Vernon Hills III Limited Partnership v. St. Paul Fire & Marine Ins. Co.

678 N.E.2d 374, 287 Ill. App. 3d 303, 222 Ill. Dec. 762, 1997 Ill. App. LEXIS 188
CourtAppellate Court of Illinois
DecidedApril 3, 1997
Docket2-96-0724
StatusPublished
Cited by29 cases

This text of 678 N.E.2d 374 (Vernon Hills III Limited Partnership v. St. Paul Fire & Marine Ins. Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vernon Hills III Limited Partnership v. St. Paul Fire & Marine Ins. Co., 678 N.E.2d 374, 287 Ill. App. 3d 303, 222 Ill. Dec. 762, 1997 Ill. App. LEXIS 188 (Ill. Ct. App. 1997).

Opinion

PRESIDING JUSTICE GEIGER

delivered the opinion of the court:

The defendant and counterplaintiff, Bucon, Inc. (Bucon), appeals from the April 23, 1996, order of the circuit court of Lake County granting summary judgment in favor of the plaintiff and counterdefendant, Vernon Hills III Limited Partnership (VHLP), on its claim for declaratory judgment. The trial court ruled that Bucon forfeited its mechanic’s lien by failing to commence an action to foreclose the lien within 30 days after receipt of VHLP’s written demand to sue, as required by section 34 of the Mechanics Lien Act (the Act) (770 ILCS 60/34 (West 1994)). On appeal, Bucon argues that the trial court erred in finding that VHLP’s letter of July 29, 1994, constituted a written demand to sue pursuant to section 34 of the Act. We affirm and remand.

The facts necessary for the disposition of this appeal are as follows. On February 18, 1993, VHLP contracted with Bucon to design and build a shopping center in Vernon Hills. Bucon was to design and construct all of the buildings, as well as numerous site improvements, including the parking lot and utility connections. The contract provided that Bucon would be paid approximately $15 million for the project. Bucon commenced construction in the spring of 1993, and a certificate of substantial completion was issued on August 22, 1994.

On July 21, 1994, Bucon filed a mechanic’s lien against the shopping center in the Lake County recorder’s office. The lien was in the amount of $1,315,249. On August 1, 1994, Bucon received, via certified mail, a letter from VHLP dated July 29, 1994. The letter provides, in pertinent part:

"Pursuant to Article 11.4 of that certain Design Build Contract dated as of February 18, 1993, *** between [VHLP] and [Bucon] for the design and construction of a retail shopping center *** located in Vernon Hills, Illinois, this letter shall serve as notice of your breach on the Contract pursuant to Article 11.5.2 of the Contract.
Article 11.5.2 of the Contract provides that '[i]n no event may Design/Builder file, or permit those whom it controls or for whom it has legal responsibility under the Contract to file, a mechanics’ *** lien or claim for lien for work performed under the Contract ***.’ However, on July 21, 1994, a claim for lien in the amount of $1,315,249.00 was filed in the Lake County Recorder’s Office ***. This course of action is clearly in violation of the Contract.
We hereby demand that you either immediately release your lien or bring suit to enforce it so that this matter can be expeditiously resolved. We fully intend to look to your organization in order to recapture any additional costs we may incur in connection with your actions. In addition, in the event this lien is not released of record immediately, we will pursue all other rights and remedies available in the Contract, at law or in equity in response to your breach and your failure to fulfill the requirements of this letter.”

On August 3, 1994, Bucon received a follow-up letter from VHLP’s attorney dated July 28, 1994. The letter provided as follows:

"You should be receiving, if you have not received already, a copy of ownership’s letter in connection with the mechanic’s lien you recently filed under Illinois’ Mechanic’s Lien Statute (770 ILCS 60/1, et seq.). It is not the purpose of this letter to alter the contents of ownership’s letter, but I did want to initiate with you a discussion as to why you have filed the lien and what purpose you think it will serve and further to suggest a dialogue to accomplishing the mutual objectives of your company and ownership. If you are so inclined, please give me a call.”

Thereafter, VHLP’s attorney and Bucon’s attorney had several conversations in which they discussed the lien. During these conversations, Bucon’s attorney explained that, although Bucon intended to preserve its rights under the Act, it would nonetheless assist VHLP in closing out the project. VHLP’s attorney reiterated VHLP’s position that Bucon had breached the contract by filing the lien.

On August 4 and 17,1994, VHLP’s attorneys wrote Bucon regarding certain paperwork that had to be completed in order to close out the project and to get the property ready for sale. After August 1994, Bucon and VHLP continued to correspond through their attorneys with respect to completing the steps necessary to close out the project. Bucon fully cooperated with these efforts to complete the project.

On October 27, 1994, VHLP made a claim to Bucon seeking liquidated damages arising from construction delays on the project. Between November 1994 and August 1995, Bucon and VHLP engaged in. negotiations in an attempt to settle Bucon’s lien and VHLP’s delay claim. The parties arrived at a tentative settlement agreement whereby Bucon would discount its lien from $1,315,249 to $922,901.50 and the parties would mutually release their claims. However, this settlement agreement broke down when the parties were unable to reach an agreement with respect to alleged defects in the building’s roof.

On January 13, 1995, VHLP filed suit against Bucon claiming damages in excess of the amount of Bucon’s lien. On February 27, 1995, VHLP filed an amended five-count complaint. Count IV, which is the only count relevant on appeal, sought a declaration that Bucon had forfeited its mechanic’s lien by failing to commence an action to foreclose its lien within 30 days after receipt of VHLP’s written demand to sue as required by section 34 of the Act (770 ILCS 60/34 (West 1994)). In June 1995, Bucon filed a counterclaim against VHLP seeking a judgment in the amount of its contract balance. On August 30, 1995, Bucon filed a separate action seeking enforcement of its lien.

On January 19, 1996, VHLP filed a motion for summary judgment on count IV of the amended complaint. VHLP argued that its letter of July 29, 1994, was a written demand, made pursuant to section 34 of the Act, that Bucon commence suit to enforce its mechanic’s lien. Although Bucon received VHLP’s letter on August 3, 1994, it did not file suit to enforce its lien within the next 30 days. VHLP therefore concluded that Bucon had forfeited its lien under section 34 of the Act.

In response to the motion, Bucon argued that VHLP’s July 29, 1994, letter was not a written demand to sue under section 34 of the Act. Bucon argued that the letter did not contain any reference to section 34 and did not indicate that Bucon’s failure to commence suit within 30 days would render its lien void. In support of its position, Bucon submitted the affidavit of its attorney stating that he did not understand the July 29, 1994, letter to be a demand pursuant to section 34 of the Act. Bucon’s attorney also stated that he was unaware of section 34 at the time he received the letter and that at no time did VHLP’s attorney mention the statute or its contents. Alternatively, Bucon argued that, even if the July 29, 1994, letter was a written demand to sue under section 34 of the Act, VHLP was estopped from asserting the defense due to its subsequent conduct and attempts to settle the lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mitchell v. Applied Behavioral Interventions, LLC
2025 IL App (1st) 221442-U (Appellate Court of Illinois, 2025)
Riaz v. Northwestern Memorial Hospital
2025 IL App (1st) 241203-U (Appellate Court of Illinois, 2025)
In re Estate of Frantz
2022 IL App (4th) 210596-U (Appellate Court of Illinois, 2022)
Hayden v. Adams
2020 IL App (1st) 191411-U (Appellate Court of Illinois, 2020)
Tucker v. Miller
2019 IL App (4th) 190331-U (Appellate Court of Illinois, 2019)
Curtis v. Lofy
914 N.E.2d 248 (Appellate Court of Illinois, 2009)
People v. Borello
906 N.E.2d 1250 (Appellate Court of Illinois, 2009)
Grimes v. Saikley
904 N.E.2d 183 (Appellate Court of Illinois, 2009)
TSP-Hope, Inc. v. Home Innovators of Illinois, LLC
890 N.E.2d 1220 (Appellate Court of Illinois, 2008)
TSP-Hope v. Home Innovators of Illinois
Appellate Court of Illinois, 2008
Illinois Department of Healthcare & Family Services v. Warner
882 N.E.2d 557 (Illinois Supreme Court, 2008)
Gateway Concrete Forming Systems, Inc. v. Dynaprop XVIII: State Street LLC
826 N.E.2d 1051 (Appellate Court of Illinois, 2005)
People v. Quinella W.
765 N.E.2d 1214 (Appellate Court of Illinois, 2002)
In re Tinya W.
Appellate Court of Illinois, 2002
Carr v. Cook County Hospital
Appellate Court of Illinois, 2001
People v. Jung
733 N.E.2d 1256 (Illinois Supreme Court, 2000)
Franzoni v. Hart Schaffner & Marx
Appellate Court of Illinois, 2000
Moran v. Erickson
Appellate Court of Illinois, 1998

Cite This Page — Counsel Stack

Bluebook (online)
678 N.E.2d 374, 287 Ill. App. 3d 303, 222 Ill. Dec. 762, 1997 Ill. App. LEXIS 188, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vernon-hills-iii-limited-partnership-v-st-paul-fire-marine-ins-co-illappct-1997.