State Ex Rel. Jones v. Feak

18 P.2d 203, 141 Or. 481, 1933 Ore. LEXIS 196
CourtOregon Supreme Court
DecidedDecember 14, 1932
StatusPublished
Cited by4 cases

This text of 18 P.2d 203 (State Ex Rel. Jones v. Feak) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Jones v. Feak, 18 P.2d 203, 141 Or. 481, 1933 Ore. LEXIS 196 (Or. 1932).

Opinion

*483 BEAN, J.

The decision in this case depends on the construction to be placed upon the following provisions of the bond:

“Now, therefore, if the principal herein shall faithfully and truly observe and comply with the terms, conditions and provisions of the said contract, in all respects, and shall well and triily and fully do and perform all matters and things by him undertaken to be performed under said contract, upon the terms proposed therein, and within the time prescribed therein, or as extended as provided in the general provisions; * * * and shall promptly pay all laborers, mechanics, subcontractors and materialmen, and all persons who shall , supply such laborers, mechanics or subcontractors with material, supplies or provisions for carrying on such work, and all just debts, dues and demands incurred in the performance of such work; * * * and shall in all respects faithfully perform said contract according to law, then this obligation is to be void, otherwise to remain in full force and effect.”

The sections of the code under which the bond was given, in so far as their provisions are applicable to the controversy herein, read as follows:

Section 49-701. “Every contract made with the state, * * * shall contain a condition that the contractor shall promptly, as due, make payment to all persons supplying to such contractor labor or material for the prosecution of the work provided for in such contract * * * and a penal bond, with good and sufficient sureties, shall be required of each and every such contractor to secure the faithful performance of' all the usual or particular obligations of such contract, especially the conditions herein mentioned # * #

Section 67-1101. “Hereafter any person * * * entering into a formal contract with the state of Oregon * * * for the construction of any building, or the prosecution and completion of any work, or for *484 repairs upon any building or work, shall be required before commencing such work to execute the usual penal bond with good and sufficient sureties, with the additional obligations that such contractor or contractors shall promptly make payments to all persons supplying him or them labor or materials for any prosecution of the work provided for an [in] such contracts. * * *”

The assignments of error present one clear-cut question: Does such unloading, dismantling and hauling of the steam shovel for 90 miles and reassembling of the contractor’s equipment at a cost of $799.30 constitute “labor * * * for any prosecution of the work provided for in such contract?”

The appellant requested appropriate findings, according to its theory of the case, and assigns error of the court in making findings aixd rendering judgment in favor of the plaintiff and in failing to find as requested by appellant.

The appellant contends, in effect, that the dismantling, unloading, hauling and assembling of the steam shovel was not labor for the prosecution of the work, for the principal reason that, under the mechanic’s lien statute, the hauling and transportation of the contractors’ tools and appliances to and from the job is not “performing labor upon or furnishing material or transporting or hauling any material of any kind to be used in the construction, alteration or repair of any building,” and therefore is not within the statute. Citing Allen v. Elwert, 29 Or. 428 (44 P. 823, 824); Stewart v. Spalding, 71 Or. 310 (141 P. 1127).

We start with this condition: the contractor had at the end of the railroad at Condon, Oregon, this large steam shovel, which was necessary for him in order to *485 carry on the construction work on the highway in accordance with his contract, and, in order to be available, the shovel must of necessity be moved from the cars at Condon to the highway at Kimberly, a distance of 90 miles. If the shovel had not been so transported by the relator or some one for the contractor it would have been practically impossible for the contractor to prosecute the work provided for in his contract, and we think such labor was within the protection of the statute.

Neither the bond in question nor sections 49-701 and 67-1101 are governed by exactly the same rules of construction as the mechanic’s lien statute.

In State ex rel. Trojan Powder Co. v. Johnson Contract Co., 120 Or. 633 (253 P. 520), cited by appellant, there were involved 30 cases of powder worth $244 which were furnished to the subcontractor under a contract, but which were diverted by the subcontractor and not used for the prosecution of the work under the contract. The decision in that case is absolutely correct. State ex rel. Hagquist v. United States Fidelity & Guaranty Co., 125 Or. 13 (265 P. 775), also cited by appellant, was an action on a contractor’s bond given to secure the performance of a highway contract, in which it was claimed that the surety for the contractor was liable to the relator on account of sums of money loaned to the contractor, and it was held that the loan of the money was not protected by the bond. The two cases mentioned are not analogous to the case at bar.

The language of the public improvement bonding act is that the contractor. shall promptly make pay *486 ments to all persons supplying him! labor or material for any prosecution of the work provided for in the contract. Under such bond and statute this court has held that one furnishing rental of equipment, meats and groceries to feed contractors’ laborers, feed for horses, for mules used in the work, incidental repairs to equipment, gas, oil and lubricating outfits and drawing of plans, for the prosecution of the work provided in a public contract, was protected by the bond: Portland v. O’Neill, 98 Or. 162 (192 P. 909); Multnomah County v. United States Fidelity & Guaranty Co., 87 Or. 198 (170 P. 525, L. R. A. 1918C, 685); 44 A. L. R. 383; Columbia County v. Consolidated Contract Co., 83 Or. 251 (163 P. 438); Brogan v. National Surety Co., 246 U. S. 257 (38 S. Ct. 250, 62 L. Ed. 703, L. R. A. 1918D, 776); 65 A. L. R. 260; City Trust, Safe Deposits Surety Co. v. United States, 147 Fed. 155; United States v. Port Deposit Quarry Co., 272 Fed. 698; United States v. Lowrance, 252 Fed. 122; Title, Guaranty & Trust Co. v. Crane Co., 219 U. S. 24 (31 S. Ct. 140, 55 L. Ed. 72); United States v. Columbus Circle Const. Corp., 284 Fed. 155; State v. Southern Surety Co., 221 Ala. 113 (127 So. 805, 70 A. L. R. 296).

Under the public improvement bonding act it is not necessary that the labor or material become incorporated into the improvement. It is sufficient if it was furnished for “any prosecution of the work.”

In Multnomah County v. United States Fidelity S Guaranty Co., supra, we find the following:.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
18 P.2d 203, 141 Or. 481, 1933 Ore. LEXIS 196, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-jones-v-feak-or-1932.