Williams & Works, Inc. v. Springfield Corp.

293 N.W.2d 304, 408 Mich. 732, 1980 Mich. LEXIS 229
CourtMichigan Supreme Court
DecidedJune 24, 1980
Docket61180, (Calendar No. 9)
StatusPublished
Cited by18 cases

This text of 293 N.W.2d 304 (Williams & Works, Inc. v. Springfield Corp.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams & Works, Inc. v. Springfield Corp., 293 N.W.2d 304, 408 Mich. 732, 1980 Mich. LEXIS 229 (Mich. 1980).

Opinion

Williams, J.

(for reversal). This case concerns the sole question whether oif-site engineering services rendered before the beginning of actual, on- *735 site construction qualify, pursuant to § 9(3) of the Michigan mechanics’ lien law, as "the commencement of said building or buildings, erection, structure or improvement” 1 so as to give priority to mechanics’ liens over a mortgage recorded after the provision of such services but prior to the beginning of any visible, on-site construction. 2

Long established Michigan precedent 3 in line with that in most American jurisdictions 4 requires *736 a visible, on-site "commencement” for the purpose of fixing priorities under § 9(3) of the mechanics’ lien law. Plaintiffs in this case, however, claim the Legislature intended to change by indirection this traditional rule based on § 9(3) "commencement of said building or buildings, erection, structure or improvement” by amending the list of lienable items in § l 5 of the mechanics’ lien law to include engineering and surveying services and by adding to the definition of "improvement” 6 found in § 1 *737 the language, "designs or engineering plans for the improvement of any lot”.

In view of the overwhelming weight of historical precedent, whose rationale and policy underpinnings remain vital today, we find that such non-visible, off-site engineering services as those rendered in the instant case, although lienable under Michigan law, do not signal the "commencement” of a building, erection, structure, or improvement for the purpose of fixing priority under Michigan’s mechanics’ lien law. Accordingly, since the appellant mortgagee recorded its mortgage prior to any visible, on-site construction which could be said to "commence” the building, erection, structure or improvement, the trial court and Court of Appeals improperly accorded priority to the appellee mechanic lienors. We therefore reverse.

I. Facts

Springfield Corporation ("Springfield”) desired to erect a multifamily apartment building complex on certain land located in Genesee County, Michigan, and owned by LAW Development Company and appellant Kelly Mortgage and Investment Company ("Kelly”). In pursuance of this desire, Springfield contacted Williams & Works ("W & W”) about May 16, 1972 in regard to using its engineering services for the contemplated development. Thereafter, on June 8, 1972, Robert Foote, *738 President of Springfield, met two representatives of W & W at the contemplated development site for discussions and a preliminary view of the premises. Then, near the end of June, 1972, W & W and Springfield entered into a formal written contract, under which W & W was to perform certain engineering services for the contemplated development. The contract was divided into three parts or phases with Springfield reserving the right to terminate the contract at the end of any phase. Phase I called for W & W to undertake and complete initial feasibility studies which included soil borings, drainage studies, topographical and boundary surveys, preliminary utility plans, cost estimates and plan approvals. Phase II called for W & W to finalize all plans for site development, including final drafting of the construction plans. Phase III involved the actual construction of the project and required W & W to supervise and direct parts of the construction work.

By September, 1972, Phase I was substantially completed. The only on-site work done by W & W during Phase I consisted of certain soil borings, which were taken on August 29, 1972, when two workers drilled twelve holes into the ground, each approximately 6" in diameter.

After the completion of Phase I, W & W began Phase II and throughout the latter part of 1972, it submitted various construction specifications to Springfield. It was also established that during this period Kelly knew of W & W’s work since Kelly had actually written W & W requesting that all correspondence dealing with W & W’s work to date be forwarded to Kelly since it would be handling the project for Mr. Foote. In late December, 1972, after substantial completion of the Phrase II drawings, Springfield decided to go for *739 ward with the construction of the apartment building project. Thereafter, on January 4, 1973, Springfield purchased the land from LAW Development and Kelly and executed a mortgage on the property to City National Bank ("CNB”) which was recorded in Genesee County and which was subsequently assigned from City National Bank to Kelly. On January 9, 1973, Springfield executed a second mortgage to Kelly, which was also recorded in Genesee County. Almost one year later, Springfield conveyed its fee interest in the premises to Bristol Square Properties Group, a limited copartnership in which Mr. Foote and Springfield are the sole general partners, by deed dated December 27, 1973.

It is undisputed that building operations on the premises did not begin until February, 1973, almost one full month after the mortgages were recorded by CNB and Kelly. The initial Phase III work, consisting of staking, began on February 10, 1973 and building operations commenced sometime thereafter. The project went into default in 1974 and this mechanics’ lien foreclosure action followed.

This suit was commenced on March 25, 1974, in the Genesee Circuit Court. The Complaint alleges that the plaintiff, W & W, had a mechanics’ lien upon the project property and prayed for its foreclosure. Numerous other parties were joined as defendants or intervened, and several cross-claims were filed by various other contractors, alleging mechanics’ liens against the property. Kelly, the mortgagee in the instant proceeding, as well as other defendants aligned in interest, answered the various mechanics’ lien claims, denying the validity of the claims and asserting that the mortgage interest in the property was superior and para *740 mount to the interest of the various mechanics’ liens.

After pretrial and trial proceedings concluded, the trial court entered judgments of foreclosure against the owner of the apartment project, Bristol Square Properties Group, in favor of W & W and the instant appellee mechanics’ lienors (Shank, Coupland and Long Co., PPG Industries, Inc., and Garno Brothers Heating and Cooling, Inc., all subcontractors who began supplying labor and materials while the project was owned by Springfield, and completed their work after Springfield conveyed to Bristol Square Properties Group). The trial court also ruled that all mechanics’ liens were prior to the mortgage interest of Kelly in the property because it found W & W’s services to have been "improvements”, as that term is defined in § 1, MCL 570.1; MSA 26.281, which were "commenced” before the mortgage was recorded.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michael's Construction, Inc. v. American National Bank
2012 WY 76 (Wyoming Supreme Court, 2012)
Jeddo Drywall, Inc. v. Cambridge Investment Group Inc.
810 N.W.2d 633 (Michigan Court of Appeals, 2011)
Je Dunn Northwest, Inc. v. Corus Const. Venture
249 P.3d 501 (Nevada Supreme Court, 2011)
MICHIGAN Ex Rel WAYNE COUNTY PROSECUTOR v. BENNIS
527 N.W.2d 483 (Michigan Supreme Court, 1994)
Lepore v. Parker-Woodward Corp.
818 F. Supp. 1029 (E.D. Michigan, 1993)
M D Marinich, Inc v. Michigan National Bank
484 N.W.2d 738 (Michigan Court of Appeals, 1992)
Pds Engineering Const. v. Double Rs, No. Cv90-0378684 (Dec. 19, 1991)
1991 Conn. Super. Ct. 10306 (Connecticut Superior Court, 1991)
KETCHUM, KONKEL v. Heritage Mt.
784 P.2d 1217 (Court of Appeals of Utah, 1989)
Morris v. Metriyakool
344 N.W.2d 736 (Michigan Supreme Court, 1984)
Durant Construction, Inc v. Gourley
336 N.W.2d 856 (Michigan Court of Appeals, 1983)
Michigan Roofing & Sheet Metal, Inc. v. Dufty Road Properties
298 N.W.2d 923 (Michigan Court of Appeals, 1980)
Bosch v. Altman Construction Corp.
298 N.W.2d 725 (Michigan Court of Appeals, 1980)
Portage Realty Corp. v. Baas
298 N.W.2d 892 (Michigan Court of Appeals, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
293 N.W.2d 304, 408 Mich. 732, 1980 Mich. LEXIS 229, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-works-inc-v-springfield-corp-mich-1980.