Opinion

Mr. Chief Justice Moore,

after making the foregoing statement of facts, delivered the opinion.

It is contended by Howitt’s counsel that Beach and Hogue knew that certain material furnished by them, respectively, was not used in the building, and that the claims therefor were therefore willfully false; that, [404]*404while Nottingham & Company filed their claim within 30 days from the completion of the building, more than that period had elapsed after such material was furnished, and for these reasons no lien attached in either case to the real property sought to be incumbered in this statutory method. Counsel for Beach and Hogue jointly maintain that the material provided by their clients was furnished to be used in the erection of said building, and this fact alone entitles them to their liens for the respective amounts so demanded, notwithstanding some of this material may have been diverted from the purpose for which it was originally intended; while counsel for Nottingham & Company insist that their client, having filed their claim within 30 days from the completion of the house, complied with the requirements of the statute conferring the lien.

Considering first the rights of the latter claimants, the question is presented whether the lien was lost by the failure to file the notice thereof within 30 days from the time they ceased to furnish the material, it being admitted that it was filed within 30 days from the completion of the building. In Ainslie v. Kohn, 16 Or. 363 (19 Pac. 97), the court, construing in pari materia sections 3673 and 3678 of Hill’s Ann. Laws, held that the claim of lien, if filed within 30 days after the completion of the structure, was a compliance with the requirements of the statute. Thayer, J., in writing the opinion, says: “Whether the claim was filed within 30 days after the work and material were furnished is unimportant, provided it was done within 30 days after the house was completed.” While [405]*405this interpretation of the statute may be somewhat doubtful, it was approved in Curtis v. Sestanovich, 26 Or. 107 (37 Pac. 67); and, having become a settled rule, it must be held that the claim of Nottingham & Company was filed within the time prescribed by law, and hence the lien was thereby preserved.

Considering Beach’s claim next, the evidence tends to show that McHenry, at the time Howitt’s building was in process of construction, was erecting a building for himself, and also another structure, known as the “Reed House”; that Beach furnished to McHenry material of the value of $297.05 to be used in the construction of Howitt’s building, and delivered the same at the site thereof, but that McHenry, without Beach’s knowledge, removed therefrom and used in the Reed building a portion of said material, of the value of $80; that Beach made no charges for material furnished on account of the latter building, but had an account, and charged McHenry, individually, with the value of certain material which he supposed was furnished for his own dwelling; that in a settlement with McHenry, on account of the contract price for the completion of the Reed house, it was discovered that certain material used therein was manufactured by Beach, or came from his establishment, whereupon the sureties on McHenry’s bond for the faithful performance of said contract informed Beach of the discovery, who inspected the building, ascertained the value of such material, and accepted from the said sureties the sum of $80 in payment therefor, which amount he credited upon McHenry’s individual account. Thereafter Beach filed a claim against Howitt’s [406]*406building for the full amount of the material furnished to be used, but the court, disallowing the value of the part so diverted therefrom, and used in the Reed house, gave a decree for the balance due; and this presents for consideration the extent of the authority of a contractor to bind the owner of a building for material furnished to be used in its construction. The statute upon this subject, so far as applicable to the case at bar, reads as follows: “Every * * * lumber merchant * * * furnishing material * * * to be used in the construction * * * of any building * * * shall have a lien upon the same for the * * * material furnished at the instance of the owner of the building * * * and every contractor * * * having charge of the construction * * * of any building * * * shall be held to be the agent of the owner for the purposes of this act”: Hill’s Ann. Laws, § 3669. While the legislative assembly has thus declared the effect of the relation existing between the owner of real property and one who has entered into a contract with him for the erection of a building thereon, it has not defined the measure of the authority delegated, so that it becomes necessary to consider whether the contractor, in such case, is the general or special agent of the owner. If the former, he could doubtless bind his principal by every act connected with the duty intrusted to him, and, by the purchase and appropriation of unnecessary material, entail a burden upon him, the extent of which could be measured only by his avarice. If the latter, however, his authority would be limited to the procurement of material reasonably sufficient in [407]*407quantity for the completion of the structure in accordance with the terms of his contract,— a limitation of which persons dealing with him as such agent would be obliged to take notice.

In Andrews v. Kneeland, 6 Cow. 354, Savage, C. J., in distinguishing between these two classes of agents, and the measure of their respective powers, says: “ The difference between a general and a special agent is well understood. The principal is bound by the acts of a general agent, provided they are within the scope of his authority. But an agent constituted for a particular purpose, and under a limited and circumscribed power, cannot bind his principal by any act beyond his authority.” In Morrison v. Hancock, 40 Mo. 561, under a statute of Missouri which provides, in substance, that every person furnishing any material for a building shall have a lien upon the same, whether it was supplied at tbe request of the owner or contractor, it was held that the contractor was the agent of the owner. Fagg, J., in rendering the decision of the court, and defining the power of such agent, says: “Under the provisions of the special law authorizing this proceeding, these contractors, for certain purposes and to a certain extent, are to be treated as the agents of the company, with authority to bind it to the extent of the material necessary to complete their contract,” — in effect holding that the contractor is the special agent of the owner; for, if the agent can bind the principal to the extent only of the material necessary for the completion of the building, then it necessarily follows that he would be powerless to bind him for the payment of more [408]*408than that quantity, and, his authority being thus limited, he is a special agent. Section 3669 of our statute confines the lien to the property benefited by the material entering into the construction of a building, and, in doing so, the statute, in effect, limits the power of the contractor; for, were he the general agent of the owner, he could undoubtedly bind the latter personally for the payment of the balance due on account of the material purchased, if the proceeds of a sale of the property subject to the lien were insufficient to satisfy the demands of the materialman: Deardorff v. Everhartt, 74 Mo. 37.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Watkins v. St. Charles Memorial Hospital, Inc.
569 P.2d 4 (Oregon Supreme Court, 1977)
Smith v. DeKraay
342 P.2d 784 (Oregon Supreme Court, 1959)
Drake Lumber Co. v. Paget Mortgage Co.
274 P.2d 804 (Oregon Supreme Court, 1954)
State Ex Rel. Sauers v. C. J. Montag Co.
286 P. 995 (Oregon Supreme Court, 1930)
Paget v. Peters
289 P. 1119 (Oregon Supreme Court, 1930)
Northwest Lbr. & Fuel Co. v. Plantz
268 P. 763 (Oregon Supreme Court, 1928)
State Ex Rel. Trojan Powder Co. v. Johnson Contract Co.
253 P. 520 (Oregon Supreme Court, 1927)
James A. C. Tait & Co. v. Stryker
243 P. 104 (Oregon Supreme Court, 1926)
Christman v. Salway
205 P. 541 (Oregon Supreme Court, 1922)
Hammond Lumber Co. v. Yeager
197 P. 111 (California Supreme Court, 1921)
Portland v. New England Casualty Co.
189 P. 211 (Oregon Supreme Court, 1920)
Johnson v. Paulson
154 P. 685 (Oregon Supreme Court, 1916)
Harbridge v. Six Points Lumber Co.
152 P. 860 (Arizona Supreme Court, 1915)
Kollock & Co. v. Leyde
143 P. 621 (Oregon Supreme Court, 1915)
Arctic Lumber Co. v. Borden
211 F. 50 (Ninth Circuit, 1914)
Farmer's Irrigation Co. v. Kamm
55 Colo. 440 (Supreme Court of Colorado, 1913)
Fletcher, Crowell Co. v. Chevalier
81 A. 578 (Supreme Judicial Court of Maine, 1911)
Grants Pass Trust Co. v. Enterprise Mining Co.
113 P. 859 (Oregon Supreme Court, 1911)
Coffey v. Smith
97 P. 1079 (Oregon Supreme Court, 1908)
Valley Lumber & Manufacturing Co. v. Nickerson
93 P. 24 (Idaho Supreme Court, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
52 P. 192, 32 Or. 396, 1898 Ore. LEXIS 46, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fitch-v-howitt-or-1898.