H. B. Deal Construction Co. v. Labor Discount Center, Inc.

418 S.W.2d 940, 1967 Mo. LEXIS 817
CourtSupreme Court of Missouri
DecidedSeptember 11, 1967
Docket51939
StatusPublished
Cited by40 cases

This text of 418 S.W.2d 940 (H. B. Deal Construction Co. v. Labor Discount Center, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. B. Deal Construction Co. v. Labor Discount Center, Inc., 418 S.W.2d 940, 1967 Mo. LEXIS 817 (Mo. 1967).

Opinion

*943 HOUSER, Commissioner.

This is an equitable proceeding to impress a mechanic’s lien on the real property located at 7995 Dunn Road in an unincorporated area of St. Louis County in the amount of $178,182.80 plus interest and to have the mechanic’s lien declared superior to the lien of a deed of trust and a security agreement of record. Plaintiff is the general contractor, H. B. Deal Construction Company, a corporation. Defendants named in the petition are the owner, Labor Discount Center, Inc.; A. L. Uebel, trustee, and Charles W. Sunderman, beneficiary, of a $2,000,000 deed of trust on the property; the trustee and named beneficiary, General Title Service Corporation, named in a security agreement affecting the property; six banks claiming a beneficial interest in the two million dollar deed of trust, and nine other mechanic’s lien claimants, five of whom were subcontractors and four of whom were contractors who dealt directly with the owner. An excavating and grading contractor who also contracted directly with the owner was permitted to intervene and Seventeen Ninety-Five Dunn Road, Inc., purchaser of the land and improvements at a foreclosure sale under the two million dollar deed of trust, conducted after the institution of this action, was added as a defendant.

Defendant Labor Discount Center, Inc. filed an answer and cross-petition seeking damages against the six banks for breach of contract, fraud and conspiracy. On motion the trial court ordered the separate trial of the mechanic’s lien controversies and the issues raised in that cross-petition, so those issues are not involved in this appeal.

Defendant State Bank and Trust Company of Wellston, General Title Service Corporation and the latter’s trustee, filed answers and a counterclaim against the general contractor for $316,141.48 damages from the filing of mechanic’s liens by the general contractor and its subcontractors.

The five subcontractors each sought judgment against the general contractor for the balance due on their accounts and the four defendants contracting directly with the owner asked judgment against the owner for the balance due each of them. Each of these defendants by crossclaim or crossbill also prayed for a mechanic’s lien upon the buildings, improvements and land. Appropriate answers and replies were filed.

Judgment was rendered (1) for the general contractor and against the owner for a total amount of $197,604.73, including interest, fixing a mechanic’s lien against the property and declaring the mechanic’s lien superior to the liens of the deed of trust and security agreement; (2) for the five subcontractors and the four original contractors and against the general contractor for the amounts of their respective claims, which were adjudged to be paid out of the judgment in favor of the general contractor (also fixing a mechanic’s lien on the property for each of the nine and adjudging their liens superior to the liens of the -deed of trust and security agreement) ; (3) for the general contractor and against the bank, title service company and its trustee on the counterclaim; (4) declaring the aggregate judgment of $228,-172.46 plus interest paramount to the purchase by Seventeen Ninety-Five Dunn Road, Inc. at foreclosure of the property under the two million dollar deed of trust, and (5) declaring the judgment final for the purpose of appeal under § 512.020, V.A.M.S.

The six banks, the title service company and its trustee, and the purchaser at foreclosure appealed. The owner did not appeal.

On November 29, 1962 the then beneficial owners of the approximately 106-acre tract in question contracted with Labor Discount Center, Inc. for its sale and purchase. On the same day the beneficial owners and the record title holder executed quitclaim deeds conveying the tract to Labor Discount Center, Inc., subject to an out *944 standing note and deed of trust on the property.

On December 5, 1962 Labor Discount Center, Inc. entered into a contract with H. B. Deal Construction Company as general contractor for the erection thereon of a building to be used as a discount house and shopping center. Deal contracted to furnish all material and do all work according to specifications and drawings prepared by the architects and to erect and construct the commercial building, parking area, fences, sidewalks, appurtenances and improvements as provided for in the contract documents, for the actual cost of the work plus a fixed fee of $50,000, “guaranteeing the total cost of the work described in this contract, including said Fixed Fee, shall not exceed the sum of One Million Two Hundred Fifty Thousand And No/100 Dollars ($1,250,000.00).” This sum was referred to in the contract as “The maximum guaranteed sum.” The contract was made contingent upon the signing of a satisfactory construction and dispersing escrow agreement providing for the deposit with the escrowee of the funds necessary for the payment of the contract amount. In a supplemental agreement it was provided that the maximum guaranteed price was based on several specified changes in the plans and specifications, and that “The contract price only includes the items of work clearly outlined in this contract, and does NOT include any work in connection with tenant changes, which are not indicated on the drawings.” Article 8 dealt with the securing of payment of the fixed fee of the general contractor. Article 15 of the General Conditions made provisions for changes in the work, as follows: “The Owner, without invalidating the Contract, may order extra work or make changes by altering, adding to or deducting from the work, the Contract Sum being adjusted accordingly. All such work shall be executed under the conditions of the original contract except that any claim for extension of time caused thereby shall be adjusted at the time of ordering such change.

“In giving instructions, the Architect shall have authority to make minor changes in the work, not involving extra cost, and not inconsistent with the purposes of the building, but otherwise, except in an emergency endangering life or property, no extra work or change shall be made unless in pursuance of a written order from the Owner signed or countersigned by the Architect, or a written order from the Architect stating that the Owner has authorized the extra work or change, and no claim for an addiion (sic) to the contract sum shall be valid unless so ordered. •

“The value of any such extra work or change shall be determined in one or more of the following ways:

“a) By estimate and acceptance in a lump sum.

“b) By unit prices named in the contract or subsequently agreed upon.

“c) By cost and percentage or by cost and a fixed fee.”

On December 5, 1962 (the date of execution of the construction contract) the general contractor’s project manager, John Mincher, who was instructed to “get the. job going,” spent 3 hours visiting the site, walking over the ground to acquaint himself with any of the problems involved in the site work. On December 6 he returned to the site and spent 4 hours getting acquainted with the conditions such as trees and amount of grading to be done, preparatory to awarding subcontracts. On December 10 he and a laborer performed surveying work to determine the limits of the property in order to locate the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pentalon Construction, Inc. v. Rymark Properties, LLC
2015 UT App 29 (Court of Appeals of Utah, 2015)
Bob DeGeorge Associates, Inc. v. Hawthorn Bank
377 S.W.3d 592 (Supreme Court of Missouri, 2012)
Glenstone Block Co. v. Pebworth
264 S.W.3d 703 (Missouri Court of Appeals, 2008)
Space Planners Architects, Inc. v. Frontier Town-Missouri, Inc.
107 S.W.3d 398 (Missouri Court of Appeals, 2003)
Brockman v. Soltysiak
49 S.W.3d 740 (Missouri Court of Appeals, 2001)
Glenda S. Scoville v. United States
250 F.3d 1198 (Eighth Circuit, 2001)
Gilmartin Bros., Inc. v. Kern
916 S.W.2d 324 (Missouri Court of Appeals, 1995)
Dave Kolb Grading, Inc. v. Lieberman Corp.
837 S.W.2d 924 (Missouri Court of Appeals, 1992)
Winn-Senter Construction Co. v. Katie Franks, Inc.
816 S.W.2d 943 (Missouri Court of Appeals, 1991)
KETCHUM, KONKEL v. Heritage Mt.
784 P.2d 1217 (Court of Appeals of Utah, 1989)
Markway Construction Co. v. Kirchenbauer
769 S.W.2d 836 (Missouri Court of Appeals, 1989)
In Re Gateway Center Building Investors, Ltd.
95 B.R. 647 (E.D. Missouri, 1989)
Calder Bros. Co. v. Anderson
652 P.2d 922 (Utah Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
418 S.W.2d 940, 1967 Mo. LEXIS 817, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-b-deal-construction-co-v-labor-discount-center-inc-mo-1967.