Bankers Trust Co. v. El Paso Pre-Cast Co.

560 P.2d 457, 192 Colo. 468, 1977 Colo. LEXIS 713
CourtSupreme Court of Colorado
DecidedFebruary 22, 1977
Docket27087, 27143
StatusPublished
Cited by29 cases

This text of 560 P.2d 457 (Bankers Trust Co. v. El Paso Pre-Cast Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bankers Trust Co. v. El Paso Pre-Cast Co., 560 P.2d 457, 192 Colo. 468, 1977 Colo. LEXIS 713 (Colo. 1977).

Opinion

MR. JUSTICE LEE

delivered the opinion of the Court.

These cases, consolidated on appeal, concern a priority dispute between Bankers Trust Company of New York (Bankers), beneficiary of a deed of trust, and the holders of several mechanics’ liens on the same property. The El Paso County District Court found Bankers’ interest junior to the interests of all but one of the lien claimants. We affirm the judgments.

The Breaks Land Corporation (BLC), owner of a Colorado Springs apartment project, hired Steven Jacobs and Associates (Jacobs), an architectural firm, in June 1972 to prepare preliminary plans and drawings for the project. BLC also hired Lovejoy & Williams, Inc. (now G. L. Williams & Partners, Ltd.), an engineering firm, to perform engineering services for the project. Neither Jacobs nor Lovejoy & Williams had a written contract with BLC.

BLC submitted Jacobs’ plans and drawings to Bankers to obtain financing for the project. Bankers made the construction loan to BLC in mid-November 1972, which was secured by a deed of trust on the property, dated November 14, 1972, and recorded November 20, 1972.

BLC retained Cokany Construction Company (Cokany) as general contractor for the project, by a contract dated November 14, 1972. *471 However, Cokany did not obtain its Colorado license until March 22, 1973.

Pursuant to its loan agreement, Bankers disbursed approximately $1.27 million from November 1972 to January 1974. When BLC defaulted on its obligations, Bankers began proceedings to forclose its deed of trust through the public trustee. The public trustee sold the property at public sale on May 23, 1974, to Bankers, the sale was approved by order of the district court, and on December 30, 1975, Bankers received a public trustee’s deed to the property.

El Paso Pre-Cast Company, a supplier of materials for the property, filed a complaint on February 6, 1974, to foreclose its mechanics’ lien against the property. Bankers was named a party defendant and asserted a first lien under its deed of trust. It also challenged the constitutionality of the mechanics’ lien statutes.

Work on the project substantially ceased on February 15, 1974. However, in late February and again on March 1, Lovejoy & Williams performed site inspections. It did not bill BLC for these unrequested site inspections, nor did it report its findings to BLC. Its last work billed to BLC occurred on February 8, 1974.

Lovejoy & Williams filed a lien statement on May 16, 1974. On April 4, 1975, numerous lien claimants, including Lovejoy & Williams, intervened in the action filed by El Paso Pre-Cast.

After trial, the district court ruled that the interests of ten lien claimants related back to a time prior to the filing for record of Bankers’ deed of trust and thus were senior to Bankers’ lien. The court denied Lovejoy & Williams’ lien on the grounds that it had not been timely filed. Bankers’ challenge to the constitutionality of the mechanics’ lien statutes was rejected by the court.

Bankers appeals from the district court judgment in favor of the lien claimants, contending that its deed of trust is prior to all of the mechanics’ liens, and that the Colorado mechanics’ lien procedures violate due process. Lovejoy & Williams appeals the denial of its lien for failure to timely file a lien statement.

I.

Section 38-22-106(1), C.R.S. 1973, concerning priority of mechanics’ liens, provides:

“All liens established by virtue of this article shall relate back to the time of the commencement of work under the contract between the owner and the first contractor, or, if said contract is not in writing, then such liens shall relate back to and take effect as of the time of the commencement of the work upon the structure or improvement, and shall have priority over any lien or encumbrance subsequently intervening * *

The district court ruled that the commencement of work by Jacobs and by Lovejoy- & Williams before Bankers filed its deed of trust *472 established the priority date for all valid mechanics’ liens on the project. Thus, under the foregoing statute, these liens had priority over Bankers’ deed of trust.

Bankers argues in the first instance that determination of the priority date depends upon whether there was a written contract between the owner and the “first contractor”; and that since here there was a written contract between Cokany and BLC, the owner, the priority date related back to the commencement of the work under the written contract. It follows, it is argued, that since no work was performed under the written contract until long after Bankers’ deed of trust was recorded, the lien of the deed of trust was therefore prior to the interests of the mechanic-lien claimants. We do not agree.

Regarding the contention that Cokany, not Jacobs or Lovejoy & Williams, was the “first contractor,” the mechanics’ lien statutes do not define “first contractor.” However, section 38-22-108(1) defines principal and subcontractors as follows:

“Every person given a lien by this article whose contract, either express or implied, is with the owner or reputed owner or his agent or other representative, is a principal contractor and all others are subcontractors * * Based on this statute, every lienholder is a contractor, either a principal contractor or subcontractor, and this does not depend on whether the contract is in writing. And section 38-22-101(1) expressly includes architects and engineers in the class of those eligible for mechanics’ liens. Consequently, Jacobs and Lovejoy & Williams were both contractors within the contemplation of section 38-22-106(1).

Whether one is a “first contractor” does not depend upon whether the contract is in writing, but rather at what time the contract, either express or implied, is entered into with the owner. There is no dispute that Jacobs’ and Lovejoy & Williams’ contracts with BLC were prior to Cokany’s written contract. Thus, Cokany was not the “first contractor” whose work set the priority date for mechanics’ liens.

Alternatively, Bankers argues that, even if Jacobs or Lovejoy & Williams is determined to be the “first contractor,” the priority date is the commencement of work upon the structure or improvement. Section 38-22-106(1). In this context, Bankers contends: “work” means “lienable work”; and the commencement of work upon the structure or improvement means the start of actual, on-site construction; since the work of the architect or engineer, done before November 20, 1972 (the date of recording of the deed of trust), was not done on the structure or improvement, such work was not lienable work; on-site, actual construction did not start until after Bankers’ deed of trust was recorded. Therefore, in the view of Bankers, the trial court erred in granting a first lien to the mechanic-lien claimants.

*473 The district court assumed without deciding, and Bankers agreed, that “work” in the context of section 38-22-106(1) means lienable work. Assuming the correctness of this definition, it is clear by decisions of this court that an architect’s and engineer’s preliminary work is lienable. Sontag v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michael's Construction, Inc. v. American National Bank
2012 WY 76 (Wyoming Supreme Court, 2012)
Ferguson Enterprises, Inc. v. Keybuild Solutions, Inc.
275 P.3d 741 (Colorado Court of Appeals, 2011)
People v. Cohn
160 P.3d 336 (Colorado Court of Appeals, 2007)
Mutual Savings Ass'n v. Res/Com Properties, L.L.C.
79 P.3d 184 (Court of Appeals of Kansas, 2003)
Kerns v. Kerns
53 P.3d 1157 (Supreme Court of Colorado, 2002)
Merrick & Co. v. Estate of Verzuh
987 P.2d 950 (Colorado Court of Appeals, 1999)
Printz Services Corp. v. Main Electric, Ltd.
949 P.2d 77 (Colorado Court of Appeals, 1998)
Powder Mtn. Painting v. Peregrine Joint Venture
899 P.2d 279 (Colorado Court of Appeals, 1994)
Pds Engineering Const. v. Double Rs, No. Cv90-0378684 (Dec. 19, 1991)
1991 Conn. Super. Ct. 10306 (Connecticut Superior Court, 1991)
Gabel v. Jefferson County School District R-1
824 P.2d 26 (Colorado Court of Appeals, 1991)
KETCHUM, KONKEL v. Heritage Mt.
784 P.2d 1217 (Court of Appeals of Utah, 1989)
General Growth Development Corp. v. A & P Steel, Inc.
678 F. Supp. 243 (D. Colorado, 1988)
Columbia Group, Inc. v. Jackson
725 P.2d 1110 (Arizona Supreme Court, 1986)
C.J. Richard Lumber Co. v. Melancon
476 So. 2d 1018 (Louisiana Court of Appeal, 1985)
Calder Bros. Co. v. Anderson
652 P.2d 922 (Utah Supreme Court, 1982)
Seracuse Lawler & Partners, Inc. v. Cooper Mountain
654 P.2d 1328 (Colorado Court of Appeals, 1982)
Mobile Components, Inc. v. Layon
1980 OK 173 (Supreme Court of Oklahoma, 1980)
Franklin Contract Sales Co. v. First National Bank
615 P.2d 684 (Supreme Court of Colorado, 1980)
Williams & Works, Inc. v. Springfield Corp.
293 N.W.2d 304 (Michigan Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
560 P.2d 457, 192 Colo. 468, 1977 Colo. LEXIS 713, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bankers-trust-co-v-el-paso-pre-cast-co-colo-1977.