Corporation v. Gould

431 P.2d 466, 163 Colo. 356
CourtSupreme Court of Colorado
DecidedSeptember 18, 1967
Docket21572
StatusPublished
Cited by15 cases

This text of 431 P.2d 466 (Corporation v. Gould) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corporation v. Gould, 431 P.2d 466, 163 Colo. 356 (Colo. 1967).

Opinion

Opinion by

William L. Gobin. *

In the trial court, defendants in error, Gould and Vittum, brought this action against one Harper M. Ora-hood, trustee-owner of an apartment building and parking area to foreclose the mechanics’ lien claimed by them. The trustee-owner did not defend. Plaintiff in error, 3190 Corporation, intervened claiming a prior lien based on foreclosure of a deed of trust. We refer to the parties as plaintiffs and intervenor, as they appeared in the trial court. With one exception the facts are not in dispute.

On May 13, 1960 Mark Ramsey, then owner of the real property which was already encumbered by one loan not involved in this action, obtained a loan secured by an unrecorded deed of trust for $23,200 from Summit Investment Co. (This instrument was later recorded on June 24, 1961.)

In July 1960 Ramsey commenced building a 43-unit apartment on the land, serving as his own contractor in the construction. On November 9, 1960, while construction was still in progress, he obtained a $25,000 loan secured by a deed of trust, recorded November 15, 1960 from Denver Industrial Company to pay debts not connected with this property.

The Denver Building Inspection Department gave a certificate of occupancy on January 13, 1961 showing that the building then complied with the building codes of the city. Witnesses for the intervenor testified that they were living in some apartments in the building at this time and did not see any construction in progress. Plaintiffs’ witnesses testified the building was not complete at that time, that portions were not painted, storage bins had to be constructed, parking areas had *359 to be completed, and other things were required to be done to complete the structure and project. Ramsey’s capital was exhausted and he used rental income as he received it to work on the uncompleted items.

Ramsey’s financial condition became more precarious and Denver Industrial Company started proceedings to foreclose its deed of trust. Several creditors, including plaintiffs, hoping to complete the construction and salvage the amounts owed them, persuaded Ramsey to convey the property to Harper M. Orahood, trustee. Among creditors who did not go along with this, plan were a Mr. Stoddard and a Mr. Marx, officers of Summit Investment Company, who are also the organizers and principal officers of intervenor.

By agreement with Orahood, plaintiffs furnished and purchased material and provided labor to finish parts of the building and grounds which were necessary to make the apartment project complete. For this material and labor plaintiffs filed their mechanics’ lien claim and have brought this action.

Earl C. Gould, and one Donald McDonald, as trustees, became assignees of the Denver Industrial Company and as such became entitled to the benefits of the foreclosure of the deed of trust dated November 9, 1960. The Summit Investment Co. assigned its interest in the deed of trust for their benefit to intervenor, which then redeemed the property from the foreclosure and contested plaintiffs’ right to their mechanics’ lien.

The only disputed evidence is on the question of whether there was cessation of labor for 30 days or more at any time between July, 1960, and July, 1961, when the construction was completed. This contested matter goes to the very heart of the litigation and presents the main problem involved herein because only if there was continuity without the allowable 30 day interruption would plaintiffs be able to relate their claim back to the beginning of the construction and thus assert the priority of their mechanics’ lien. The court found from the con *360 flicting evidence on this issue in favor of the plaintiffs and concluded that the lien did revert back to the commencement of the structure. On this and three other rulings of the court intervenor seeks the reversal of the judgment entered in favor of the plaintiffs.

Intervenor first contends the court erred in holding that plaintiffs come within the class of persons who may claim a mechanics’ lien because, they assert, it was not contemplated that they would do any of the work personally. Intervenor’s theory is that plaintiffs merely advanced credit to Orahood to enable him to obtain labor and material and relies upon Kern v. Guiry Bros. Co., 60 Colo. 286, 153 P. 87. Our answer to this point of argument is that C.R.S. 1963, 86-3-1, provides in pertinent part:

“Mechanics, materialmen, contractors, subcontractors, builders, and all persons of every class performing labor upon or furnishing materials to be used in the construction, alteration, addition to, or repair, * * * of any building, * * * shall have a lien upon the property upon which they have rendered service or bestowed labor * * * for the value of such services rendered -or labor done or material furnished, whether at the instance of the owner, or of any other person acting by his authority or under him, * *

Plaintiffs in this case were contractors actually in the business of construction such as performed here and purchased the material and contracted and paid for the labor done. We hold they come within the class of persons as defined in the statute, supra, and may claim a mechanics’ lien.

Intervenor’s second contention is that the court erred in ruling that a principal contractor can relate back his priority to the date when work was commenced by the owner of the property.

C.R.S. 1963, 86-3-6, states in part:

“All liens established by virtue of this article shall relate back to the time of the commencement of work *361 under the contract between the owner and the first contractor, or, if said contract be not in writing, then such liens shall relate back to and take effect as of the time of the commencement of the work upon the structure or improvement, and shall have priority over any and every lien or encumbrance subsequently intervening, or which may have been created prior thereto, but which was not then recorded, and of which, the lienor, under this article, did not have actual notice. * * *” (Emphasis added.)

Intervenor’s claim is based on a deed of trust recorded November 15, 1960. Construction began in July, 1960, and plaintiff’s services were performed from April 6, 1961 to the following June. The trial court found on conflicting evidence that from the time construction started until plaintiffs had completed their tasks, work was continually in progress. The court’s determination that plaintiffs are entitled to relate back their lien claim to July, 1960, is supported by substantial and competent evidence, and we will not disturb such findings on review.

Intervenor’s third contention is that it was error to rule that a principal contractor can relate back his priority to a date prior to the time the owner with whom he was dealing acquires his interest in the property. It is argued that Orahood, as trustee, acquired title to the subject property on March 22, 1961 and subsequent thereto made arrangements with plaintiffs, who became principal contractors, and that since there was a complete change of ownership, there can be no relation back.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brickman Group, Ltd. v. Compass Bank
83 P.3d 1167 (Colorado Court of Appeals, 2003)
Skillstaff of Colorado, Inc. v. Centex Real Estate Corp.
973 P.2d 674 (Colorado Court of Appeals, 1998)
General Growth Development Corp. v. A & P Steel, Inc.
678 F. Supp. 243 (D. Colorado, 1988)
Valley Federal Savings & Loan Ass'n v. T-Bird Home Centers, Inc.
741 P.2d 826 (New Mexico Supreme Court, 1987)
Ragsdale Bros. Roofing, Inc. v. United Bank of Denver, N.A.
744 P.2d 750 (Colorado Court of Appeals, 1987)
Thirteenth Street Corp. v. A-1 Plumbing & Heating Co.
640 P.2d 1130 (Supreme Court of Colorado, 1982)
Barker's Inc. v. B.D.J. Development Co.
308 N.W.2d 78 (Supreme Court of Iowa, 1981)
A-1 Plumbing & Heating Co. v. Thirteenth Street Corp.
616 P.2d 141 (Colorado Court of Appeals, 1980)
Wasson v. Hogenson
583 P.2d 914 (Supreme Court of Colorado, 1978)
Bankers Trust Co. v. El Paso Pre-Cast Co.
560 P.2d 457 (Supreme Court of Colorado, 1977)
Lemler v. Real Estate Commission
558 P.2d 591 (Colorado Court of Appeals, 1976)
Ridge Erection Co. v. Mountain States T. & T. Co.
549 P.2d 408 (Colorado Court of Appeals, 1976)
C & W ELECTRIC INC. v. Casa Dorado Corporation
523 P.2d 137 (Colorado Court of Appeals, 1974)
American Fac. Assoc., Ltd. v. Triangle Heat. & Sm Co.
503 P.2d 163 (Colorado Court of Appeals, 1972)
Kobayashi v. Meehleis Steel Co.
472 P.2d 724 (Colorado Court of Appeals, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
431 P.2d 466, 163 Colo. 356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corporation-v-gould-colo-1967.