E.W. Allen & Associates, Inc. v. Federal Deposit Insurance

776 F. Supp. 1504, 1991 WL 230164
CourtDistrict Court, D. Utah
DecidedNovember 5, 1991
DocketCiv. 88-C-598A
StatusPublished
Cited by5 cases

This text of 776 F. Supp. 1504 (E.W. Allen & Associates, Inc. v. Federal Deposit Insurance) is published on Counsel Stack Legal Research, covering District Court, D. Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E.W. Allen & Associates, Inc. v. Federal Deposit Insurance, 776 F. Supp. 1504, 1991 WL 230164 (D. Utah 1991).

Opinion

ALDON J. ANDERSON, Senior District Judge.

The above captioned case is now before the court on cross motions for summary judgment. Consolidated plaintiff Nautilus Architecture and Planning, Inc. (“Nautilus”) filed a Motion for Partial Summary Judgment seeking a determination of priority in favor of itself against consolidated defendant Federal Deposit Insurance Corporation (“FDIC”). FDIC then filed a Motion for Summary Judgment seeking a ruling on the same issue. The court held a hearing on the cross motions for summary judgment on October 7, 1991. Michael Hughes and Craig Coburn appeared on behalf of Nautilus. Jeffrey Silvestrini and Martha Stonebrook appeared on behalf of *1506 FDIC. Having reviewed the briefs of the parties, the file, and relevant available authorities, the court is prepared to rule.

I.

This lawsuit revolves around a 280 acre parcel of wooded land in the mountains of southern Utah. The parties now before the court, Nautilus and FDIC, claim competing interests in the parcel. The owner of the parcel originally envisioned building a mul-ti-million dollar luxury resort complex on the parcel. Unfortunately, that vision never came to fruition. The project, however, did not expire before acquiring some creditors, two of which, Nautilus and FDIC, are now vying for priority before this court.

Early in the life of the project, the owner hired Nautilus, an architecture firm, to give substance to his vision of a luxury resort by drawing plans and specifications for the resort complex. Nautilus then subcontracted with E.W. Allen & Associates (“Allen”) 1 to provide some structural engineering assistance. Allen finished its work and, not having been paid for its work, recorded a notice of lien on the property to protect its mechanics’ lien interest. Allen recorded its notice of lien on January 25, 1985. Shortly after Allen recorded its notice of lien, Nautilus apparently finished its work on the project because it also began complying with the procedural requirements for preserving its mechanics’ lien interest. The owner of the property never fully paid either Nautilus or Allen for their work. Nautilus now asserts its claim for payment in this lawsuit as a mechanics’ lien against the 280 acre parcel.

FDIC is the successor in interest to North American Savings and Loan (“North American”). North American helped finance the owner in attempting to build the multi-million dollar resort complex. North American loaned the owner substantial sums of money for the project on the security of a trust deed to the 280 acre parcel. The owner failed to repay the loan given him by North American. The trust deed in favor of North American on which FDIC now bases its claim to the parcel is dated February 25, 1985, and was recorded on March 16, 1985. FDIC and Nautilus now dispute which of their claims in the parcel has priority.

II.

A. Nautilus’ Motion for Partial Summary Judgment

1. commencement of work.

Nautilus argues it has a valid mechanics’ lien that takes priority over FDIC’s interest in the parcel and is, therefore, entitled to judgment as a matter of law. The parties do not dispute that Nautilus performed lienable work for which it has not been paid. Nautilus’ first asserted ground for priority is that sufficient construction had been completed on the property to constitute “commencement to do work” under the applicable statute prior to the execution of FDIC’s deed of trust. Nautilus’ position is based on the Utah statutes governing mechanics’ liens. 2

Utah statutory law provides a mechanics’ lien for architects such as Nautilus that perform services in the improvement of land. See Utah Code Ann. § 38-1-8 (1988). The priority of a mechanics’ lien with respect to other encumbrances, such as a deed of trust, is governed by § 38-1-5 of the Utah Code which provides in pertinent part:

[Mechanics’ liens] shall relate back to, and take effect as of, the time of the commencement to do work or furnish materials on the ground for the structure or improvement, and shall have priority over any lien, mortgage or other encumbrance which may have attached subsequently to the time when the building, improvement or structure was com *1507 menced, work begun, or first material furnished on the ground.

Utah Code Ann. § 38-1-5 (1988) (emphasis added).

Nautilus claims a lien against the 280 acre parcel and argues that work had “commenced” on the ground on the development of the resort complex prior to FDIC’s trust deed. Nautilus makes specific factual allegations regarding actions it claims constituted “commencement to do work” and had been completed prior to the trust deed. Nautilus’ claim, however, is not appropriate for decision on summary judgment. Significant factual disputes exist in the deposition testimony as to when and if the actions alleged by Nautilus to be “commencement to do work” were taken. Consequently, the court cannot grant Nautilus summary judgment since substantial issues of material fact remain disputed. See Fed.R.Civ.P. 56.

2. record notice of lien.

As an alternative, Nautilus asserts that Allen’s recording of its notice of lien claim in January of 1985, prior to FDIC’s trust deed, entitles Nautilus to summary judgment on the issue of priority. Nautilus begins its argument by properly noting that all mechanics’ liens stand on an equal footing with each other for purposes of priority. See Utah Code Ann. § 38-1-10. In other words, once any mechanic establishes the priority of its lien, that date serves as the date of priority for all mechanics’ liens on the same project. See First of Denver Mortgage Investors v. C.N. Zundel, 600 P.2d 521, 526 (Utah 1979). Nautilus next cites § 38-1-9(2) of the Utah Code which states, “From the time the claim is filed for record, all persons are considered to have notice of the claim.” Utah Code Ann. § 38-1-9(2). From these two principles of Utah mechanics’ lien law, equal footing and record notice, Nautilus concludes that Allen’s recording of a notice of lien on January 25, 1985, established the priority date for Nautilus’ mechanics’ lien. Nautilus cites no directly supporting authority for giving this interpretation to these two principles. But cf. Hostetter v. Inland Dev. Corp. of Montana, 172 Mont. 167, 561 P.2d 1323, 1326 (1977) (filing of a lien does not create lien, it merely extends and preserves life of lien).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
776 F. Supp. 1504, 1991 WL 230164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ew-allen-associates-inc-v-federal-deposit-insurance-utd-1991.