Middle-West Concrete Forming & Equipment Co. v. General Insurance Co. of America

267 S.E.2d 742, 165 W. Va. 280, 1980 W. Va. LEXIS 527
CourtWest Virginia Supreme Court
DecidedJuly 10, 1980
Docket14027
StatusPublished
Cited by17 cases

This text of 267 S.E.2d 742 (Middle-West Concrete Forming & Equipment Co. v. General Insurance Co. of America) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Middle-West Concrete Forming & Equipment Co. v. General Insurance Co. of America, 267 S.E.2d 742, 165 W. Va. 280, 1980 W. Va. LEXIS 527 (W. Va. 1980).

Opinion

McGraw, Justice:

Middle-West Concrete Forming and Equipment Company appeals from an order of the Circuit Court of Cabell County which set aside a jury verdict in its favor and awarded a new trial to appellee, General Insurance Company of America. Appellant contends that the trial *281 court erred in not considering the evidence in the light most favorable to appellant and asks us to reverse the order of the lower court and reinstate the jury verdict. We agree and reverse the lower court’s ruling.

Appellant is a small construction company located in Cincinnati, Ohio, and engaged in the business of renting materials and equipment used in the fabrication of poured concrete structures. In 1971, appellant leased to Oakridge Construction Company (hereinafter Oakridge), a general contractor with headquarters in California, certain equipment to be used in the construction of a Holiday Inn hotel in Huntington. Under the terms of the leasing agreement, Oakridge agreed to pay monthly rental on the equipment and to be responsible for returning it to the point of shipment upon completion of the work. Appellee was engaged by the owner of the project, Continental Realty, as a surety company and executed a labor and material payment bond on Oak-ridge, guaranteeing payment “for all labor and material used or reasonably required for use in the performance of the Contract.”

On June 6, 1973, Oakridge ceased work on the project prior to its completion. Oakridge did not notify appellant of the work stoppage, nor did it return the materials as required under the terms of the agreement. No further work was done on the structure until November, 1974, when the owner engaged another contractor, the Schur-man Construction Company (hereinafter Schurman) to complete the hotel. Much of appellants’ material remained on the job site until January or February of 1975, at which time appellant shipped the equipment from the job site at its own expense. Appellant maintains that some of the forms were still in use on the construction project at the time of trial in July 1976. Under Oakridge’s labor and materials payment bond, appellee paid all rentals due appellant up to July 1, 1973, but refused to pay any sums claimed by appellant after that date. Appellant instituted this action in the Circuit Court of Cabell County to recover unpaid rental on the equipment and interest on the accrued installments.

*282 At trial, appellee contended that the labor and materials payment bond covering Oakridge was in effect only during the time Oakridge was actively involved in construction and that it was not obligated to pay rental accruing after the contractor walked off the job. Appel-lee also maintained that appellant was under a duty to mitigate its damages by removing its equipment from the job site once it learned of the work stoppage. Appellant introduced evidence showing that the building in its unfinished state was structurally unsound and prone to collapse upon removal of the equipment. Appellant also introduced evidence to show that appellee’s own engineers had forbidden removal of the rented forms. Appel-lee countered this showing by introducing evidence that, with minor exceptions, the equipment could have been removed within a month after the concrete structures had been poured without endangering the soundness of the building.

The jury returned a verdict in favor of appellant in the amount of $50,000. Upon motion of appellee, the trial court concluded that the verdict was contrary to the law and ordered a new trial. Appellant contends that the trial court did not consider the evidence in the light most favorable to appellant but rather re-evaluated the evidence and ordered the verdict set aside upon reaching a conclusion different from that of the jury. Appellant also contends that the verdict was not contrary to the law and asks us to reverse the order of the trial court and reinstate the verdict. We grant appellant relief.

Appellant’s first contention is that trial court should not have set aside the jury’s verdict based on the jury’s failure to follow the Defendant’s Instruction No. 9 1 since *283 that instruction incorrectly states the law. The instruction informed the jury that appellant’s claim depended upon the use of the materials in the prosecution of the construction under the terms of the payment bond without regard to the terms of the rental contract between the parties. We find no merit in appellant’s contention.

Our review of the applicable case law in this area reveals that the purpose of the labor and materials payment bond is to protect the owner of the structure from liens levied against the building by creditors of the contractor who supplied labor and materials actually used by the contractor in furtherance of the contracted construction. Standard Accident Ins. Co. v. Rose, 314 Ky. 233, 234 S.W.2d 728 (1950); Portland v. O’Neill, 98 Or. 162, 192 P. 909 (1920). 2 It is the labor and material supplied for the prosecution of the work which is protected by the bond and not obligations incurred by the contractor which do not approximate the construction contracted to be done. Fitzgerald v. Neal, 231 P. 645 (Or. 1924). Cf., Chief Industries, Inc. v. Schwendiman, 587 P.2d 823 (Or. *284 1978). The surety is not liable for damages resulting from the breach of the rental agreement by the contractor which are not covered by the payment bond. The remedy of the supplier of labor or materials for such damages is a breach of contract action. Olive v. U.S., 297 F.2d 70 (5th Cir. 1961); Lucas v. Western Cas. & Sur. Co., 176 F.2d 506 (10th Cir. 1949); Firestedt Co. v. U.S. Fireproofing Co., 125 F.2d 1010 (10th Cir. 1942); American Surety Co. v. Wheeling Structural Steel Co., 114 F.2d 237 (4th Cir. 1940). The trial court correctly instructed the jury that appellee’s liability in this case was limited to the time the materials were actually used in furtherance of the construction without regard to the rental agreement between appellant and Oakridge. 3

The trial court determined, however, that the jury verdict was contrary to the law as stated in Defendant’s Instruction No. 9 and concluded that the jury disregarded that instruction in reaching its verdict. The trial court’s reasoning, as stated in its memorandum opinion, which was incorporated by reference in the final order, 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

William D. Goodwin v. First National Bank
West Virginia Supreme Court, 2013
Gateway Communications, Inc. v. John R. Hess, Inc.
541 S.E.2d 595 (West Virginia Supreme Court, 2001)
Rusty's Welding Service, Inc. v. Gibson
510 S.E.2d 255 (Court of Appeals of Virginia, 1999)
Bressler v. Mull's Grocery Mart
461 S.E.2d 124 (West Virginia Supreme Court, 1995)
Ribeira & Lourenco v. Jackson Health Care Asso.
603 A.2d 976 (New Jersey Superior Court App Division, 1992)
In re Eplin
411 S.E.2d 862 (West Virginia Supreme Court, 1991)
Birdsell v. Monongahela Power Co.
382 S.E.2d 60 (West Virginia Supreme Court, 1989)
Berry v. Nationwide Mutual Fire Insurance
381 S.E.2d 367 (West Virginia Supreme Court, 1989)
Martin v. Charleston Area Medical Ctr.
382 S.E.2d 502 (West Virginia Supreme Court, 1989)
State v. Masters
373 S.E.2d 173 (West Virginia Supreme Court, 1988)
Jones v. Trustees of Bethany College
351 S.E.2d 183 (West Virginia Supreme Court, 1986)
Papenhaus v. Combs
292 S.E.2d 621 (West Virginia Supreme Court, 1982)
State v. Wimer
284 S.E.2d 890 (West Virginia Supreme Court, 1981)
Elsey Ford Sales, Inc. v. Soloman
280 S.E.2d 718 (West Virginia Supreme Court, 1981)
Dukane Corp. v. Sides Construction Co.
302 N.W.2d 721 (Nebraska Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
267 S.E.2d 742, 165 W. Va. 280, 1980 W. Va. LEXIS 527, Counsel Stack Legal Research, https://law.counselstack.com/opinion/middle-west-concrete-forming-equipment-co-v-general-insurance-co-of-wva-1980.