Byrd Underground, L.L.C. v. Angaur, L.L.C.

2014 NV 62
CourtNevada Supreme Court
DecidedAugust 7, 2014
Docket61978
StatusPublished

This text of 2014 NV 62 (Byrd Underground, L.L.C. v. Angaur, L.L.C.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Byrd Underground, L.L.C. v. Angaur, L.L.C., 2014 NV 62 (Neb. 2014).

Opinion

130 Nev., Advance Opinion 472- IN THE SUPREME COURT OF THE STATE OF NEVADA

BYRD UNDERGROUND, LLC; AND No, 61978 WELLS CARGO, INC., Appellants, vs. FILED ANGAUR, LLC; BALAJI PROPERTIES AUG 0 7 2014 INVESTMENT, LLC; AND US BANK C K cLINDEMAN NATIONAL ASSOCIATION, CLEI •

Respondents. BY tir At E 11 I er Ariports::::

i Certified questions, pursuant to NRAP 5, concerning the priority of mechanics' liens based on visible commencement of construction. United States Bankruptcy Court for the District of Nevada; Bruce T. Beesley, Judge. Questions answered in part.

Foley & Oakes, PC, and Daniel T. Foley, Las Vegas; M. Nelson Segel, Las Vegas; Peel Brimley LLP and Eric B. Zimbelman and Richard L. Peel, Henderson, for Appellants.

Fennemore Craig Jones Vargas and Craig S. Dunlap and Christopher H. Byrd, Las Vegas; Meier & Fine, LLC, and Glenn F. Meier, Las Vegas, for Respondents.

BEFORE THE COURT EN BANC.

OPINION

By the Court, GIBBONS, C.J.: In Nevada, a mechanic's lien takes priority over other encumbrances on a property that are recorded after construction of a work SUPREME COURT OF NEVADA

(0) 194Th ca4MAD of improvement visibly commences. The visible-commencement-of- construction requirement often gives rise to dispute, however, and the United States Bankruptcy Court for the District of Nevada has certified three questions of law to this court regarding this aspect of mechanic's lien priority law.' The first question queries whether the placement of dirt material on a future project site before building permits are issued and the

'The three certified questions were presented as follows:

1. Can a mechanic's lien claimant properly claim lien priority under NRS 108.225 when the dirt/material that is the basis of the lien on the project was placed on a prospective building project site months before the building permit was issued or the general contractor hired? Stated another way, does placing significant quantities of dirt/material on a prospective building project site months before a building permit is issued constitute "commencement of construction" on such a site pursuant to NRS [108.221121? 2. Did the Nevada Supreme Court in J.E. Dunn Northwest, Inc. v. Corus Construction Venture, LLC, 249 P.3d 501, 509, 127 Nev. Adv. Op. 5 (Nev. 2011) mistakenly use the term of art "clearing and grading" instead of "clearing and grubbing" when describing preparatory work on a construction project? 3. Does "grading" in the circumstances presented here constitute visible "commencement of construction" under NRS 108.22112 for purposes of establishing lien priority under NRS 108.225?

SUPREME COURT OF NEVADA 2 (0) 1947A tretep general contractor is hired can constitute commencement of construction. The second question asks us to clarify our decision in J.E. Dunn Northwest, Inc. v. Corns Construction Venture, L.L.C., 127 Nev. 249 P.3d 501 (2011), in which we stated that "clearing or grading" does not constitute commencement of construction. 127 Nev. at 249 P.3d at 509. In our view, answering this question requires us to evaluate the appropriate precedential weight that courts should give to the passage in question, and we therefore rephrase the• second certified question to include whether this statement was dictum. See, e.g., Boorman v. Nev. Mem'l Cremation Soc'y, 126 Nev. „ 236 P.3d 4, 6 (2010) (rephrasing certified questions under NRAP 5). We rephrase the second question as follows: Was the passage in J.E. Dunn Northwest, Inc. v. Corns Construction Venture, L.L.C., 127 Nev. , 249 P.3d 501, 509 (2011), that states "preparatory work on a site, such as clearing or grading, does not constitute commencement of construction," dictum? If so, can grading work constitute visible commencement of construction under NRS 108.22112? Finally, the third question inquires whether the grading that took place in this case constituted visible commencement of construction, such that the mechanics' liens at issue take priority. Because the second question influences our analysis of the other questions, we address it first. We respond to the three questions as follows. Regarding the bankruptcy court's second question, we conclude that this court's use of the term "clearing or grading" was dictum, and thus, our holding in J.E. Dunn does not preclude a trier of fact from finding that grading property for a work of improvement constitutes visible commencement of construction. Regarding the first question, we SUPREME COURT OF NEVADA 3 (0) 1947A c(gDir conclude that contract dates and permit issuance dates are irrelevant to the visible-commencement-of-construction test, but may assist the trier of fact in determining the scope of the work of improvement. Finally, we decline to answer the third question because it would require this court to resolve the factual dispute as to whether the grading presented here constituted visible commencement of construction of the work of improvement. FACTS AND PROCEDURAL HISTORY The construction project The debtor respondents Angaur, LLC, and Balaji Properties Investment, LLC (collectively, the owners), jointly purchased a parcel of unimproved real property in Las Vegas, Nevada. No relevant activity took place with respect to the subject property until the spring and summer of 2006; when two different third parties placed, and allegedly spread, between 200 and 300 truckloads of dirt/material on the property. 2 Both of the third parties were performing work on unrelated construction projects on neighboring parcels and roadways. The degree to which the subject property was covered and subsequently spread or graded is unclear given the record before this court. Meanwhile, the owners solicited bids from general contractors to construct a strip mall on the property. During bidding on the project,

2 The parties could not agree what to call the substance that was placed on the property, so the bankruptcy court used the term "dirt/material." The bankruptcy court noted that it did not intend the term to carry any specific legal meaning. We also will use the term "dirt/material" to remain consistent with the bankruptcy court.

SUPREME COURT OF NEVADA 4 (0) 1.947A appellant Byrd Underground, LLC, submitted a bid to general contractor Joseph's Construction to perform subcontracted grading work, but Atlas Construction Ltd., not Joseph's Construction, was selected as the general contractor. On November 2, 2006, at the request of Atlas, a representative of Byrd dug four to six holes on the subject property with a backhoe. Byrd dug these holes to determine how much dirt/material had been brought onto the subject property since its prior bid in order to submit a revised bid to Atlas incorporating the new scope of work. On November 8, 2006, Atlas and the owners executed the written contract for Atlas to serve as the general contractor on the construction project. On November 28, 2006, a title company conducted a site inspection of the subject property and concluded that the land was vacant and that there was no evidence of a recent work of improvement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schultz v. King
228 P.2d 401 (Nevada Supreme Court, 1951)
Aladdin Heating Corp. v. Trustees of Central States
563 P.2d 82 (Nevada Supreme Court, 1977)
Clark v. General Electric Co.
420 S.W.2d 830 (Supreme Court of Arkansas, 1967)
City of North Las Vegas v. Warburton
262 P.3d 715 (Nevada Supreme Court, 2011)
In Re Fontainebleau Las Vegas Holdings, LLC
267 P.3d 786 (Nevada Supreme Court, 2011)
Stockmeier v. State, Board of Parole Commissioners
255 P.3d 209 (Nevada Supreme Court, 2011)
St. James Village, Inc. v. Cunningham
210 P.3d 190 (Nevada Supreme Court, 2009)
Je Dunn Northwest, Inc. v. Corus Const. Venture
249 P.3d 501 (Nevada Supreme Court, 2011)
May Construction Co. v. Town Creek Construction & Development, LLC
2011 Ark. 281 (Supreme Court of Arkansas, 2011)
Wilmington Trust FSB v. A1 Concrete Cutting & Demolition, LLC
289 P.3d 1199 (Nevada Supreme Court, 2012)
I. Cox Construction Co. v. CH2 Investments, LLC
296 P.3d 1202 (Nevada Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
2014 NV 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/byrd-underground-llc-v-angaur-llc-nev-2014.