The Kanawha-Gauley Coal & Coke Company v. Pittston Minerals Group, Inc.

501 F. App'x 247
Court of Appeals for the Fourth Circuit·Decided December 20, 2012·No. 11-1835, 12-1037·Unpublished·Cited by 8 cases

Opinion

Affirmed by unpublished PER CURIAM opinion.

Unpublished opinions are not binding precedent in this circuit.

PER CURIAM:

Kanawha-Gauley Coal & Coke Company (“KG”) and Pittston Minerals Group (“Pitt-ston”) bring this cross-appeal, challenging the judgment of the district court following a bench trial. We have reviewed the record. For the reasons below, we find no reversible error and affirm the judgment of the district court.

I.

A.

In January 1998, KG entered into a lease with Kanawha Development Corporation (“KDC”), a subsidiary of Pittston at the time. KG agreed to lease several thousand acres of its land in Fayette County, West Virginia, to KDC for mining purposes in exchange for receiving whee-lage on coal transported across the premises and royalties on the coal mined from the premises. KDC also agreed to additional obligations under the lease, which included paying property taxes and taxes on the coal. In an agreement 1 attached to the lease, Pittston agreed to serve as a *250 surety to KDC. 2

Pittston sold its interest in KDC to Appalachian Coal Holdings (“ACH”) in November 2003. Despite Pittston’s attempts to end its surety relationship, KG declined to modify the agreement. Both the lease and the agreement, therefore, remained in effect after ACH’s acquisition of KDC. After several years passed, the relationship between KG and KDC declined. KDC ceased mining on the property in mid-April 2008. By September of that year, KDC had failed to pay property taxes, as required by the lease, and soon thereafter KDC began failing to pay royalties on the coal it mined and sold.

In early March 2009, KG and KDC negotiated a payment plan to bring KDC’s obligations current. Although ACH contributed several hundred thousand dollars on KDC’s behalf, KDC ultimately failed to make its payments under the new plan. On May 22, 2009, KG sent notice of KDC’s default to KDC and Pittston, 3 and Pittston received notice five days later. Both companies were given twenty days to cure the default, but they did nothing. 4 Having received no communication or payment from Pittston by June 19, 2009, KG gave notice to both KDC and Pittston that it was terminating the lease.

B.

KG filed suit against Pittston on September 25, 2009, seeking unpaid royalties, property taxes, and fines. KG also requested legal costs and attorney’s fees. The district court denied the parties’ cross-motions for summary judgment; however, the district court found KG, as a matter of law, “did not have a duty to enforce its lien against KDC before proceeding against Pittston, who unconditionally guaranteed KDC’s performance under the lease.” The case then proceeded to trial.

Following a bench trial, the district court found that KDC had breached the lease and that Pittston did not prove its affirmative defense that KG breached its implied duty of good faith by failing to provide Pittston with timely notice of KDC’s breaches under the lease. The district court also found that KG took reasonable steps to mitigate its damages and that reasonableness did not require KG to initiate litigation to enforce a landlord’s lien against KDC before proceeding against Pittston.

The district court ultimately awarded KG $1,047,194.42 in unpaid royalties, $134,080.32 in unpaid interest on late unpaid royalties, $15,500 in late payment penalties, and $212,889.89 in unpaid taxes. It also ruled that KG was not entitled to attorney’s fees because the suretyship agreement did not unambiguously provide for the recovery of such fees. The district court, therefore, entered judgment in favor of KG against Pittston for a total of $1,409,664.63. Subsequently, KG moved to alter or amend the judgment, contending that it was also entitled to post-judgment interest at the rate of 5.25% per annum for unpaid royalties. The district court, however, denied its request, and this cross-appeal followed.

II.

Pittston first contends that the district court erred in ruling at the summary *251 judgment stage that KG had no duty under West Virginia surety law to enforce a landlord’s lien on coal and equipment owned by KDC. 5 Pittston asserts that, by failing to enforce the lien, KG impaired the collateral securing the debt KDC owed to KG. Because the collateral exceeded the debt, Pittston argues it cannot be held liable as a surety. We review de novo the district court’s interpretation of West Virginia state law at the summary judgment stage. See Delebreau v. Bayview Loan Servicing, LLC, 680 F.3d 412, 415 (4th Cir.2012).

Free access — add to your briefcase to read the full text and ask questions with AI

The Kanawha-Gauley Coal & Coke Company v. Pittston Minerals Group, Inc., 501 F. App'x 247 (4th Cir. 2012).

501 F. App'x 247 (The Kanawha-Gauley Coal & Coke Company v. Pittston Minerals Group, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Vir2us, Inc. v. Sophos Inc.
E.D. Virginia, 2021
Vicki Linneman v. Vita-Mix Corp.
970 F.3d 621 (Sixth Circuit, 2020)
Bayer Cropscience Ag v. Dow Agrosciences LLC
680 F. App'x 985 (Federal Circuit, 2017)
Tricon Energy Limited v. Vinmar International, Ltd
718 F.3d 448 (Fifth Circuit, 2013)
TIG Insurance v. Tyco International Ltd.
919 F. Supp. 2d 439 (M.D. Pennsylvania, 2013)