Clark v. General Electric Co.

420 S.W.2d 830, 243 Ark. 399
CourtSupreme Court of Arkansas
DecidedDecember 13, 1967
Docket5-4288
StatusPublished
Cited by17 cases

This text of 420 S.W.2d 830 (Clark v. General Electric Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clark v. General Electric Co., 420 S.W.2d 830, 243 Ark. 399 (Ark. 1967).

Opinion

John A. Fogleman, Justice.

The principal question in this case requires the determination of priority between a construction money mortgage on the one hand and several liens of materialmen, suppliers and mechanics on the other.

In 1964 Morehead Properties, Inc., (hereinafter called Morehead) having in mind construction of a large complex of “garden apartments,” acquired certain lands in Hot Springs. Morehead had previously dealt with appellant for materials, supplies and financing in connection with similar construction in Texas. Appellant arranged for both permanent and construction financing for Morehead on the project in question. He accomplished this by guaranteeing the $400,000.00 construction loan by the Exchange National Bank of Dallas and acquiring a commitment for permanent financing by John Hancock Life Insurance Company when construction was completed and the apartments occupied. On April 14, 1965, Morehead executed a proper and valid mortgage on the property to the bank as security for the construction loan. It was not filed for record until April 21, 1965, at 11:21 a.m. It contained a recital that the money was to be advanced to Morehead from time to time. Actually, the entire amount of the loan was disbursed pursuant to preliminary agreement, however, by advances by the bank to appellant from time to time. He, in turn, made advances to Morehead for the payment of various costs incident to the project, with the proposed application of the advances usually specified by Morehead. The latter commenced construction on the project, making contracts with appellees for labor and materials. Morehead became insolvent before the buildings were completed or appellees paid. Appellant then paid the Morehead note upon demand of the bank and took an assignment of the note and mortgage. He also took possession of the apartment complex. Appellees then filed suits to enforce their liens and appellant filed a suit for foreclosure of the construction money mortgage. The suits were consolidated for trial and the chancellor found that the liens of appellees were prior to the lien of the construction money mortgage. The principal contention of appellant is that the trial court erred in holding that the appellees’ liens had priority over his mortgage.

The court’s findings in this respect were based upon the activities of appellee Carroll Pyron, d/b/a Carroll Pyron Construction Company. Pyron was a heavy construction contractor, operating bulldozers and similar machinery. He was employed in October 1964 to' clear the land of brush, debris and trees in order for a topographical survey of the premises to be made. This assignment was completed, Pyron billed Morehead and was fully paid. While no agreement was reached, Pyron was told at the time he did this work that Morehead would like to have him do the excavation for the concrete work. In the early part of April 1965 Morehead contracted with Pyron for the leveling of the land for a proposed apartment complex to consist of more than one building. After the clearing in 1964, several large trees and two old houses remained on the site, but these latter had been removed when Pyron first went there in 1965. The old foundations remained, however, and the land itself was of an uneven elevation. Pyron was furnished with a set of plans and building elevations were discussed. An agreement was made for Pyron to clear the property of remaining debris and to grade elevations for the building sites with compensation to be paid on an hourly basis. The latter undertaking was to be accomplished by moving dirt from one place to another on the site so as to bring the sites for the buildings to elevations satisfactory for the laying of concrete slab foundations.

On the morning of April 19th Pyron went to the building site with an employee named Terry to commence work. Pyron spent about 45 minutes establishing cut and fill elevations with a transit and an elevation rod. Terry had brought a large bulldozer with which he started moving the foundations of the old houses. That day he worked approximately six hours, during which he removed the foundations of the old buildings and commenced the leveling operation. The condition of the soil after this work would have revealed that it had been “bulldozed over.” The machine remained on the job site and was actually not removed therefrom for at least one week. An employee named Taylor went to the property at 7 a.m. on April 21st and spent about thirty minutes with Pyron, becoming oriented' to the elevations. He then worked for an hour and a half, using the same machine. Nothing else was done on the apartment site before the filing of the mortgage. Ultimately Pyron completed the leveling work. Shortly prior to May 13th he dug the footings for the concrete foundations. This was the first actual work in connection with building the apartments, other than the bulldozer work.

Appellees contend that the work done by Pyron establishes the priority of all their liens, relying upon Ark. Stat. Ann. § 51-607 (1947). They argue that this work constituted “commencement of the buildings or improvements” in the sense of that section of the statute, so that all such liens dated from this “commencement” under the rule announced in Planters Lumber Co. v. Jack Collier East Co., 234 Ark. 1091, 356 S. W. 2d 631. Appellees have virtually abandoned their original contention that the work in October 1964 constituted a commencement from which the priority would date, but rely on the work done on April 19th and 21st. We had occasion to determine whether there was a “commencement” of a building sufficient to establish lien priority recently in Mark’s Sheet Metal, Inc. v. Republic Mortgage Co., 242 Ark. 475, 414 S. W. 2d 106. There we held that the work done must be such as to make it obvious that improvements, on the property were being commenced or were underway. We said that the clause in question means some visible or manifest action on the premises to be improved, making it apparent that the building is going up or other improvement is to be made. Reference was made in that opinion to Rupp, Trustees v. Earl H. Cline & Sons, 230 Md. 573, 188 A. 2d 146, 1 ALR 3d 815. In that case, the Maryland Supreme Court held that neither the removal of soil from a part of a development site intended for the erection of an apartment building to another part of the site, intended for the construction of cottages, nor the grading and leveling of the apartment site constituted such “ commencement’ ’ under a similar statute as to give a mechanic’s lien preference over a subsequently recorded mortgage. They relied on their previous decisions holding that commencement of the building is “the first work on the ground which is made the foundation of the building and forms a part of the work suitable and necessary for its construction” (Brooks v. Lester, 36 Md. 65) and that driving of stakes and digging away of soil to level the ground prior to beginning construction were not sufficient (Kelly v. Rosenstock, 45 Md. 389). They had said in the earlier cases that the work must be such that everyone can readily see and recognize it as commencement of a building. This rule is followed by a great majority of the cases in which the question has arisen in states with statutes similar to ours.. It is generally held that the mere preparation of the land for the construction is not sufficient. See Annot., 1 ALR 3d 822.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Byrd Underground, L.L.C. v. Angaur, L.L.C.
2014 NV 62 (Nevada Supreme Court, 2014)
May Construction Co. v. Town Creek Construction & Development, LLC
2011 Ark. 281 (Supreme Court of Arkansas, 2011)
Je Dunn Northwest, Inc. v. Corus Const. Venture
249 P.3d 501 (Nevada Supreme Court, 2011)
KETCHUM, KONKEL v. Heritage Mt.
784 P.2d 1217 (Court of Appeals of Utah, 1989)
In Re Zachman Homes, Inc.
47 B.R. 496 (D. Minnesota, 1984)
Worthen Bank & Trust Co., N.A. v. Walker
606 S.W.2d 382 (Court of Appeals of Arkansas, 1980)
Williams & Works, Inc. v. Springfield Corp.
293 N.W.2d 304 (Michigan Supreme Court, 1980)
Bank of Cave City v. Hill
587 S.W.2d 833 (Supreme Court of Arkansas, 1979)
Town of Paradise Valley v. Gulf Leisure Corp.
557 P.2d 532 (Court of Appeals of Arizona, 1976)
Diversified Mortgage Investors v. Gepada, Inc.
401 F. Supp. 682 (S.D. Iowa, 1975)
Jim Walter Homes Inc v. Oather Bowling
521 S.W.2d 828 (Supreme Court of Arkansas, 1975)
John E. Mahaffey & Associates, Inc. v. Brophy
462 S.W.2d 226 (Supreme Court of Arkansas, 1971)
First Natinal Bank of Conway v. Conway Sheet Metal Co.
428 S.W.2d 293 (Supreme Court of Arkansas, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
420 S.W.2d 830, 243 Ark. 399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clark-v-general-electric-co-ark-1967.