Vasquez v. Village Center, Inc.

362 S.W.2d 588, 1962 Mo. LEXIS 562
CourtSupreme Court of Missouri
DecidedDecember 11, 1962
Docket49448
StatusPublished
Cited by42 cases

This text of 362 S.W.2d 588 (Vasquez v. Village Center, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vasquez v. Village Center, Inc., 362 S.W.2d 588, 1962 Mo. LEXIS 562 (Mo. 1962).

Opinion

*590 COIL, Commissioner.

Respondent L. Vasquez, the plaintiff below, an excavating and grading contractor, brought an action against Village Center, Inc., for $12,606.12 and interest thereon, the balance due for labor performed allegedly at the special instance and request of Village Center, and to have real estate owned by appellant John Dooly impressed with a mechanic’s lien for the amount of such judgment. The jury returned a verdict, including interest, for $16,271.91, and found that the plaintiff had perfected and established the right to a mechanic’s lien against the realty. Dooly alone has appealed and contends that the judgment impressing his property with a mechanic’s lien was void because the trial court was without jurisdiction, erred in failing to direct a verdict for him, and erred in giving instructions on behalf of plaintiff.

All the evidence in the case was adduced by plaintiff and we state it from a standpoint favorable to him. Edward Bilhorn testified that he and his brother-in-law, James J. Nicholson, and Terry Nicholson, from 1953 until sometime in 1956, constituted the officers and directors and owners of all the stock of Nicholson & Bilhorn, Inc., a corporation which was engaged in real estate development and that, beginning in 1954, that company was engaged in developing about 200 acres of land in the vicinity of Manchester and New and Old Ballwin Roads in St. Louis County involving approximately 500 homesites in various sections of an area known as Ball-win Hills. Those homesites were developed (construction began in 1954) by a subsidiary corporation of Nicholson & Bilhorn, Inc., viz., Suburban Homes, Inc. A plot of ground fronting approximately 1,300 feet on the south side of Manchester Road and running southwardly for approximately 300 feet was to be developed as a commercial tract (a shopping center) by another subsidiary corporation of Nicholson & Bilhorn, Inc., to be known as Village Center, Inc., to be owned and operated by the same three individuals, i. e., the two Nicholsons and Edward Bilhorn.

All of the land, including the homesites and the commercial property, was acquired under one purchase contract and record title was taken in the names of James Nicholson and his wife and, at some later time (the exact date was not shown), all of the land was deeded by James Nicholson and his wife to Nicholson & Bilhorn, Inc. The plaintiff did grading and excavating in connection with the development of the residential homesites during 1954, 1955, and 1956.

Mr. Bilhorn, on behalf of Village Center, Inc. (Village Center, Inc. had not then been incorporated, a matter to which we' shall later refer), ordered plans for the development of the tract from an architect. Those plans, dated February 20, 1955, purported to show a floor plan for buildings and facilities, including a parking area for the proposed shopping center. According to the testimony of both the plaintiff and Edward Bilhorn, in April or May of 1955 Mr. Vasquez attended a conference on the proposed commercial site. Present also were Edward Bilhorn, James Nicholson, and Terry Nicholson, and probably the construction superintendent for Nicholson & Bilhorn, Inc. The plans, including a sketch which showed the elevations for the proposed buildings, were displayed to Mr. Vasquez and the work that it was desired that he perform was explained to him. The land in question was rough, there was a large creek meandering through it, there was a steep hill on the southwest corner, some low and swampy parts in the center and there were some places where the land adjoining Manchester Road was six feet below the level of that road. Plaintiff was told that he was to realign the creek, prepare the ground for parking lots, prepare subgrades for the planned buildings and provide access to the shopping center along the frontage on Manchester. The rates were agreed upon in detail providing for hourly rates for the use of various types of *591 equipment. Mr. Vasquez was employed on behalf of Village Center, Inc., the corporation which was planned as a subsidiary of Nicholson & Bilhorn, Inc., to develop the commercial tract.

Plaintiff proceeded to do the work as directed during the remainder of 1955 and in 1956, completing the job on August 21. He worked under the control and direction of Edward Bilhorn and performed the work agreed upon. The total charges figured at the stipulated rates amounted to $15,606.12. In December 1955, a $3,000 payment was made by a check of Nicholson & Bilhorn, Inc., leaving a balance due of $12,606.12.

Mr. Bilhorn testified that Vasquez was the general contractor and, according to the evidence, plaintiff was the only contractor involved in any work on the land in question prior to the time it was conveyed to Mr. Dooly on December 10, 1956. No buildings had been constructed on the property by the time it was conveyed to Dooly.

In August 1955 the corporation, Village Center, Inc., was formed as theretofore planned by James and Terry Nicholson and Edward Bilhorn. They were the officers and directors, owned all the stock, and conducted its business in accordance with the plan which existed at the time title to the property was taken in the names of James Nicholson and his wife. The commercial site in question was conveyed to Village Center, Inc., on April 2, 1956. Plaintiff understood that the work he performed on the commercial tract in 1955 and 1956 was on a separate project and that the work was to be done for Village Center, Inc. Mr. Vasquez did not know Mr. Dooly and had had no dealings with him.

Appellant Dooly contends that the judgment impressing his land with a mechanic’s lien is void because, he says, the court was ■without jurisdiction of the case inasmuch as the parties to the contract were not made parties to the action as required by statute.

Section 429.190 1 mandatorily requires that the parties to the contract be made parties to a mechanic’s lien action. Harrison v. Creason, Mo.App., 238 Mo.App. 118, 176 S.W.2d 849; Hughes Bros. Paint & Hardware Co. v. Prewitt, 170 Mo.App. 594, 157 S.W. 120, 121 [3, 4] ; Simon Devine Welding Co. v. Kuhn, Mo.App., 329 S.W.2d 249, 252 [1-3], The contract referred to in the statute is the agreement made for the performance of the work or for the furnishing of materials. Harrison v. Creason, supra, 176 S.W.2d 850 [1-2]; Foster v. Wulfing, 20 Mo.App. 85, 87.

Appellant argues that the evidence shows that the contract to do the work was made with James Nicholson, Terry Nicholson, and Edward Bilhorn, and that the property was then owned either by James Nicholson and his wife or Nicholson & Bilhorn, Inc. And he points out that Village Center was not in existence at the time the arrangement was made for plaintiff to do the work and that the land was not conveyed to Village Center, Inc., until April 1956. Therefore, says appellant, since neither Bilhorn and the two Nicholsons, nor James Nicholson and his wife, nor Nicholson & Bil-horn, Inc., were made parties to the suit, the court was without jurisdiction over the subject matter and the judgment was void.

We are unable to agree with appellant’s contention.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Karrenbrock Constr., Inc. v. Saab Auto Sales & Leasing, Inc.
540 S.W.3d 899 (Missouri Court of Appeals, 2018)
River City Drywall, Inc. v. Raleigh Properties, Inc.
341 S.W.3d 716 (Missouri Court of Appeals, 2011)
Missouri Land Development Specialties, LLC v. Concord Excavating Co.
269 S.W.3d 489 (Missouri Court of Appeals, 2008)
Bullmaster v. Krueger
151 S.W.3d 380 (Missouri Court of Appeals, 2004)
Space Planners Architects, Inc. v. Frontier Town-Missouri, Inc.
107 S.W.3d 398 (Missouri Court of Appeals, 2003)
Haimbaugh Landscaping, Inc. v. Jegen
653 N.E.2d 95 (Indiana Court of Appeals, 1995)
Landmark Systems, Inc. v. Delmar Redevelopment Corp.
900 S.W.2d 257 (Missouri Court of Appeals, 1995)
Landmark Systems v. DELMAR REDEVELOPMENT
900 S.W.2d 258 (Missouri Court of Appeals, 1995)
McKenney v. Joplin Union Station, Inc.
867 S.W.2d 245 (Missouri Court of Appeals, 1993)
Tip-Top Plumbing & Heating Co. v. Gregoric
860 S.W.2d 22 (Missouri Court of Appeals, 1993)
Dave Kolb Grading, Inc. v. Lieberman Corp.
837 S.W.2d 924 (Missouri Court of Appeals, 1992)
Brownstein v. Rhomberg-Haglin & Associates, Inc.
824 S.W.2d 13 (Supreme Court of Missouri, 1992)
Morgan Wightman Supply Co. v. Smith
764 S.W.2d 485 (Missouri Court of Appeals, 1989)
Williams v. Enochs
742 S.W.2d 165 (Supreme Court of Missouri, 1987)
Opinion No. (1985)
Missouri Attorney General Reports, 1985
Kenny's Tile & Floor Covering, Inc. v. Curry
681 S.W.2d 461 (Missouri Court of Appeals, 1984)
Leonard v. Bennett
674 S.W.2d 123 (Missouri Court of Appeals, 1984)
R. J. Stephens Drywall & Painting Co. v. Taylor-Morley-Simon, Inc.
628 S.W.2d 374 (Missouri Court of Appeals, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
362 S.W.2d 588, 1962 Mo. LEXIS 562, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vasquez-v-village-center-inc-mo-1962.