Je Dunn Northwest, Inc. v. Corus Const. Venture

249 P.3d 501, 127 Nev. 72, 127 Nev. Adv. Rep. 5, 2011 Nev. LEXIS 6
CourtNevada Supreme Court
DecidedMarch 3, 2011
Docket54332
StatusPublished
Cited by15 cases

This text of 249 P.3d 501 (Je Dunn Northwest, Inc. v. Corus Const. Venture) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Je Dunn Northwest, Inc. v. Corus Const. Venture, 249 P.3d 501, 127 Nev. 72, 127 Nev. Adv. Rep. 5, 2011 Nev. LEXIS 6 (Neb. 2011).

Opinion

249 P.3d 501 (2011)

J.E. DUNN NORTHWEST, INC., Appellant,
v.
CORUS CONSTRUCTION VENTURE, LLC, Respondent.

No. 54332.

Supreme Court of Nevada.

March 3, 2011.

*502 Gibbs, Giden, Locher, Turner & Senet, LLP, and Ronald S. Sofen, Las Vegas, for Appellant.

Meier & Fine, LLC, and Glenn F. Meier and Kathryn J. Quinn, Las Vegas, for Respondent.

Before the Court En Banc.

OPINION

By the Court, HARDESTY, J.:

Appellant J.E. Dunn Northwest, Inc. (Dunn), performed various preconstruction services for the One Las Vegas condominium project in Las Vegas, Nevada, and recorded a mechanic's lien for this work. Respondent Corus Construction Venture, LLC (Corus *503 Bank),[1] provided construction financing for the project and recorded a deed of trust to secure its loan. In this appeal, we address four issues concerning the visibility requirement for a mechanic's lien to obtain priority over a deed of trust: (1) whether the visibility requirement contained in the definition of "commencement of construction" in NRS 108.22112 applies to both work performed and materials and equipment furnished to the construction site; (2) whether, in the 2003 amendments to NRS Chapter 108, the expansion of the definition of "work" to make preconstruction services lienable excuses the visibility requirement found in NRS 108.22112; (3) whether a lender with priority waives its superior position if it has actual knowledge of lienable preconstruction work; and (4) whether the placement of signs and removal of power lines constitutes visible work. We conclude that NRS 108.22112 plainly requires visibility of work performed, including preconstruction services, to establish priority. We also conclude that the 2003 amendments to NRS Chapter 108 did not affect the long-standing requirement that work must be visible on the property for a mechanic's lien to take priority over a deed of trust recorded before commencement of construction, and the statutory visibility requirement may not be waived by a lender who has actual knowledge of off-site preconstruction services. Finally, we conclude that the preparatory placement of signs and removal of power lines does not constitute visible work. In light of these conclusions, we affirm the district court's order granting Corus Bank's motion for summary judgment.

FACTS

In August 2005, Midbar Condo Development hired Dunn to perform a project feasibility assessment for One Las Vegas, a multimillion-dollar condominium project consisting of two 20-story towers on Las Vegas Boulevard. Dunn reviewed design considerations, coordinated contract documents, developed a construction schedule, and completed various other administrative tasks in preparation for construction.

In December 2005, Midbar hired Dunn to serve as construction manager and contractor for the One Las Vegas project. From December 2005 to March 2006, Dunn performed over $1 million in preconstruction services that included preparing project schedules, coordinating meetings with subcontractors, reviewing subcontractors' and architects' drawings, and other planning-related services.

Midbar obtained a loan from Corus Bank to finance the construction of the project, and Corus Bank recorded its deed of trust on March 17, 2006. Before recording the deed of trust, Nevada Title Company hired a third party to perform an inspection of the property. The inspector reported that power lines had been removed from the subject property and provided photographs that depicted several signs on an adjacent property. The signs were imprinted with the name of an architectural firm, Kobi Karp, which was performing design services for the One Las Vegas project in conjunction with Dunn. The signs were not located on the specific parcel inspected by the third party, and the inspector's report ultimately concluded that no construction activity had occurred on the property as of the date Corus Bank recorded its deed of trust.

During loan negotiations and before approving the release of any funds, Corus Bank performed a due diligence review, after which it approved Dunn as the contractor. Corus Bank negotiated a separate agreement with Dunn, which acknowledged that Dunn had provided, and would continue to provide, construction services. An early version of this agreement contained a subordination provision requiring Dunn to "waive its lien rights and to subordinate its mechanic['s] lien to the Corus Bank deed of trust." Dunn did not agree to this provision and Corus Bank ultimately removed it from the final version of the agreement.

*504 Midbar issued a notice to proceed to Dunn on March 20, 2006, and Dunn commenced construction. Two years later, in April and June 2008, Clark County issued temporary certificates of occupancy for both condominium towers. In August 2008, Dunn served a notice of intent to lien and, on September 8, recorded a mechanic's lien for its unpaid services. A few weeks later, Midbar defaulted on the loan, and a dispute arose between Corus Bank and Dunn regarding the priority of the deed of trust and the mechanic's lien.

Dunn filed a complaint in district court in October 2008, seeking a declaratory judgment that its mechanic's lien had priority over Corus Bank's deed of trust. Dunn then filed a motion for summary judgment, and Corus Bank filed an opposition to Dunn's motion and a countermotion for summary judgment. The district court denied Dunn's motion, finding that pursuant to NRS 108.225 and NRS 108.22112, Dunn's work must have been visible from a reasonable inspection of the property prior to the date that Corus Bank recorded its deed of trust, and Dunn failed to make that showing.[2] The district court also denied Corus Bank's countermotion for summary judgment.

In March 2009, Corus Bank renewed its motion for summary judgment, arguing that under NRS 108.225, a mechanic's lien takes priority over encumbrances that attach after construction commences. Accordingly, Corus Bank contended that, because "no visible work had been performed on the property and no visible equipment or materials had been furnished to the property" as of the date it recorded its deed of trust, construction had not commenced. Therefore, its deed of trust had priority. Dunn argued in opposition that a genuine issue of material fact existed with regard to whether its work was visible from a reasonable inspection of the property. Alternatively, Dunn claimed that Corus Bank waived the requirement that the work must be visible because, prior to recording its deed of trust, Corus Bank had knowledge that Dunn performed preconstruction services. Dunn also asked for more time for discovery to investigate Corus Bank's knowledge of Dunn's preconstruction work.

The district court granted Corus Bank's renewed motion for summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kline v. City Of Reno
Nevada Supreme Court, 2022
Lau v. City Of Las Vegas
Nevada Supreme Court, 2022
PAWLIK VS. DENG
2018 NV 11 (Nevada Supreme Court, 2018)
DUNCAN VS. STATE, OFFICE OF THE STATE TREASURER
2016 NV 73 (Nevada Supreme Court, 2016)
SCHWARTZ VS. LOPEZ
2016 NV 73 (Nevada Supreme Court, 2016)
U.S. BANK NATIONAL ASSOC. VS. PALMILLA DEV. CO.
2015 NV 9 (Nevada Supreme Court, 2015)
Byrd Underground, L.L.C. v. Angaur, L.L.C.
2014 NV 62 (Nevada Supreme Court, 2014)
Thomas v. Nev. Yellow Cab Corp.
2014 NV 52 (Nevada Supreme Court, 2014)
Century Sur. Co. v. Casino W., Inc.
2014 NV 42 (Nevada Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
249 P.3d 501, 127 Nev. 72, 127 Nev. Adv. Rep. 5, 2011 Nev. LEXIS 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/je-dunn-northwest-inc-v-corus-const-venture-nev-2011.