D. M. Foley Co. v. North West Federal Savings & Loan Ass'n

461 N.E.2d 500, 122 Ill. App. 3d 411, 77 Ill. Dec. 877, 1984 Ill. App. LEXIS 1558
CourtAppellate Court of Illinois
DecidedMarch 2, 1984
DocketNo. 83—53
StatusPublished
Cited by19 cases

This text of 461 N.E.2d 500 (D. M. Foley Co. v. North West Federal Savings & Loan Ass'n) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. M. Foley Co. v. North West Federal Savings & Loan Ass'n, 461 N.E.2d 500, 122 Ill. App. 3d 411, 77 Ill. Dec. 877, 1984 Ill. App. LEXIS 1558 (Ill. Ct. App. 1984).

Opinion

PRESIDING JUSTICE MEJDA

delivered the opinion of the court:

Plaintiff-intervenor, D. M. Foley Company, Inc. (plaintiff), appeals from an order of the circuit court which granted defendant North West Federal Savings and Loan Association’s motion for summary judgment. Plaintiff contends that the trial court erred in determining that it failed to file its claim for a mechanic’s lien within four months of completing the work under a landscaping contract. Plaintiff also asserts that even if it failed to file its claim for lien within four months of completing the work under the contract, it nonetheless has valid lien rights against defendant because defendant had actual or constructive notice of the claim for lien before acquiring an interest in the property. For the reasons which follow, we affirm.

The various documents filed in the trial court indicate that defendant is mortgagee of the subject property pursuant to three mortgages recorded on March 9, 1976, November 1, 1978, and August 1, 1979, respectively. On September 9, 1980, plaintiff entered in to a written contract with Ballantrae Development, Inc. (Ballantrae), by which it agreed to provide landscaping services, including labor and materials, for the mortgaged land. The contract provided that plaintiff “guarantees all materials and workmanship specified for a period of 12 Months unless neglected by the Purchaser.” Incorporated into the contract was a “Scope of Work” list. Several photocopies of this list appear in the record, but these are largely illegible. Plaintiff admitted, however, in answering defendant’s interrogatories that all of the items on the scope of work list were delivered and completed on or about December 14, 1980. The complaint alleged that the contract was completed on May 29, 1981, within four months of the filing of the claim for lien on July 2, 1981. It was also alleged that on December 14, 1980, plaintiff made written demand on Ballantrae for payment in full for labor and materials delivered to the real estate. On October 19, 1982, defendant filed a motion for summary judgment, based on defendant’s contention that the contract was fiilly performed more than four months before the filing of the lien claim. The affidavit of Joan Slezak accompanied the motion and stated that she had reviewed documents produced by plaintiff and that none of them supported the contention that plaintiff had performed work under the contract within four months of the filing of the claim for lien. Plaintiff’s president, D. M. Foley, filed an affidavit in opposition to defendant’s motion which stated that plaintiff, “under the terms of the contract *** continued to perform maintenance-landscaping services at Ballantrae pursuant to the terms of the contract until May 29, 1981.” A letter dated June 3, 1981, signed by D. M. Foley as plaintiff’s president, and addressed to Ballantrae, was attached to the affidavit. The letter stated .that plaintiff was terminating “our guarantee” based on Ballantrae’s failure to pay invoices and to maintain the materials installed by plaintiff.

On December 15, 1982, the trial court granted defendant’s motion for summary judgment and dismissed the complaint. Plaintiff appeals from that order.

Opinion

Plaintiff’s first contention on appeal is that the trial court erred in determining that plaintiff had failed to file its claim for lien within four months of completing work under the contract. Section 7 of the Mechanics’ Liens Act provides that:

“No contractor shall be allowed to enforce such lien against or to the prejudice of any other creditor or incumbrancer or purchaser, unless within 4 months after completion, or if extra or additional work is done or material is delivered therefor within 4 months after the completion of such extra or additional work or the final delivery of such extra or additional material, he or she shall either bring an action to enforce his or her lien therefor or shall file in the office of the recorder of deeds of the county in which the building, erection or other improvement to be charged with the lien is situated, a claim for lien ***.” (Ill. Rev. Stat. 1981, ch. 82, par. 7.)

Plaintiff’s argument assumes that the four-month period provided by the statute begins upon completion of the contract, and further that the maintenance work allegedly performed under the contract after December 14, 1980, was sufficient to bring all of the work performed under the contract within the four-month period. “However, ‘completion’ as used in section 7 does not refer to completion of the contract. It means completion of the work for which a contractor seeks to enforce his lien. (W.G. Wood Co. v. Nyeswander (1914), 187 Ill. App. 354.)” (Dougherty-Janssen Co. v. Danage Enterprises, Inc. (1980), 80 Ill. App. 3d 1112, 1116, 400 N.E.2d 1023.) In the instant case there is no dispute that all of the items on the scope of work list in the contract were delivered and installed and payment demanded on or about December 14, 1980. This work was thus “completed” on that date within the meaning of the statute. Accordingly, the claim for lien or suit to enforce the lien should have been brought within four months of December 14, 1980, in order to have been timely. Because there is no genuine dispute that the claim for lien was not filed until July 2, 1981, the lien for the work performed and materials furnished on or before December 14, 1980, was not preserved. The trial court therefore properly granted summary judgment as to this issue. See generally Ill. Rev. Stat. 1981, ch. 110, par. 2 — 1005(c); Fooden v. Board of Governors (1971), 48 Ill. 2d 580, 587, 272 N.E.2d 497.

Plaintiff’s next argument, liberally construed, is that it is entitled to a lien for the work allegedly performed after December 14, 1980, which consisted of “[mjaintenance landscaping services,” according to plaintiff’s answer to defendant’s interrogatory. Defendant has not questioned the timeliness of the filing of the claim for lien with regard to these services. Nonetheless, an examination of the basis for the claim of lien is appropriate because we may affirm the trial court when justified in law for any reason. (Ozment v. Lance (1982), 107 Ill. App. 3d 348, 350, 437 N.E.2d 930.) In our view, whether plaintiff may be entitled to a lien for the value of this work depends on whether the “maintenance” services which he assertedly performed qualify as “landscape work” -within the meaning of section 1 of the Mechanics’ Liens Act. This statute provides in pertinent part that “[a]ny person who shall by any contract *** with the owner of a lot or tract of land, or with one whom the owner has authorized or knowingly permitted to contract, to improve the lot or tract of land, furnish material, fixtures, apparatus or machinery, forms or form work ***; or fill, sod, or excavate such lot or tract of land, or do landscape work thereon or therefor; *** has a lien upon the whole of such lot or tract of land ***.” (Emphasis added.) Ill. Rev. Stat. 1981, ch. 82, par. 1.

The phrase “landscape work” does not appear to be susceptible of precise definition and construction is necessary to determine whether “maintenance landscaping services” are within the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christopher B. Burke Engineering, LTD. v. Heritage Bank of Central Illinois
2015 IL App (3d) 140064 (Appellate Court of Illinois, 2015)
Christopher B. Burke Engineering, LTD. v. Heritage Bank of Central Illinois
2015 IL App (3d) 140064 (Appellate Court of Illinois, 2015)
Cordeck Sales v. Construction Systems
Appellate Court of Illinois, 2008
Cordeck Sales, Inc. v. Construction Systems, Inc.
887 N.E.2d 474 (Appellate Court of Illinois, 2008)
Luise, Inc. v. Village of Skokie
781 N.E.2d 353 (Appellate Court of Illinois, 2002)
Merchants Environmental Industries, Inc. v. SLT Realty Ltd. Partnership
731 N.E.2d 394 (Appellate Court of Illinois, 2000)
Vernon Hills III Limited Partnership v. St. Paul Fire & Marine Ins. Co.
678 N.E.2d 374 (Appellate Court of Illinois, 1997)
L.J. Keefe Co. v. Chicago & Northwestern Transportation Co.
678 N.E.2d 41 (Appellate Court of Illinois, 1997)
Braun-Skiba, Ltd. v. La Salle National Bank
665 N.E.2d 485 (Appellate Court of Illinois, 1996)
In Re T. Brady Mechanical Services Inc.
133 B.R. 441 (N.D. Illinois, 1991)
Watson v. Watson
578 N.E.2d 275 (Appellate Court of Illinois, 1991)
Cleveland Wrecking Co. v. Central National Bank
576 N.E.2d 1055 (Appellate Court of Illinois, 1991)
Mutual Services, Inc. v. Ballantrae Development Co.
510 N.E.2d 1219 (Appellate Court of Illinois, 1987)
Legault v. SUNCOAST LAWN SERV. INC.
486 So. 2d 72 (District Court of Appeal of Florida, 1986)
AAA Fencing Co. v. Raintree Development & Energy Co.
714 P.2d 289 (Utah Supreme Court, 1986)
DM Foley Co. v. NW FED. S & L ASS'N
461 N.E.2d 500 (Appellate Court of Illinois, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
461 N.E.2d 500, 122 Ill. App. 3d 411, 77 Ill. Dec. 877, 1984 Ill. App. LEXIS 1558, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-m-foley-co-v-north-west-federal-savings-loan-assn-illappct-1984.