State Ex Rel. Trojan Powder Co. v. Johnson Contract Co.

253 P. 520, 120 Or. 633, 1927 Ore. LEXIS 32
CourtOregon Supreme Court
DecidedFebruary 1, 1927
StatusPublished
Cited by11 cases

This text of 253 P. 520 (State Ex Rel. Trojan Powder Co. v. Johnson Contract Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Trojan Powder Co. v. Johnson Contract Co., 253 P. 520, 120 Or. 633, 1927 Ore. LEXIS 32 (Or. 1927).

Opinion

RAND, J.

This is an action to recover from the original contractor and its surety for powder furnished a subcontractor on public road work. Plaintiff recovered judgment against both defendants for the full amount of its claim, which included a claim for powder furnished to the subcontractor and not used in the performance of his contract, but which was diverted by him and used in the performance of a similar contract with other parties. The cause was tried to the court without the intervention of a jury. The trial court made its findings of fact and these findings under our statute have the force and effect of a verdict. The evidence upon which these findings were based is not before us. Among other things the court found:

“That heretofore and between the dates of June 10, 1921, and January 26, 1922, the plaintiff did at the *635 special instance and request of O. D. Wolfe, the said sub-contractor, sell and deliver to said O. I). Wolfe, certain powder, explosives, caps, fuse and incidental appliances for the use thereof. That said materials were ordered by said 0. D. Wolfe for use in the construction of the said Pittsburg-St. Helens Highway and were sold by plaintiff in good faith for use thereon and with the understanding that the same were to be used on said work, and said materials were delivered by the plaintiff to said work during the time aforesaid for use by the sub-contractor in the construction of said highway. That all of the said materials were used by the said sub-contractor in the construction of said highway with the exception of 30 cases of powder worth $244.00 which were diverted from said work by the said subcontractor and used by him elsewhere.”

■ Here we have a finding by the court that a part of the powder for which plaintiff has recovered judgment against the original contractor and its surety was not used up or consumed in the prosecution of the work which the subcontractor had contracted with one of the defendants to perform and for which the bond was given and has never gone into or become a part of the work, but has been diverted to and used in the performance of a contract to which the defendants are strangers.

It is obvious that unless made so by statute, an original contractor on public work, in the absence of an express authorization, is not responsible for things purchased by his subcontractor unless the things purchased are in some way referable to the contract between them and that if the original contractor is not liable, then his surety also is not liable.

Section 4435, Or. L., provides that, “All contracts executed for the improvement of state highways shall be made in the name of the state of Oregon and *636 executed by tbe commission, and on all sucb contracts a satisfactory bond shall be required of the contractor of not less than fifty (50) per cent of the total amount of his bid, for the faithful performance of his contract.” Section 6718, Or. L., as amended by Chapter 24, Laws of 1923, provides that, “Every contract made with the state, * * shall contain a condition that the contractor shall promptly, as due,, make payment to all persons supplying to such contractor labor or material for the prosecution of the work provided for in such contract, and that said contractor shall not permit any lien or claim to be filed or prosecuted against the state * * on account of any labor or material furnished and a penal bond, with good and sufficient sureties, shall be required of each and every such contractor to secure the faithful performance of all the usual or particular obligations of such contract, especially the conditions herein mentioned, * * ” Section 2291, Or. L., provides that any person or persons entering into a formal contract with the state, “shall be required before commencing such work, to execute the usual penal bond with good and sufficient sureties, with the additional obligations that such contractor or contractors shall promptly make payments to all persons supplying him or them labor or materials for any prosecution of the work provided for in such contracts; * * ”

The purpose of these statutes was to provide security for the payment of all persons who provide labor or material on public work, and this was done by giving a claim under the bond in lieu of the lien, to which the laborer or materialman would be entitled under the mechanic’s lien law had the property been privately owned: Illinois Surety Co. v. John Davis Co., 244 U. S. 376 (61 L. Ed. 1206, 37 Sup. Ct. Rep. 614).

*637 Under the mechanic’s lien law (Section 10191, Or. L.) every person performing labor upon or furnishing material “to be used” in the construction of a building is given the right to a lien. While under the statutes in question every person furnishing labor or material “for the prosecution of the work” is given the right to recover under the bond. The difference in the phraseology used to define the labor or material for which a lien is given and that for which an action under the bond is given is not significant for in the first instance it is the labor or material “to be used” in or upon the building, and in the latter it is the labor or material to be used “for the prosecution of the work.” Under either statute, the labor or material must be not only furnished but used; in the one case in the construction, alteration or repair of a building; in the other in the prosecution of the work provided for under the contract. This conclusion is sustained by the former holdings of this court.

It is settled law in this state that a lien against a building is not given for material furnished a contractor but not used in or upon the building: Fitch v. Howitt, 32 Or. 396 (52 Pac. 192). In Portland v. New England Casualty Co., 96 Or. 48 (189 Pac. 211), an action to recover upon a bond given to the City of Portland by a contractor on public work, this court citing Fitch v. Howitt, supra, said: “In the foreclosure of a materialman’s lien it has been held that the materialman should not be required to watch the progress of a structure and to see that every piece of material supplied by him was used therein, and that if some of the material has been used elsewhere, it rests with the defendant to show that fact. We think that a similar course of reasoning may well be *638 applied in a case like the one at bar.” The effect of that decision is that there is no liability under the bond for material not used by the contractor in the performance of his contract. Again, in Portland v. O’Neill, 98 Or. 162 (192 Pac. 909), an action on a bond given by a contractor on public work, this court said: “The statute should not be interpreted so as to permit a contractor on public work to lease an equipment and use it for a short time or not at all, abandon the work without returning the rented apparatus to the lessor, and allow the rental to accumulate for a long time and be counted as an expense protected by the statute and bond. Such is not the letter or spirit of the law. If the complaint in this case is upheld a claim like the one suggested could be made.” In the case of Oregon v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Copeland Sand & Gravel Inc. v. Insurance Co. of North America
596 P.2d 623 (Court of Appeals of Oregon, 1979)
Chief Industries, Inc. v. Schwendiman
587 P.2d 823 (Idaho Supreme Court, 1978)
Dannemiller v. Amfac Distribution Corp.
566 P.2d 645 (Alaska Supreme Court, 1977)
University of Alaska v. Simpson Building Supply Company
530 P.2d 1317 (Alaska Supreme Court, 1975)
State Ex Rel. Jones v. Feak
18 P.2d 203 (Oregon Supreme Court, 1932)
State Ex Rel. Pegan v. American Surety Co.
2 P.2d 1116 (Oregon Supreme Court, 1931)
United States Fidelity & Guaranty Co. v. Benson Hardware Co.
132 So. 622 (Supreme Court of Alabama, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
253 P. 520, 120 Or. 633, 1927 Ore. LEXIS 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-trojan-powder-co-v-johnson-contract-co-or-1927.