AAA Fencing Co. v. Raintree Development & Energy Co.

714 P.2d 289, 26 Utah Adv. Rep. 12, 1986 Utah LEXIS 719
CourtUtah Supreme Court
DecidedJanuary 13, 1986
Docket19870
StatusPublished
Cited by35 cases

This text of 714 P.2d 289 (AAA Fencing Co. v. Raintree Development & Energy Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AAA Fencing Co. v. Raintree Development & Energy Co., 714 P.2d 289, 26 Utah Adv. Rep. 12, 1986 Utah LEXIS 719 (Utah 1986).

Opinion

PER CURIAM:

This appeal arises out of a mechanics’ lien foreclosure action.

Plaintiffs furnished labor and materials on premises purchased under contract by defendant Raintree Development and Energy (Raintree) and completed their work on January 10, 1982. When Raintree failed to pay, plaintiffs placed a timely lien on the premises but then sued Raintree for breach of oral contract. Plaintiffs obtained a money judgment against Raintree on January 14, 1983.

On June 29, 1982, the sellers of the property here at issue sold the property to defendant Galen J. Ross (Ross) when Rain-tree defaulted under its contract. Ross later brought suit to terminate the rights of Raintree to the property and to quiet title against plaintiffs and Raintree. Rain-tree was served with process but failed to answer or otherwise respond. On May 2, 1983, Ross obtained judgment against Raintree quieting title to the property and declaring all of Raintree’s rights, title, interest and lien or estate in the land null and void.

Meanwhile, on March 7, 1983, after they discovered that Raintree was judgment-proof against their money judgment, plaintiffs instituted their mechanics’ lien foreclosure action against defendants. Ross answered, but failed to plead the statutory bar as an affirmative defense. Plaintiffs’ action was consolidated with Ross’s quiet title action for purposes of trial. Both parties moved for summary judgment, and Ross for the first time raised the issue that plaintiffs were barred from bringing the foreclosure action as it was not filed in a timely manner. The court granted plaintiffs’ motion for summary judgment and entered judgment against Ross in the amount of the lien, together with costs and attorney fees. Ross filed motions for an amendment of findings and a new trial which were denied. This appeal followed.

Ross appeals on several grounds, but his claim that plaintiffs’ foreclosure action was barred for failure to institute their claim within the time prescribed by section 38-1-11 of the mechanics’ lien statute is disposi-tive here. That section provides that actions to enforce liens must be begun within twelve months after the completion of the original contract. 1 Plaintiffs concede that they filed their complaint late, but argue that Ross has waived his rights to the statutory bar as he failed to plead it as an affirmative defense. They also claim that filing a lawsuit is only one form of “taking action to enforce the lien,” and that filing a notice of lien is another action which they took in time. Moreover, continues their response, the foreclosure of a mechanics’ lien is a matter of equity, and this Court should therefore construe the statute liberally in accordance with section 68-3-2 of the Utah Code.

Properly framed, the issue before us is whether an untimely action under our mechanics’ lien statute affects the rights or merely the remedies of the parties. We disagree with plaintiffs that it affects merely their remedies and is therefore subject to waiver and estoppel as are procedural statutes of limitations and hold instead *291 that it is jurisdictional and forecloses their rights.

Mechanics’ liens are statutory creatures unknown to the common law. The purpose of the Utah mechanics’ lien law is to provide protection to those who enhance the value of a property by supplying labor or materials. Interiors Contracting Inc. v. Navalco, Utah, 648 P.2d 1382 (1982). Although liens and pleadings arising under the statute will be liberally construed to effect the desired object, compliance with the statute is required before a party is entitled to the benefits created by the statute. First Security Mortgage Co. v. Hansen, Utah, 631 P.2d 919 (1981); see also Schofield v. Copeland Lumber Yards, Inc., Nev., 692 P.2d 619 (1985); Lewis v. Wanamaker Baptist Church, 10 Kan.App.2d 99, 692 P.2d 397 (1984).

The law is clear in this jurisdiction that a mechanics’ lien foreclosure action must be brought within twelve months after the original contract between the lienor and the lienee is completed, or relief will not lie. Motivated Management International v. Finney, 604 P.2d 467 (1979) (dictum); Roberts v. Hansen, 25 Utah 2d 190, 479 P.2d 345 (1971); Totorica v. Thomas, 16 Utah 2d 175, 397 P.2d 984 (1965). That failure to enforce a mechanics’ lien within the statutory period is a jurisdictional question has not heretofore been decided by this Court. We therefore look to our sister jurisdictions with similar mechanics’ lien statutes.

The definitive statement of the law on this issue was first rendered in Fleshman v. Whiteside, 148 Or. 73, 34 P.2d 648 (1934), 93 A.L.R. 1456. The court in that case rejected the plaintiffs’ identical argument that defendants had waived the defense of the statutory bar by failing to raise it by demurrer or answer and stated in pertinent part:

While the contrary is held in California, 2 it is the rule in most jurisdictions that [the time limit provided for actions to enforce mechanics’ liens] is not a statute of limitations, which is waived if not pleaded, but a statute limiting the duration of the lien. The remedy forms a part of the right and must be pursued within the time prescribed, or else both are lost. If an action is not brought within the time limited, the court is without jurisdiction to decree a foreclosure. ...

34 P.2d at 650, 93 A.L.R. at 1459.

That rule is still good law today. It was echoed in Diamond National Corp. v. Dwelle, 164 Conn. 540, 325 A.2d 259 (1973), where the court addressed the same issue and citing Fleshman v. Whiteside pronounced the statutory bar substantive or jurisdictional rather than procedural or personal. As the mechanics’ lien is a creature of statute and fixes the time within which the right must be enforced, the court reasoned that “it is a limitation of the liability itself as created, and not of the remedy alone.” Similar results were reached in Well Done Heating & Sheet Metal Co. v. Ralph Schwartz & Associates, 112 Ill.App.3d 438, 68 Ill.Dec. 3, 445 N.E.2d 451 (1983), accord Garbe Iron Works, Inc. v. Priester, 99 Ill.2d 84, 75 Ill.Dec. 428, 457 N.E.2d 422 (1983) (dictum); Regal Wood Products, Inc. v. First Wisconsin Nation *292 al Bank of Milwaukee, Fla.App., 347 So.2d 643 (1977); Federal National Bank and Trust Co. of Shawnee v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Copper Hills Custom Homes v. Griffin
2024 UT App 110 (Court of Appeals of Utah, 2024)
Sunstone Realty v. Bodell Construction
2024 UT 9 (Utah Supreme Court, 2024)
Zion Village Resort v. Pro Curb USA
2020 UT App 167 (Court of Appeals of Utah, 2020)
Jordan Const v. Fed Nat Mort
2017 UT 28 (Utah Supreme Court, 2017)
2 Ton Plumbing, L.L.C. v. Thorgaard
2015 UT 29 (Utah Supreme Court, 2015)
Victor Plastering, Inc. v. SWANSON BUILDING MATERIALS, INC.
2008 UT App 474 (Court of Appeals of Utah, 2008)
Forsberg v. Bovis Lend Lease, Inc.
2008 UT App 146 (Court of Appeals of Utah, 2008)
Foothill Park, LC v. Judston, Inc.
2008 UT App 113 (Court of Appeals of Utah, 2008)
Uhrhahn Construction & Design, Inc. v. Hopkins
2008 UT App 41 (Court of Appeals of Utah, 2008)
Sill v. Hart
2007 UT 45 (Utah Supreme Court, 2007)
Pearson v. Lamb
2005 UT App 383 (Court of Appeals of Utah, 2005)
R.A. McKell Excavating, Inc. v. Wells Fargo Bank, N.A.
2004 UT 48 (Utah Supreme Court, 2004)
A.K. & R. Whipple Plumbing & Heating v. Guy
2004 UT 47 (Utah Supreme Court, 2004)
J v. Hatch Construction, Inc. v. Kampros
971 P.2d 8 (Court of Appeals of Utah, 1998)
First General Services v. Perkins
918 P.2d 480 (Court of Appeals of Utah, 1996)
World Peace Movement of America v. Newspaper Agency Corp.
879 P.2d 253 (Utah Supreme Court, 1994)
For-Shor Co. v. Early
828 P.2d 1080 (Court of Appeals of Utah, 1992)
Interiors Contracting, Inc. v. Smith, Halander & Smith Associates
827 P.2d 963 (Court of Appeals of Utah, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
714 P.2d 289, 26 Utah Adv. Rep. 12, 1986 Utah LEXIS 719, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aaa-fencing-co-v-raintree-development-energy-co-utah-1986.