Hayden v. Adams

2020 IL App (1st) 191411-U
Appellate Court of Illinois·Decided April 16, 2020·No. 1-19-1411·Unpublished

Opinion

2020 IL App (1st) 191411-U

FOURTH DIVISION

April 16, 2020

No. 1-19-1411

NOTICE: This order was filed under Supreme Court Rule 23 and may not be cited as precedent by any party except in the limited circumstances allowed under Rule 23(e)(1).

IN THE APPELLATE COURT

OF ILLINOIS

FIRST JUDICIAL DISTRICT

ROGESTER HAYDEN, JR., ) Appeal from the ) Circuit Court of Plaintiff-Appellee, ) Cook County.

)

v. ) No. 18 CH 1697 )

WILLIAM ADAMS d/b/a ADAMS REMODELING, ) Honorable ) Lewis Nixon,

Defendant-Appellant. ) Judge Presiding.

JUSTICE BURKE delivered the judgment of the court.

Justices Lampkin and Reyes concurred in the judgment.

ORDER

¶1 Held: We affirm the circuit court’s grant of summary judgment in favor of plaintiff where defendant failed to comply with section 34 of the Mechanics Lien Act.

¶2 Defendant William Adams, d/b/a Adams Remodeling, appeals following the trial court’s order denying his motion for summary judgment and granting summary judgment in favor of plaintiff Rogester Hayden, Jr. On appeal, Adams argues that the trial court erred in finding invalid Adams’ mechanics lien on Hayden’s real property and granting summary judgment to Hayden. For the reasons that follow, we affirm.

¶3 I. BACKGROUND

¶4 This lawsuit stems from a “FHA Homeowner/Contractor Agreement” (agreement) entered into between Adams and Hayden on January 12, 2017, to renovate Hayden’s residential property located on Dearborn Street in South Holland, Illinois. Hayden agreed to pay Adams $16,337.20 to rehabilitate his property under the agreement. At some point in April 2017, however, Adams ceased renovations prior to completion and Hayden terminated Adams as the contractor and failed to tender full payment.

¶5 Adams filed a mechanics lien, number 1723519064, in the amount of $10,619.18 with the Cook County Recorder of Deeds on August 23, 2017. The law firm Nicholas Law Group prepared the lien. Hayden was never served with a copy of the lien; he only discovered its existence while doing a search of his property on the Recorder’s website in October 2017.

¶6 On December 21, 2017, Hayden sent a letter to Adams demanding that he commence suit to enforce the lien (demand letter) pursuant to section 34 of the Mechanics Lien Act (the Act) (770 ILCS 60/34 (West 2018)) within 30 days of receipt of the demand letter. Hayden sent the demand letter to Nicholas Law Group by certified mail, return receipt requested. However, neither Nicholas Law Group nor Adams ever received the demand letter.

¶7 Hayden later instituted a declaratory judgment action against Adams on February 8, 2018. In the complaint, Hayden alleged that he ordered an inspection by a licensed home inspector who found 15 different problems with the renovations. Hayden requested that Adams remedy these issues, but Adams insisted that the work had been completed satisfactorily. Hayden alleged that he obtained an estimate from another construction company for the remediation, which offered a quote of $12,280. Hayden requested that the court declare the lien invalid and

forfeited due to Adams’ failure to properly respond to the demand letter within 30 days. Attached as an exhibit to the complaint was a copy of the December 21, 2017, demand letter.

¶8 Adams was served on May 2, 2018, with a copy of the complaint and summons by special process server. Adams filed an answer to the complaint on September 11, 2018. The parties both filed motions for summary judgment.

¶9 In Hayden’s motion for summary judgment, he contended that, pursuant to section 34 of the Act, Adams was required to respond to the complaint by June 4, 2018, that is, within 30 days after service of the complaint on May 2, 2018, because Hayden attached to the complaint, as an exhibit, the demand letter. Adams’ attorney filed an appearance on August 15, 2018, after obtaining an extension from the trial court to retain counsel. Adams did not file an answer to the complaint until September 11, 2018. Hayden argued that the 30-day time limitation in section 34 of the Act was jurisdictional and must be strictly complied with, or the lien is forfeited. Hayden asserted that the demand letter attached to the complaint contained the required statutory language to invoke the demand notice provision under section 34 of the Act.

¶ 10 In Adams’ motion for summary judgment, he asserted that the certified mailing United States Postal Service (USPS) tracking information related to Hayden’s demand letter showed that the demand letter was never delivered to anyone and thus cannot operate as a valid notice. It also should have been sent to Adams and not his attorney. Because Hayden failed to provide Adams with proper notice by serving on him personally the demand that Adams enforce his mechanics lien, Adams contended that Hayden’s declaratory action should be denied. Adams additionally argued that Hayden did not sufficiently allege in his complaint the facts necessary to assert that the summons and complaint, with attached demand letter, operated as a section 34 notice.

¶ 11 Following further briefing and oral arguments by the parties, the trial court issued a written memorandum opinion and order on May 29, 2019, denying Adams’ motion for summary judgment and granting Hayden’s motion for summary judgment. The trial court determined that Hayden’s attempted service of the demand letter failed to fulfill the statutory requirements under section 34 for service of a notice to commence suit because there was no evidence that Adams or his attorney ever received the demand letter. However, the trial court held that Hayden’s declaratory judgment complaint fulfilled the requirements under section 34 as a notice to commence suit because Hayden attached the demand letter as an exhibit to the complaint and referred to it in the complaint, thus incorporating it by reference. Accordingly, the trial court found Adams’ mechanics lien invalid and forfeited, and ordered it removed from the property.

¶ 12 Adams filed a timely appeal.

¶ 13 II. ANALYSIS

¶ 14 We review the circuit court's decision on a motion for summary judgment de novo. Outboard Marine Corp. v. Liberty Mutual Insurance Co., 154 Ill. 2d 90, 102 (1992). "[S]ummary judgment is proper only where the pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law." Mashal v. City of Chicago, 2012 IL 112341, ¶ 49 (citing 735 ILCS 5/2-1005(c) (West 2000)). "The purpose of summary judgment is not to try a question of fact but to determine whether one exists." Golla v. General Motors Corp., 167 Ill. 2d 353, 358-59 (1995). “In determining the existence of a genuine issue of material fact, the court must construe the evidence strictly against the moving party and liberally in favor of the nonmoving party.” Vernon Hills III Limited Partnership v. St. Paul Fire & Marine Insurance Co., 287 Ill. App. 3d 303, 307 (1997).

¶ 15 As we are called on to interpret the statutory language of section 34 of the Mechanics Lien Act in this case, “ we look at its plain meaning as well as the legislature's intent in enacting the statute. [Citations.] The best indication of the legislature's intent is the language of the statute itself; where the statutory language is unambiguous, we must enforce the law as written.” Gateway Concrete Forming Systems, Inc. v. Dynaprop XVIII: State St. LLC, 356 Ill. App. 3d 806, 810 (2005).

¶ 16 On appeal, Adams argues that the trial court erred in concluding that he was properly served with a demand notice to commence suit on his mechanics lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Hayden v. Adams, 2020 IL App (1st) 191411-U (Ill. Ct. App. 2020).

2020 IL App (1st) 191411-U (Hayden v. Adams) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Golla v. General Motors Corp.
657 N.E.2d 894 (Illinois Supreme Court, 1995)
Matthews Roofing Co. v. Community Bank & Trust Co.
550 N.E.2d 1189 (Appellate Court of Illinois, 1990)
Outboard Marine Corp. v. Liberty Mutual Insurance
607 N.E.2d 1204 (Illinois Supreme Court, 1992)
Vernon Hills III Limited Partnership v. St. Paul Fire & Marine Ins. Co.
678 N.E.2d 374 (Appellate Court of Illinois, 1997)
Watson v. Auburn Iron Works, Inc.
318 N.E.2d 508 (Appellate Court of Illinois, 1974)
Canel v. Topinka
818 N.E.2d 311 (Illinois Supreme Court, 2004)
Gateway Concrete Forming Systems, Inc. v. Dynaprop XVIII: State Street LLC
826 N.E.2d 1051 (Appellate Court of Illinois, 2005)
Bajwa v. Metropolitan Life Insurance
804 N.E.2d 519 (Illinois Supreme Court, 2004)
Novakovic v. Samutin
820 N.E.2d 967 (Appellate Court of Illinois, 2004)
Charter Bank & Trust v. Edward Hines Lumber Co.
599 N.E.2d 458 (Appellate Court of Illinois, 1992)
Mashal v. City of Chicago
2012 IL 112341 (Illinois Supreme Court, 2012)