C.J. Richard Lumber Co. v. Melancon

476 So. 2d 1018, 1985 La. App. LEXIS 10009
CourtLouisiana Court of Appeal
DecidedOctober 10, 1985
DocketNo. 84-609
StatusPublished
Cited by4 cases

This text of 476 So. 2d 1018 (C.J. Richard Lumber Co. v. Melancon) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.J. Richard Lumber Co. v. Melancon, 476 So. 2d 1018, 1985 La. App. LEXIS 10009 (La. Ct. App. 1985).

Opinion

KING, Judge.

The issues presented by this appeal are whether or not the trial court was correct in upholding the constitutionality of Louisiana’s Private Works Act and whether or not the trial court was correct in including Louisiana Sales Taxes in the amounts that can be recovered under the Louisiana Private Works Act.

C.J. Richard Lumber Company, Inc. (hereinafter the plaintiff) instituted this suit to enforce a materialman’s lien filed by it pursuant to the Louisiana Private Works Act, LSA-R.S. 9:4801 et seq., (hereinafter the Act) for materials sold by it to Harold Melancon, d/b/a Harold Melancon Painting (hereinafter the contractor) to be used for the improvement of the home and property of Vernon and Karlene Bell (hereinafter the defendants). Judgment was rendered by default in favor of plaintiff and against the contractor. Defendants filed an answer, a reconventional demand for a declaratory judgment that the law upon which plaintiff based its claim was unconstitutional, and a third party demand against the contractor for any sums they might be ordered to pay to plaintiff on the main demand. After a trial on the merits, the trial judge recognized and maintained the plaintiff’s materialman’s lien, and rendered a money judgment on the main demand in favor of the plaintiff and against the defendants and on the third party demand in favor of the defendants and against the contractor.

The defendants appeal the judgment rendered in favor of the plaintiff and against them and argue that the trial court erred in (1) not holding unconstitutional the Louisiana Private Works Act, LSA-R.S. 9:4801 et seq.; and (2) including sales taxes in the amount recoverable under the Act by the plaintiff from the defendants. We affirm.

FACTS

Defendants entered into a written contract for improvements to their home with the contractor. The written contract provided that the contractor was to make cer[1020]*1020tain improvements on the defendants’ home for a total price of $7,838.28 and additionally provided: “All labor and materials furnished.” The defendants did not avail themselves, as permitted by the Act, to obtain a bond from the contractor nor did they cause their written construction contract and a bond to be filed, as also permitted by the Act.

During the month of August, 1982, the contractor purchased building construction materials from the plaintiff for use on the home of defendants. These materials were either delivered by plaintiff to the defendant’s property or were picked up at plaintiff's store by the contractor or his representatives and taken to the defendants’ property. All of these materials were then used by the contractor in constructing improvements on the home of the defendants.

The contractor continued the work on defendants’ home until sometime in September, 1982 at which time the contractor discontinued work and failed to repair leaks in the roof of the defendants’ home. The defendants then had to hire another contractor to complete the job and fix the leaking roof of their home.

When payment for the materials was not made by the contractor, the plaintiff timely filed a materialman’s lien asserting its privilege against the defendants’ property, pursuant to LSA-R.S. 9:4801 and 9:4822, for the cost of the materials it sold to the contractor which were used in making the improvements to the defendants’ home. This lien was recorded on October 14, 1982 in St. Martin Parish, Louisiana, where the defendants’ property is situated. Notice of this lien and demand for payment were sent to the defendants, which they received on October 16,1982. Notice of the lien and demand for payment were again sent to the defendants, which they received on February 2, 1983. Notice of the lien and demand for payment were also made by plaintiff on the contractor.

After receiving no response from either the contractor or the defendants, the plaintiff filed suit on March 17, 1983 against both the contractor and the defendants seeking a money judgment and to enforce the privilege arising from its materialman’s lien. Plaintiff also filed a Notice of Lis Pendens in the records of St. Martin Parish, Louisiana on March 18, 1983. No Answer or other responsive pleadings were timely filed by the contractor and a Preliminary Default Judgment was taken against him by plaintiff, which was later confirmed on June 10, 1983. The defendants answered the plaintiff’s petition by an answer of general denial, raising as an affirmative defense that the law on which plaintiff based its claim was unconstitutional, and also filed a Reconventional Demand seeking a declaratory judgment that LSA-R.S. 9:4801 and 9:4802 are unconstitutional, as violative of the Fourteenth Amendment to the United States Constitution. The defendants also included with their Answer a third party demand against the contractor, praying that the contractor be held liable to the defendants for any amounts they might be cast in any judgment rendered against them in favor of the plaintiff in the main demand and for other sums they had been required to pay on account of the contractor’s default.

After a trial on the merits, judgment was rendered on the main demand in favor of plaintiff and against the defendants (1) recognizing the materialman’s lien; and (2) holding the defendants liable to plaintiff in the amount of $3,042.77, which was the price of the materials sold and sales tax, with legal interest thereon from October 14, 1982, the date of the filing of the mate-rialman’s lien, together with the sum of $43.00 as the cost of recording the materi-alman’s lien. Judgment was also rendered rejecting the defendant’s reconventional demand to have the Louisiana Private Works Act declared unconstitutional. Judgment was rendered in favor of the defendants on their third party demand against the contractor for the sum of $3,085.77, subject to a credit of $2,296.22, with legal interest thereon from date of judicial demand, until paid. All costs were assessed against the defendants on the main demand, and against the contractor on the third party [1021]*1021demand. The defendants subsequently timely perfected this devolutive appeal from the judgment rendered against them.

UNCONSTITUTIONALITY OF THE ACT

The defendants first contend that inasmuch as LSA-R.S. 9:4801 and 9:4802 impose personal liability on an owner of property for failure to exact a bond from his contractor, the Louisiana Private Works Act violates their right to equal protection of law under the United States Constitution and deprives them of their property without due process of law.

LSA-R.S. 9:4801 provides in relevant part:

“The following persons have a privilege on an immovable to secure the following obligations of the owner arising out of a work on the immovable:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jermaine C. Jackson v. State of Florida
191 So. 3d 423 (Supreme Court of Florida, 2016)
Baton Rouge Press, Inc. v. Andries
865 So. 2d 950 (Louisiana Court of Appeal, 2004)
Baton Rouge Press, Inc. v. Donna J. Andries
Louisiana Court of Appeal, 2004
Norris Rader, Inc. v. Swilley
625 So. 2d 1125 (Louisiana Court of Appeal, 1993)
C. J. Richard Lumber Co. v. Melancon
478 So. 2d 1236 (Supreme Court of Louisiana, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
476 So. 2d 1018, 1985 La. App. LEXIS 10009, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cj-richard-lumber-co-v-melancon-lactapp-1985.