May Construction Co. v. Town Creek Construction & Development, LLC

2011 Ark. 281, 383 S.W.3d 389, 2011 Ark. LEXIS 263
CourtSupreme Court of Arkansas
DecidedJune 23, 2011
DocketNo. 09-1238
StatusPublished
Cited by12 cases

This text of 2011 Ark. 281 (May Construction Co. v. Town Creek Construction & Development, LLC) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
May Construction Co. v. Town Creek Construction & Development, LLC, 2011 Ark. 281, 383 S.W.3d 389, 2011 Ark. LEXIS 263 (Ark. 2011).

Opinion

COURTNEY HUDSON HENRY, Justice.

hMay Construction Company (“May”) appeals from a Washington County Circuit Court order declaring a hen on real property, owned by Town Creek Construction & Development, LLC (“Town Creek”), subordinate to a mortgage filed by Chambers Bank of North Arkansas (“Chambers”) and unenforceable against a lien bond issued by Ohio Casualty Insurance Company (“Ohio Casualty”). For reversal, May argues that the circuit court erred in interpreting the materialmen’s lien statute, ruling that construction commenced after the execution of Chambers’s mortgage, and finding that May could not recover against the lien bond. Town Creek cross-appeals, arguing that the circuit court erred in ruling that May was entitled to a lien in the amount of $858,904.53. Because this appeal presents issues of first impression and statutory interpretation, we have jurisdiction pursuant to Arkansas Supreme 1 gCourt Rule l-2(b). We reverse and remand the direct appeal, and we affirm the cross-appeal.

I. Facts

Town Creek owned the Aspen Ridge property (“the property”), a twenty-nine-acre project consisting of mixed residential and commercial development in Fayette-ville. On June 2, 2005, Town Creek hired May as a general contractor and entered into a written cost-plus contract with May to construct improvements on the property not to exceed $3,900,000. The contract contained an arbitration clause. To finance the project, Town Creek obtained a loan from Chambers that was secured by a mortgage of Phases I and II of the residential portions of the property and a certificate of deposit valued at $150,000. However, Town Creek did not mortgage Phase III, the commercial portion of the property. The loan totaled $6,385,918.05 (“$6,385 million”).

The facts are in dispute as to when May began construction on the property. After a preconstruction meeting on June 16, 2005, Mike Gilbert, May’s senior vice-president, and Hal Forsyth, president of Town Creek, exchanged various emails concerning the date that construction would begin. In an email dated June 30, 2005, Gilbert wrote to Forsyth, stating, “Hal we are permitted and inspected and plan to be ready to go on Tuesday. We will NOT commence without your authorization.” On that same day, Forsyth wrote, “Mike, we are okay to mobilize equipment [on Phase III, which was not the subject of the lien] on the site. The only thing for sure we can’t do is to turn any dirt.” Forsyth also sent an email to Justin Salter at Chambers, which stated, “I was just checking in to see if you had finalized our loan |sfor Aspen Ridge, so I could have May Construction get things started.”

On July 13, 2005, Town Creek executed the mortgage encumbering the property, and on July 20, 2005, the mortgage was recorded in Washington County. Over the next year, May worked on the project primarily through its subcontractor, Ver-naci Construction Company (“Vernaci Construction”). During the course of the project, disputes arose between the parties involving unanticipated delays, change orders, and unpaid subcontractors. As a result, in August 2006, Town Creek terminated its contract with May. Subsequently, on September 26, 2006, May recorded a materialmen’s lien against Town Creek’s property.

Vernaci Construction filed suit in Washington County Circuit Court against May, Town Creek, Chambers, and several other contractors and suppliers, which led to a number of cross-claims, counterclaims, and third-party claims. Among them, May sought money due from Town Creek under the construction contract. Town Creek defaulted on its loan to Chambers, leading Chambers to seek foreclosure on the property.

May’s contract claim against Town Creek went to arbitration, and the circuit court stayed the remainder of the lawsuit pending the outcome of the arbitration. On September 4, 2007, the arbitrator awarded May $393,995.56 plus $35,000 in attorney’s fees for a total amount of $428,995.56 but did not address the issue of entitlement and priority of the liens. May returned to circuit court, seeking confirmation of the arbitration award, foreclosure on its lien, and a declaration that its lien was superior to all others. Town Creek later deeded the property to Chambers in lieu of foreclosure and secured a lien bond to release the property |4from the encumbrance of May’s lien. Ohio Ca^ sualty, as surety, issued a materialmen’s lien bond in the penal sum of $800,000, naming Town Creek as principal and May as obligee.

In late May 2008, the circuit court conducted a three-day bench trial and later issued a letter opinion, dated January 16, 2009. On July 1, 2009, the circuit court entered a final order, granting judgment in favor of May in the amount of $428,995.56, which reflected the arbitration award. Specifically, the circuit court made the following rulings: (1) construction did not commence until after the filing of Chambers’s mortgage; (2) Chambers’s mortgage on the property had first priority while May’s lien had second priority; (3) May’s affidavit of account and cost-detail report were sufficient and credible evidence to substantiate its lien amount as determined by the court; (4) May had a valid lien claim in the amount of $353,904.53, and May’s lien attached to tracts one and two of Phase I of the Aspen Ridge property; (5) with the filing of the lien bond, the property was freed from the encumbrance of May’s lien; and (6) May could not recover against the lien bond because the value of May’s lien upon foreclosure would call for speculation. May timely filed a notice of appeal and an amended notice of appeal. Town Creek cross-appealed. Subsequently, this case was certified to our court, and we now consider May’s appeal.

II. Commencement of Construction and Priority of the Lien

For the first point on appeal, May challenges the circuit court’s ruling that its lien was inferior to Chambers’s mortgage on the property. Specifically, May argues that its lien relates back to the date that the construction commenced, pursuant to Arkansas Code Annotated section 18^14-110(a)(1) (Repl.2003). May asserts that construction commenced when |5Vernaci mobilized workers and equipment on site as early as June 16, 2005.

Town Creek, Chambers, and Ohio Casualty argue that the circuit court properly ruled that May did not commence construction until after the execution of Chambers’s construction mortgage and that Chambers’s mortgage had priority over May’s lien. Appellees contend that the priority between a mortgage lien and a materialmen’s lien is determined by Arkansas Code Annotated section 18-44-110.

The applicable statute pertaining to the priority of a materialmen’s lien is set forth in Arkansas Code Annotated section 18-44-110. We construe lien statutes strictly, as they are in derogation to the common law. BB & B Constr. Co. v. F.D.I.C., 316 Ark. 663, 875 S.W.2d 48 (1994). Strict construction means narrow construction and requires that nothing be taken as intended that is not clearly expressed. Lawhon Farm Servs. v. Brown, 335 Ark. 272, 984 S.W.2d 1 (1998). The first rule in considering the meaning and effect of a statute is to construe it just as it reads, giving the words their ordinary and usually accepted meaning in common language. Wilson v. Phillips Cnty. Election Comm’n, 2011 Ark. 223, 2011 WL 1896779.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aaron C. Sluyter and Cheryl Sluyter v. Wood Guys, LLC
2021 Ark. App. 442 (Court of Appeals of Arkansas, 2021)
Metzner v. State
2015 Ark. 222 (Supreme Court of Arkansas, 2015)
Ahern Rentals, Inc. v. Salter Construction, Inc.
2014 Ark. App. 423 (Court of Appeals of Arkansas, 2014)
Byrd Underground, L.L.C. v. Angaur, L.L.C.
2014 NV 62 (Nevada Supreme Court, 2014)
Adams v. Howard
2014 Ark. App. 328 (Court of Appeals of Arkansas, 2014)
Robinson v. State
2014 Ark. 101 (Supreme Court of Arkansas, 2014)
Daugherty v. Jacksonville Police Department
2012 Ark. 264 (Supreme Court of Arkansas, 2012)
Hauser v. Sims
423 S.W.3d 104 (Court of Appeals of Arkansas, 2012)
Opinion No.
Arkansas Attorney General Reports, 2011

Cite This Page — Counsel Stack

Bluebook (online)
2011 Ark. 281, 383 S.W.3d 389, 2011 Ark. LEXIS 263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/may-construction-co-v-town-creek-construction-development-llc-ark-2011.