W. G. Wood Co. v. Nysewander

187 Ill. App. 354, 1914 Ill. App. LEXIS 705
CourtAppellate Court of Illinois
DecidedJune 15, 1914
DocketGen. No. 19,305
StatusPublished
Cited by4 cases

This text of 187 Ill. App. 354 (W. G. Wood Co. v. Nysewander) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. G. Wood Co. v. Nysewander, 187 Ill. App. 354, 1914 Ill. App. LEXIS 705 (Ill. Ct. App. 1914).

Opinion

Mb. Justice Scanlan

delivered the opinion of the court.

The decree in this case finds that Haagan Otterson had a mechanic’s lien on the improvements on the real estate involved herein, but that the lien was a subsequent one to that of the appellee, the State Bank of Chicago, an incumbrancer, and the only question presented by this appeal is, did the chancellor err in decreeing that the said lien of the said Otterson was a subsequent lien on the said improvements to that of the appellee 1 The appellant contends that the chancellor should have found that the lien of Otterson was a prior one on said improvements to that of the appellee.

Section 7, ch. 82, of the Bevised Statutes of Illinois (Hurd’s) page 1479 (J. & A. f[ 7145), so far as it is material to the present inquiry, reads as follows:

“No contractor shall be allowed to enforce such lien against or to the prejudice of any other creditor or incumbrancer or purchaser, unless within four months after completion, or if extra or additional work is done or material is delivered therefor within four months after the completion of such extra or additional work or the final delivery of such extra or additional material, he shall either bring suit to enforce his lien therefor or shall file with the clerk of the Circuit. Court in the county in which the building, erection or other improvement to be charged with the lien is situated, a claim for lien, verified by the affidavit of himself, or his agent or employe, which shall consist of a brief statement of the contract, the balance due after allowing all credits and a sufficiently correct description of the lot, lots or tracts of land to identify the same. Such claim for lien may be filed at any time after the contract is made, and as to the owner may be filed at any time after the contract is mad<e and within two years after the completion of said contract, or the completion of any extra work or the furnishing of any extra material thereunder, and as to such owner may be amended at any time before the final decree.”

The decision of this case requires us to interpret the meaning of the italicized word “completion” in the above section. Appellant contends that the work done by the appellant was regular work (as distinguished from extra or additional work); that the first clause in the above section is the only part of the section that is applicable to appellant’s lien, and that the said clause is without force and effect, for the reason that there is no definite time fixed nor the happening of any certain event stated when the limitation should begin to run; that it is impossible to determine the meaning of the italicized word “completion”; that it might mean “completion of contract, completion of work, completion of building, completion of the last delivery of material, or any other number of events that might happen,” and that the courts have no power to interpolate words to supply the defect in the act; and appellant argues, as section 7 is without force and effect as to the lien of the appellant and as there is no other limitation section in the act, that applies to said lien, the chancellor erred in not finding that the lien of the appellant was a prior one to that of the appellee. Appellant further argues that (if this court should hold that it is possible to ascertain the meaning of the italicized word “completion” from a reading of the act) the only reasonable meaning that can be given to the said word is, completion of the contract.

In determining, if possible, the meaning of the italicized word “completion” in section 7, it is our duty to follow certain well known rules laid down by the courts. In the late case of Krome v. Halbert, 263 Ill. 172, it is said: “It is an elementary rule of construction that all parts of a statute must be considered together and not each by itself. * * # In the construction of a statute the courts are not confined to a literal meaning of the words, but the intention may be collected from the necessity or objects of the act and its words may be enlarged or restricted according to its intent. A thing which is within the intention is regarded within the statute though not within the letter, and a thing within the letter is not within the statute unless within the intention. When the intention can he collected from the statute, words may be modified, altered or supplied so as to obviate any repugnancy or inconsistency with such intention. The several provisions of a statute should be construed together in the light of the purpose and objects of the act, so as to give effect to the main intent, even though in so doing particular provisions are not construed according to their literal reading.” After a careful consideration of section 7 and the entire act, in the light of the above rule, we are satisfied that the meaning of the word “completion” is not so indefinite and uncertain that it cannot be ascertained. It seems reasonably plain to us that the word in question means completion of work or completion of the delivery of material for which a contractor (that is a contractor under the act) seeks to enforce his lien as against any other creditor, etc., under section 7. While it is essential to a right of lien of a contractor that some work be actually done or some material be actually furnished by him under his contract, it is not essential to his right of lien that the contract be fully performed on his part. Under section 4 of the act, (J. & A. jf 7142), a contractor is allowed a lien for a partial performance of the contract when there has been a breach of the contract by the owner of the land. The plain purpose of section 7 is to give notice to creditors, etc., of all existing liens on improvements on real estate. The meaning that we have given to the word in question carries out the intent and object of the section, and at the same time it does not conflict with the purpose and intent of any other part of the act. To give to the word the meaning contended for by the appellant, that is, that the said word means completion of the contract, would, in our judgment, tend to destroy the very purpose of the section. Under such an interpretation, creditors, incumbrancers or purchasers of existing liens on improvements might have practically no protection against lien claimants. In our opinion, the reasoning of the court in Schmidt v. Anderson, 253 Ill. 29, supports our conclusion as to the meaning of the word in question.

It is admitted that Otterson, on November 1, 1910, abandoned work upon the premises, and that no work was thereafter done by him on the buildings. To the bill filed by the complainant and to the cross-bill filed by Bye et al., Otterson answered on June 17, 1911, that he discontinued work upon the premises in question on October 21, 1910, because Nysewander had neglected and failed to make payments due him under the contract, and that this default continuing for ten days thereafter, he abandoned work upon the premises on November 1,1910. Otterson asked that this answer be considered as an intervening petition, and he prayed that the court might decree that he be given a lien upon the premises for the sum of eight thousand dollars.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DM Foley Co. v. NW FED. S & L ASS'N
461 N.E.2d 500 (Appellate Court of Illinois, 1984)
D. M. Foley Co. v. North West Federal Savings & Loan Ass'n
461 N.E.2d 500 (Appellate Court of Illinois, 1984)
Dougherty-Janssen Co. v. Danage Enterprises, Inc.
400 N.E.2d 1023 (Appellate Court of Illinois, 1980)
Components, Inc. v. Walter Kassuba Realty Corp.
381 N.E.2d 42 (Appellate Court of Illinois, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
187 Ill. App. 354, 1914 Ill. App. LEXIS 705, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-g-wood-co-v-nysewander-illappct-1914.