Interiors Contracting, Inc. v. Smith, Halander & Smith Associates

827 P.2d 963, 181 Utah Adv. Rep. 52, 1992 Utah App. LEXIS 21, 1992 WL 41596
CourtCourt of Appeals of Utah
DecidedMarch 2, 1992
Docket900642-CA
StatusPublished
Cited by2 cases

This text of 827 P.2d 963 (Interiors Contracting, Inc. v. Smith, Halander & Smith Associates) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Interiors Contracting, Inc. v. Smith, Halander & Smith Associates, 827 P.2d 963, 181 Utah Adv. Rep. 52, 1992 Utah App. LEXIS 21, 1992 WL 41596 (Utah Ct. App. 1992).

Opinion

OPINION

BILLINGS, Associate Presiding Judge:

Coonradt Construction Company (Coon-radt) appeals from a judgment concluding Coonradt did not file its mechanic’s lien timely and, therefore, the lien is invalid. We reverse and remand.

FACTS

Walker, McElliot, Wilkinson & Associates (WMW) purchased the GSA Photo Lab Building (Photo Lab) in 1984 from appellee Smith, Halander & Smith Associates (SHS). 1

On February 24, 1987, WMW entered into a contract with the tenant, United States of America, General Services Administration (GSA), under which GSA agreed to pay WMW $99,997.00 to make certain improvements to the Photo Lab by April 17, 1987. At the same time, WMW contracted with appellant Coonradt, a general contractor, to make the improvements required under WMW’s contract with GSA.

On April 29, 1987 and May 1, 1987, GSA representatives inspected the improvements to the Photo Lab and determined there were four minor items remaining to be completed: (1) poor caulking on a corner of one of the rooms needed to be reapplied for a smooth, uniform appearance; (2) the placement and leveling of one of the rooftop air conditioning units was not a good long-term solution and needed to be replaced; (3) an air test and balance report was needed; and (4) an air condenser pipe penetrating through the roof needed a weatherproof seal.

On May 14,1987, Coonradt sealed the air condenser pipe penetrating through the roof with tar. This task was completed in a short time at a cost of no more than $1.00. A subcontractor adjusted the computer room doors and installed weather stripping around them on May 15, 1987. This work took two hours, at a billing rate of $13.49 per hour. Finally, on June 29, 1987, Coonradt installed non-skid pads and a threshold piece on the computer room ramp. The parties dispute whether Coon-radt repaired the support for the rooftop air conditioner. There is no evidence in the record that Coonradt ever provided the air test and balance report.

On May 4, 1987, WMW sent an invoice to GSA, requesting the full contract price. GSA began preparing its payment voucher for the full contract price by at least May 18, 1987 and obtained approval from all necessary officials by no later than May 28, 1987. A memo to GSA’s file dated May 20, 1987 acknowledges “4 very minor ‘punch list’ work items” but “certif[ies] that all major items of work” on the contract “have been satisfactorily completed.” On May 27, 1987, GSA sent a letter to WMW listing the four items to be completed and requesting that the work be performed by June 19, 1987, but thanking WMW “for a job well *965 done.” Although GSA paid WMW in full on or about June 19, 1987, WMW did not pay Coonradt. Coonradt filed its notice of mechanic’s lien against the Photo Lab on August 19, 1987. On August 24, 1987, WMW paid Coonradt $30,000.00.

The trial court held Coonradt’s lien invalid because Coonradt did not file its notice of lien within 100 days of the completion of the contract. The trial court concluded that work on the Photo Lab was substantially completed on or before May 10, 1987, and that subsequent work was insubstantial, trivial, and could not be used to extend the statutory lien filing period.

On appeal, Coonradt claims the trial court committed reversible error by applying the wrong legal standard in determining its lien was untimely filed.

TIMELINESS OF FILING OF MECHANIC’S LIEN NOTICE

Coonradt urges this court to reverse the trial court’s invalidation of its lien because of the remedial function of mechanic’s lien statutes and the accompanying principle that such statutes should be broadly interpreted. It is well settled that “ ‘[t]he purpose of the mechanic’s lien act is remedial in nature and seeks to provide protection to laborers and materialmen who have added directly to the value of the property of another by their materials or labor.’ ” Projects Unlimited, Inc. v. Copper State Thrift & Loan Co., 798 P.2d 738, 743 (Utah 1990) (quoting Colder Bros. Co. v. Anderson, 652 P.2d 922, 924 (Utah 1982)); accord Butterfield Lumber, Inc. v. Peterson Mortgage Corp., 815 P.2d 1330, 1334 (Utah App.1991). We liberally construe lien statutes to implement their protective purpose. See AAA Fencing Co. v. Raintree Dev. and Energy Co., 714 P.2d 289, 291 (Utah 1986); Butterfield Lumber, 815 P.2d at 1334. However, in order to claim the benefits of the mechanic’s lien statutes, Coonradt has the burden of proving compliance with the statutory requirements, including timeliness of filing notice. See Projects Unlimited, 798 P.2d at 743; Govert Copier Painting v. Van Leeuwen, 801 P.2d 163, 172 (Utah App.1990).

Utah Code Ann. § 38-1-7 specifies the time period in which Coonradt, as an original contractor, must file a notice of mechanic’s lien.

(1) Every original contractor within 100 days after the completion of his contract, and except as provided in this section, every person other than the original contractor who claims the benefit of this chapter within 80 days after furnishing the last material or performing the last labor for or on any land, building, improvement, or structure shall file for record with the county recorder of the county in which the property, or some part of the property, is situated, a written notice to hold and claim a lien.

Utah Code Ann. § 38-1-7 (Supp.1987) (emphasis added). In interpreting this statutory filing requirement, Utah courts have articulated a two-prong test. A contract is “completed” and the 100-day filing period begins to run when the work has been “substantially completed,” leaving only minor or trivial work to be accomplished, see Wilcox v. Cloward, 88 Utah 503, 56 P.2d 1, 6-7 (1936), and “has been accepted by the owner.” Carlisle v. Cox, 29 Utah 2d 136, 506 P.2d 60, 62 (1973). 2

In Wilcox, the court explained the first part of the test as one of deciding whether the disputed work “was a substantial continuation of the work on the contract or a minor or trivial adjustment or the remedying of trivial imperfections.” Wilcox, 56 *966 P.2d at 6. 3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ellsworth Paulsen Construction Co. v. 51-SPR, L.L.C.
2006 UT App 353 (Court of Appeals of Utah, 2006)
Interiors Contracting, Inc. v. Smith, Halander & Smith Associates
881 P.2d 929 (Court of Appeals of Utah, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
827 P.2d 963, 181 Utah Adv. Rep. 52, 1992 Utah App. LEXIS 21, 1992 WL 41596, Counsel Stack Legal Research, https://law.counselstack.com/opinion/interiors-contracting-inc-v-smith-halander-smith-associates-utahctapp-1992.