Farmer's Irrigation Co. v. Kamm

55 Colo. 440
CourtSupreme Court of Colorado
DecidedSeptember 15, 1913
DocketNo. 7824
StatusPublished
Cited by8 cases

This text of 55 Colo. 440 (Farmer's Irrigation Co. v. Kamm) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farmer's Irrigation Co. v. Kamm, 55 Colo. 440 (Colo. 1913).

Opinion

Chief Justice Musser

delivered the opinion of the court:

By this writ of error it is sought to review a judgment of the district court, decreeing a mechanic’s lien upon the ditch and reservoir of plaintiff in error. The evidence is not incorporated into the record. The defendant in error claimed a lien on account of materials furnished to one Harris, a subcontractor. That the materials were furnished is not denied. The only questiou raised is the validity of the lien. The plaintiff in error claims that its validity sufficiently appears from the record proper. The question as presented to this court, therefore, is a demurrer to the complaint upon the ground [441]*441that it does not state facts sufficient to constitute a cause of action against the plaintiff in error.

The defendants named in the complaint were C. Gr. Harris, Harry Hokasona, The Antlers Orchard Development Company and The Farmer’s Irrigation Company, the latter being the plaintiff in error. The action was dismissed as to the Orchard Development Company and as to Hokasona. The complaint alleges that Hokasona entered into a written contract to build up the banks of the ditch and to enlarge the dam of the reservoir; that Hokasona subcontracted all of the work to the defendant Harris by written contract, which is set out in the complaint. In this contract, it was recited that Hokasona had entered into the contract to enlarge about eight miles of the ditch, to build up its bank with material taken from it and to enlarge the dam of the reservoir belonging to the plaintiff in error; that Hokasona- was desirous of subletting the work to Harris; that he did thereby sublet all of the work upon the ditch, dam and reservoir to Harris, and the latter agreed to perform it. The contract also stated that the estimated amount of earth to be removed from the ditch was 45,000 cubic yards, and the estimated amount of earth work on the dam was 90,000 cubic yards. Hokasona was to furnish an engine for pulling the grader, an earth elevator and dump' wagons, and the Antlers Orchard1 Development Company was to furnish rollers and sprinklers for use upon the dam, and was to spread the material as delivered. Harris was to be paid twenty cents per cubic yard for all earth work on the ditch, seventy cents per cubic yard for rock work, and nineteen cents per cubic yard . for earth material removed for the enlarging of the dam, and the contract specifically stated “that second party’s (Harris’) work in connection with the enlarging of said dam is the moving of the earth material therefor.” After setting out the contract, the complaint continues [442]*442and alleges that subcontractor Harris purchased from plaintiff, for use in, upon and about the construction of the said work, “a large amount or quantity of material consisting of lumber, nails, lath, wire, tar-paper, and other hardware and materials;” that Harris, as such subcontractor, purchased from another, for use in, upon and about the construction of said work, 6,862 feet of lumber, the claim for which was assigned to plaintiff. The complaint then goes on and recites that a mechanic’s lien statement was filed and concludes with other allegations necessary in such an action.

It is pláin from this complaint that Harris was to perform work, only, upon the ditch, reservoir and dam by removing earth therefrom and placing it, or some of it, upon the dam. He was not to furnish any materials that would enter into the construction. Under his contract with Iiokasona, he could have no use for lumber and such materials as are specified in the complaint, for which the lien is claimed, so far as putting those materials into the structure is concerned, and, according to the complaint, it was only his contract with Hokasona that he was performing. The only sense in which those materials can be said to have been used in the construction of the ditch and dam, under Harris’ contract, is the. same sense in which it might have been said that the dump wagons were used, or that it might have had said that other appliances are used in the performance of work. For instance, the lumber and other material sold by the plaintiff may have been bought to be used for building temporary sheds and bunk-houses for the animals and men employed upon the work, and in that sense may be said to have been furnished to be used in the construction of the ditch and dam. In no other sense can it be said that Harris could have used them in the performance of his contract, according to the allegations of the complaint, or that they were to be used in [443]*443the construction of the ditch and dam. That, however, is not the sense in which materials are to be used in the construction of a building, ditch or other structure in order that a material-man may have a lien therefor. The statute (Sec. 4025 Rev. Stat. 1908) provides that (mechanics, material men, contractors, subcontractors, and all persons of every class performing labor upon or furnishing materials to be used in the construction, alteration, addition to, or repair, either in whole or in part of any * * ditch, flume, aqueduct, reservoir * * shall have a lien upon the property * * for which they have furnished materials, ’ ’ etc.

So far as we have been able to investigate the authorities, they are unanimous in holding that under such a statute, in order to give a material man a lien,’ material must be furnished to be used in the construction in the sense that it is to be wrought up in the structure so as to become a part of it when completed, as for instance lumber is to be used in the construction of a house by being wrought up and actually used in the building as a part of it, or that the material is to be directly consumed in the structure so as to improve it. The fundamental principle upon which mechanics’ liens are based is that labor and material have gone into the property of another and made it more valuable, so that when the owner is called upon to protect his property from a lien by paying for the labor or material he is but paying for something that he has received. Value has been created by labor performed upon and material wrought into the property, or consumed directly in its improvement, and he who has furnished such labor or material has added to the value and is given a lien to the extent of the addition he has made. Lindemann v. Belden, Etc. Co., 16 Colo. App. 342, 365 Pac. 403.

To hold that a lien exists for materials furnished to be used about the construction, as an aid to the contractor [444]*444in the performance of his work, as his tools and appliances are aids, and which are not intended to go into the structure, or to be directly consumed in' its betterment, but are to be taken away when the work is completed, as the tools and appliances are taken away, would be violative of that fundamental principle and would be extending the provisions of the statute to cover claims not contemplated, a species of legislation which is forbidden to the judiciary. R. A. G. & S. R. Co. v. Bouscher, 9 Colo. 385, 12 Pac. 438.

In the case last cited, the claim of the plaintiff was for labor performed in and upon mines as foreman, superintendent and mechanic, also as the owner’s disbursing agent and in keeping books. The labor as foreman, superintendent and mechanic was held to afford a basis for a lien under the statute as it then was, and which was similar to the present one, but with regard to the labor as disbursing agent and bookkeeping this court said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CPS Distributors, Inc. v. Federal Insurance Co.
685 P.2d 783 (Colorado Court of Appeals, 1984)
A-1 Plumbing & Heating Co. v. Thirteenth Street Corp.
616 P.2d 141 (Colorado Court of Appeals, 1980)
American Fac. Assoc., Ltd. v. Triangle Heat. & Sm Co.
503 P.2d 163 (Colorado Court of Appeals, 1972)
Plateau Supply Co. v. Bison Meadows Corp.
500 P.2d 162 (Colorado Court of Appeals, 1972)
Jones v. People
393 P.2d 366 (Supreme Court of Colorado, 1964)
Brannan Sand & Gravel Co. v. Santa Fe Land & Improvement Co.
332 P.2d 892 (Supreme Court of Colorado, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
55 Colo. 440, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farmers-irrigation-co-v-kamm-colo-1913.