American Fac. Assoc., Ltd. v. Triangle Heat. & Sm Co.

503 P.2d 163, 31 Colo. App. 240
CourtColorado Court of Appeals
DecidedAugust 22, 1972
Docket70-411
StatusPublished
Cited by13 cases

This text of 503 P.2d 163 (American Fac. Assoc., Ltd. v. Triangle Heat. & Sm Co.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Fac. Assoc., Ltd. v. Triangle Heat. & Sm Co., 503 P.2d 163, 31 Colo. App. 240 (Colo. Ct. App. 1972).

Opinion

503 P.2d 163 (1972)

AMERICAN FACTORS ASSOCIATES, LIMITED, a corporation doing business as Silver Steel Company, Plaintiff-Appellee,
v.
TRIANGLE HEATING AND SHEET METAL COMPANY, a corporation, et al., Defendants-Appellees,
International Business Machines Corporation, a corporation, Defendant-Appellant.

No. 70-411.

Colorado Court of Appeals, Division I.

August 22, 1972.
Rehearing Denied September 12, 1972.
Certiorari Denied December 4, 1972.

*164 Fairfield & Woods, Peter F. Breitenstein, Charles E. Matheson, Denver, for plaintiff-appellee.

Hoffman, Goldstein & Armour, Abe L. Hoffman, Dyer & Swenson, Denver, for defendant-appellant.

D. L. Glenn, Denver, for Air Purification Company, defendant-appellee.

Hopkins, Hurth & Yeager, Charles A. Hurth, Jr., Boulder, for Boulder Steel and Masonry Supply, Inc., defendant-appellee.

Selected for Official Publication.

PIERCE, Judge.

This action originally involved multiple parties and various claims, cross-claims, and counterclaims between them. On appeal, however, the only issues raised concern the respective rights of three alleged mechanics' lien holders against land owned by International Business Machines Corporation (IBM). Those involved here are American Factors Associates, Limited, doing business as Silver Steel Company (Silver); Boulder Steel and Masonry Supply, Inc., (Boulder Steel); and Air Purification Company (Air Purification).

This dispute arose out of construction of the IBM plant at Niwot, Colorado. IBM retained N. G. Petry Co. (Petry) as general contractor for construction of the plant. Petry, in turn, subcontracted with Cook Construction Co. to do the mechanical work. Cook subcontracted with Triangle Heating & Sheet Metal Co. (Triangle) to manufacture the ducts. Each lien claimant supplied goods to Triangle, allegedly to be used in the construction of the IBM plant. Triangle went out of business prior to settling accounts with these claimants. As a result, the claimants sought foreclosure on the IBM property. The trial court ruled in their favor, and IBM brought this appeal.

*165 I.

IBM's first contention is that the trial court erred in applying the mechanics' lien law as it existed prior to certain amendments to the statute. Specifically, in 1965, the mechanics' lien statute was amended to provide more precise time requirements for filing liens. 1965 Perm.Supp., C.R.S.1963, 86-3-9. However, the amendment, by its terms, applied only to construction commenced after that date. 1965 Perm.Supp., C.R.S.1963, 86-3-27. The trial court determined that this amendment did not apply to the construction at the IBM plant, even though portions of that construction began after October 1, 1965. The court found that the proposed plant at IBM was a continuing project, designed to function as one integrated unit. In the absence of proof that specific portions of the project were not essential components of the whole, the trial court applied the correct statute. State Bank v. Plummer, 54 Colo. 144, 129 P. 819; Cary Hardware Co. v. McCarty, 10 Colo.App. 200, 50 P. 744.

We reject IBM's claim that these cases are distinguishable. While it is true that they deal with the issue of "relating back" to determine at what point in time a job was started so as to determine when the lien attached, the principles regarding the commencement date of continuing projects, enunciated therein, are relevant and controlling in this case.

II.

IBM next contends that, even were the pre-1965 law applicable, these claimants did not timely file because IBM occupied the buildings prior to completion of the construction and the work done thereafter was fitting-up in nature and not part of the original contract. The trial court rejected this contention. It ruled that the work done after IBM's occupation was significant and necessary; hence, lien statements did not need to be filed until after completion of this work.

IBM, relying upon C.R.S.1963, 86-3-9(8),[1] argues that occupation of the building was conclusive proof of its completion. It is undisputed that IBM occupied the building prior to the completion date determined by the trial court. However, the Colorado Supreme Court has previously held that C.R.S.1963, 86-3-9(8) is not to be construed in an unreasonable way, and that it is within the province of the finder of fact to rule that occupation of premises does not necessarily mean completion of the project. Mortgage Brokerage Co. v. W. B. Barr Lumber Co., 91 Colo. 445, 16 P.2d 32. Nor, as IBM suggests, can the rule in Mortgage Brokerage Co. be restricted to work done by the principal contractor on the initial contract after occupation. To so rule, would strip the protections offered by the lien statute of any vitality with regard to subcontractors. See 3190 Corp. v. Gould, 163 Colo. 356, 431 P.2d 466. Here, there was sufficient evidence presented for the trial court to find that occupation by IBM was not coterminous with completion.

We have considered all of IBM's claims regarding the nature of the work done after occupation and up to the completion date as determined by the trial court, together with its claim that the work entailed in fitting up the new buildings for occupancy was not of such a nature as to extend the time for filing lien claims. *166 While it is true that each additional increment of work, in and of itself, might not be substantial enough to entitle the mechanic to a lien claim on the entire project, the fit-up work, which IBM claims was not substantial in nature, was necessary for efficient occupation of the building. It was in no respect trivial. Therefore, it was not error to include that work within the time period to file lien claims. See Lichty v. Houston Lumber Co., 39 Colo. 53, 88 P. 846; Stidger v. McPhee, 15 Colo.App. 252, 62 P. 332. Determination of completion date is within the province of the trier of fact and will not be overturned on appeal where the evidence supports its finding. Kaibab Lumber Co. v. Osburne, 171 Colo. 49, 464 P.2d 294.

III.

IBM's next contention is that each lien claimant failed to establish that the goods supplied by it were, in fact, delivered to the IBM construction site for incorporation into the project and, for that reason, it was error to enter judgment in their favor. We agree, in part, with this contention.

Initially, it should be noted that the failure of IBM and Petry, as general contractor, to file the construction contract, as provided by C.R.S.1963, 86-3-1(3), results in each claimant becoming the statutory agent of the owner. As such, IBM's contention that they are too remote to be entitled to a lien is without merit. Therefore, the question becomes whether they have done all else that is required to establish themselves as lien claimants.

The fundamental principle involved in mechanics' liens is that, in order to be entitled to a lien, the lienor must add value to the structure of the owner. With value added, the owner would gain an unjust enrichment were he not required to pay for the services or material rendered. Farmers Irrigation Co. v. Kamm, 55 Colo. 440, 135 P. 766; Kobayashi v. Meehleis Steel Co., 28 Colo.App. 327, 472 P.2d 724.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCann v. Lettig
928 P.2d 816 (Colorado Court of Appeals, 1996)
Colorado Leasing Corp. v. Borquez
738 P.2d 377 (Colorado Court of Appeals, 1986)
Richter Plumbing & Heating, Inc. v. Rademacher
729 P.2d 1009 (Colorado Court of Appeals, 1986)
Kuchenski v. Kramer Sheet Metal, Inc.
377 N.W.2d 133 (North Dakota Supreme Court, 1985)
Daniel v. MJ Development, Inc.
603 P.2d 947 (Colorado Court of Appeals, 1979)
US Fidelity & Guaranty v. YOUNG LIFE CAMPAIGN
600 P.2d 79 (Colorado Court of Appeals, 1979)
Wilkinson v. Wilkinson
585 P.2d 599 (Colorado Court of Appeals, 1978)
Zwick v. Simpson
572 P.2d 133 (Supreme Court of Colorado, 1977)
Zwick v. Simpson
551 P.2d 216 (Colorado Court of Appeals, 1976)
In Re Marriage of Hines
525 P.2d 517 (Colorado Court of Appeals, 1974)
C & W ELECTRIC INC. v. Casa Dorado Corporation
523 P.2d 137 (Colorado Court of Appeals, 1974)
STAR SPRINKLER CORP. OF FLA v. Mead & Mount Const. Co.
508 P.2d 801 (Colorado Court of Appeals, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
503 P.2d 163, 31 Colo. App. 240, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-fac-assoc-ltd-v-triangle-heat-sm-co-coloctapp-1972.