Calder Bros. Co. v. Anderson

652 P.2d 922, 1982 Utah LEXIS 1037
CourtUtah Supreme Court
DecidedAugust 24, 1982
Docket17449, 17458 and 17459
StatusPublished
Cited by34 cases

This text of 652 P.2d 922 (Calder Bros. Co. v. Anderson) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Calder Bros. Co. v. Anderson, 652 P.2d 922, 1982 Utah LEXIS 1037 (Utah 1982).

Opinion

STEWART, Justice:

In case No. 17459 Calder Bros. Company (Calder Bros.) brought an action to foreclose a $490,000 purchase money mortgage against real property sold to Ross Anderson. This action was consolidated in the district court with two other actions brought by independent contractors to foreclose their mechanics’ liens against the same property (Nos. 17449 and 17458). The judgment in favor of Calder Bros, in No. 17459 is appealed by defendants Star Palace, Inc., Michael Crowley, and Signs, Inc., on the grounds that the lower court erred in entering default judgments against them, in denying Signs’ motion to substitute Micro-Investment as the real party in interest, and in denying Star Palace’s motion to vacate an order appointing a receiver. Jarvis & Sons Electric Co., Inc. (Jarvis), Dunn Construction Co. (Dunn), and Royden, Inc. (Royden), appeal the district court’s judgments in Nos. 17449 and 17458, establishing Calder Bros.’ purchase money mortgage priority over their mechanics’ liens.

I. The Mortgage and the Mechanics’ Liens (Nos. 17449 and 17458)

On June 14, 1978, Calder Bros, conveyed the real property commonly known as the Star Palace to Ross Anderson by warranty deed. On the same day, Anderson executed and delivered a purchase money mortgage to Calder Bros. The mortgage was not recorded until June 27, 1978. Shortly after the mortgage was recorded, a building permit was obtained from Provo City to make improvements on the property based on a submitted set of plans.

After the deed and mortgage were executed but before the mortgage was recorded, Anderson hired two young men on an hourly basis to help cut weeds, cut down two trees, and grout cracks in the building. They were paid $18.95 for their labor. In addition, a painter was hired to paint the building with paint supplied by an associate of Anderson. He was paid $850. No mechanics’ liens were filed as a result of any of the above described work.

After Calder Bros.’ mortgage was recorded, Anderson hired Jarvis to perform electrical work, Dunn to resurface the parking area around the building, and Royden to furnish labor and materials. On this appeal, they claim that the trial court erred in holding that their mechanics’ liens were subsequent in priority to the purchase money mortgage and that their priority should be established as of the commencement of the maintenance work which occurred prior to the recording of the mortgage.

*924 Utah Code Ann., 1953, § 38-1-5 provides the guidelines for determining the priority of the liens in this case. That section provides:

Priority — Over other encumbrances.— The liens herein provided for shall relate back to, and take effect as of, the time of the commencement to do work or furnish materials on the ground for the structure or improvement, and shall have priority over any lien, mortgage or other encumbrance which may have attached subsequently to the time when the building, improvement or structure was commenced, work begun, or first material furnished on the ground; also over any lien, mortgage or other encumbrance of which the lien holder had no notice and which was unrecorded at the time the building, structure or improvement was commenced, work begun, or first material furnished on the ground.

The purpose of the mechanics’ lien act is remedial in nature and seeks to provide protection to laborers and materialmen who have added directly to the value of the property of another by their materials or labor. First of Denver Mortgage Investors v. Zundel and Assoc., Utah, 600 P.2d 521 (1979); Rio Grande Lumber Co. v. Darke, 50 Utah 114, 167 P. 241 (1917). To accomplish that purpose, the phrase “commencement to do work,” as used in the mechanics’ lien statute, is construed in favor of lien claimants. Bankers Trust Co. v. El Paso PreCast Co., 192 Colo. 468, 560 P.2d 457 (1977). See also First of Denver Mortgage Investors, supra. Materialmen’s and mechanics’ liens resulting from materials furnished or labor performed relate back to and attach as of the date of the commencement of the first work on the improvement or structure involved. First of Denver Mortgage Investors, supra.

For one contractor’s lien to relate back to the commencement of work or supplying of materials by another contractor however, both contractors’ projects must have been performed in connection with what is essentially a single project performed under a common plan prosecuted with reasonable promptness and without material abandonment. See, e.g., Miller Electric Co. of Miami, Inc. v. Sweeny, Fla.App., 199 So.2d 734 (1967); National Lumber Co. v. Farmer & Son, Inc., 251 Minn. 100, 87 N.W.2d 32 (1957); Fryman v. McGhee, 108 Ohio App. 501, 163 N.E.2d 63 (1958). Ordinary maintenance or cleanup work does not serve as a basis for “tacking” so as to fix an earlier lien date under § 38-1-5 for labor and materials supplied. 57 C.J.S. Mechanics Liens § 179 (1948).

The building permit, applied for June 20, 1978, a date preceding the recording of Calder Bros.’ mortgage, was issued June 28, 1978, a date subsequent to the recording. Drawings made in November, 1977, and later submitted with the application for a building permit, disclosed alterations principally related to the interior of the building. The only exterior improvement shown is a drawing of a building with a peaked roof to replace the existing flat roof.

Nothing in the plans suggested that the painting and maintenance work was part of an improvement project envisioned by the new owners. The work performed prior to the recording of Calder Bros.’ mortgage included painting the building exterior, cutting down two trees, clearing weeds, and placing grout in the building. At no point up to and including the time Calder Bros.’ mortgage was recorded, was it evident from the inspection of the premises that an improvement had been commenced. 1 No materials were delivered to the premises prior to the recording of Calder Bros.’ mortgage.

The trial court found that the cleanup and painting were insubstantial and constituted ordinary and necessary maintenance *925 rather than the commencement of an improvement to the building within the meaning of the mechanics’ lien statute. In addition, the court found that improvements to the exterior of the building subsequent to the recording of Calder Bros.’ mortgage rendered the painting “to a large measure valueless.” Therefore, it follows that Jarvis & Sons, Dunn, and Royden could not establish the date of their liens as of the commencement of the general maintenance and cleanup work.

In sum, there is ample support in the record to support the trial court’s findings that the liens in favor of Jarvis, Dunn, and Royden did not attach prior to the Calder Bros.’ mortgage and do not have priority over the mortgage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kielkowski v. Kielkowski
2015 UT App 59 (Court of Appeals of Utah, 2015)
Pentalon Construction, Inc. v. Rymark Properties, LLC
2015 UT App 29 (Court of Appeals of Utah, 2015)
2 Ton Plumbing, L.L.C. v. Thorgaard
2015 UT 29 (Utah Supreme Court, 2015)
All Clean, Inc. v. Timberline Properties
2011 UT App 370 (Court of Appeals of Utah, 2011)
Roth v. Joseph
2010 UT App 332 (Court of Appeals of Utah, 2010)
EDSA/CLOWARD, LLC v. Klibanoff
2008 UT App 284 (Court of Appeals of Utah, 2008)
Davis v. Goldsworthy
2008 UT App 145 (Court of Appeals of Utah, 2008)
Foothill Park, LC v. Judston, Inc.
2008 UT App 113 (Court of Appeals of Utah, 2008)
Lundahl v. Quinn
2003 UT 11 (Utah Supreme Court, 2003)
Udy v. Udy
893 P.2d 1097 (Court of Appeals of Utah, 1995)
Schoney v. Memorial Estates, Inc.
863 P.2d 59 (Court of Appeals of Utah, 1993)
Richards v. Security Pacific National Bank
849 P.2d 606 (Court of Appeals of Utah, 1993)
Interiors Contracting, Inc. v. Smith, Halander & Smith Associates
827 P.2d 963 (Court of Appeals of Utah, 1992)
Richins v. Delbert Chipman & Sons Co.
817 P.2d 382 (Court of Appeals of Utah, 1991)
Projects Unlimited, Inc. v. Copper State Thrift & Loan Co.
798 P.2d 738 (Utah Supreme Court, 1990)
Nu-Trend Electric, Inc. v. Deseret Federal Savings & Loan Ass'n
786 P.2d 1369 (Court of Appeals of Utah, 1990)
KETCHUM, KONKEL v. Heritage Mt.
784 P.2d 1217 (Court of Appeals of Utah, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
652 P.2d 922, 1982 Utah LEXIS 1037, Counsel Stack Legal Research, https://law.counselstack.com/opinion/calder-bros-co-v-anderson-utah-1982.