theory used to measure damages plaintiff may not recover under Count I.

Defendants argue that the proper measure of damages for breach of a construction contract is the difference between the cost of construction and the fair market cost of the agreed construction. (Citing Ross v. Danter Associates, Inc. (1963), 102 Ill.App.2d 354, 370; Bertram v. Bergquist (1910), 153 Ill.App. 43, 45; County of Schuyler v. Missouri Bridge and Iron Co. (1912), 256 Ill. 348, 352-353.) However, in each of cited cases the contractor breached his contract by refusing to perform and the owner was suing. Here, the roles are reversed. The contract was breached by Auburn’s nonpayment of monthly installments for work performed as per the contract. Consequently this particular measure of damages relied upon by the defendant is inapplicable.

Defendants claim that the court erred in finding that plaintiff had an excuse to walk off the job and in finding that plaintiff’s rights were established as of June 8 rather than at the time of the termination on October 7 when the general contractor forced plaintiff off the job. Additionally, defendants argue that even if plaintiff had an excuse by virtue of Auburn’s nonpayment of monthly installments, his resumption of work on July 22 either operated as a waiver or established the nonpayment as nothing more than an excuse to get out of a bad business deal.

Defendants’ contentions are without merit. Auburn’s failure to make monthly installments was properly viewed as a material breach establishing plaintiff’s rights and entitling him to suspend work until payment was received. (J. J. Brown Co. v. J. L. Simmons Co. (1954), 2 Ill.App 2d 132, 143.) The facts reveal that plaintiff received $2,500 prior to resuming work on July 22. Subsequent payments were late, with $1,500 being received on August 18 and $3,000 received on September 2. Further, there was conflicting evidence regarding the character of plaintiff’s performance notwithstanding the general contractor’s termination of the erection contract on October 6. Under such circumstances, the resolution of tire question of fault, which also disposed of defendant’s counterclaim, was a matter properly made by the trier of fact. (Edward Electric Co. v. Metropolitan Sanitary Dist. (1973), 16 Ill.App.3d 521, 526.) The court’s finding on this issue is affirmed on the record before us.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hayden v. Adams
2020 IL App (1st) 191411-U (Appellate Court of Illinois, 2020)
Spanish Court Two Condominium Ass'n v. Carlson
2012 IL App (2d) 110473 (Appellate Court of Illinois, 2012)
National City Mortg. v. Hillside Lumber
966 N.E.2d 1076 (Appellate Court of Illinois, 2012)
National City Mortgage v. Hillside Lumber
2012 IL App (2d) 101292 (Appellate Court of Illinois, 2012)
Speedy Gonzalez Landscaping, Inc. v. O.C.A. Construction, Inc.
896 N.E.2d 494 (Appellate Court of Illinois, 2008)
Cordeck Sales v. Construction Systems
Appellate Court of Illinois, 2008
Cordeck Sales, Inc. v. Construction Systems, Inc.
887 N.E.2d 474 (Appellate Court of Illinois, 2008)
Seasons-4, Inc. v. Hertz Corp.
Appellate Court of Illinois, 2003
Petroline Co. v. Advanced Environmental Contractors, Inc.
711 N.E.2d 1146 (Appellate Court of Illinois, 1999)
J & B Steel Contractors, Inc. v. C. Iber & Sons, Inc.
617 N.E.2d 405 (Appellate Court of Illinois, 1993)
A.Y. McDonald Manufacturing Co. v. State Farm Mutual Automobile Insurance
587 N.E.2d 623 (Appellate Court of Illinois, 1992)
Matthews Roofing Co. v. Community Bank & Trust Co.
550 N.E.2d 1189 (Appellate Court of Illinois, 1990)
Fireman's Fund Mortgage Corp. v. Zollicoffer
719 F. Supp. 650 (N.D. Illinois, 1989)
Malloy v. Judge's Foster Home Program, Inc.
746 P.2d 1073 (Montana Supreme Court, 1987)
Herbert W. Jaeger & Associates v. Slovak American Charitable Ass'n
507 N.E.2d 863 (Appellate Court of Illinois, 1987)
Du Page Bank & Trust Co. v. Du Page Bank & Trust Co.
462 N.E.2d 25 (Appellate Court of Illinois, 1984)
Kenny Construction Co. v. Hinsdale Sanitary District
444 N.E.2d 510 (Appellate Court of Illinois, 1982)
Las Vegas Plywood & Lumber, Inc. v. D & D Enterprises
649 P.2d 1367 (Nevada Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
318 N.E.2d 508, 23 Ill. App. 3d 265, 1974 Ill. App. LEXIS 1825, Counsel Stack Legal Research, https://law.counselstack.com/opinion/watson-v-auburn-iron-works-inc-illappct-1974.