Arctic Lumber Co. v. Borden

211 F. 50, 127 C.C.A. 486, 4 Alaska Fed. 151, 1914 U.S. App. LEXIS 1712
CourtCourt of Appeals for the Ninth Circuit
DecidedFebruary 2, 1914
DocketNo. 2282
StatusPublished
Cited by12 cases

This text of 211 F. 50 (Arctic Lumber Co. v. Borden) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arctic Lumber Co. v. Borden, 211 F. 50, 127 C.C.A. 486, 4 Alaska Fed. 151, 1914 U.S. App. LEXIS 1712 (9th Cir. 1914).

Opinion

GILBERT, Circuit Judge

(after stating the facts as above).

The court below, upon the consideration of the conflicting testimony of witnesses heard in open court, having found two important facts against the appellant, the only question for consideration here is whether the findings or the conclusions of law are based upon a mistaken view of the law, or an obvious error in applying the evidence. The appellant contends that, in finding that the lien notice was not filed within 30 days from the completion of the building, the court took the erroneous view that, because work upon the building had ceased and the building was occupied, it was completed, although a heating plant had not been installed therein and in other respects the building had not been finished. The lease provided that the building should be equipped with steam heat and radiators, “said steam heat to be either furnished by a boiler in the building or from and through steam pipes from outside the building.” The court below found that, after the execution of the lease, McCauley and Palmer, the lessees, abandoned the plan of installing a heating plant and other features in said building, as provided in said lease, “and adopted different plans, in accordance with terms and plans set out in the written contract with Goodall.” If this were a finding reached upon a consideration of conflicting evidence, it would be conclusive here. But it is not. The court- assumed from the fact that the heating plant was not included in the contract which the lessees made with Goodall, a carpenter and builder, for the construction of the building, and from the fact that the lessees postponed the installation of the heating plant, that the agreement between the lessees [156]*156and Borden had been changed. But Borden testified that no change had ever been made in his agreement with the lessees, and it is clear from the evidence, that Goodall’s contract was limited to the construction of the building only. It did not include the plumbing nor the heating plant, and it did not include several important features of the agreement between Borden and his lessees. It included only a part of what was agreed upon in the lease. Goodall testified that he could not recall that he had ever discussed with Borden the subject of the heating plant, “only he (Borden) said that McCauley had agreed he would put in a steam heating plant at some future time,” and Goodall testified that the lessees did not intend to put in a heating plant right then; that it was a consideration to come later on. All this indicates that the installation of the heating plant was deferred for a short time. The manager of the appellant testified that, when McCauley first discussed with him the prices of lumber for the building, McCauley said he was going to build a two-story house, to be a rooming house upstairs, plastered and lighted, and wired for electric lights and telephone, “and to contain a steam heating plant with radiators and pipes.” Borden left for Juneau April 3, 1910, and did not return to Cordova until February 28, 1911. Feldman, a hardware merchant, who had an understanding with the lessees by which he was to furnish the heating plant, testified that Borden corresponded with him concerning the heating plant, and that in July he wrote Feldman a letter, “in which he complained that I did not answer his questions, and to induce me to answer his questions he said I might have something to say when the heating plant is going to be put in.” The evidence indicates that at the time when the lien notice was filed, not only had the steam heating plant not been installed, but the building was incomplete, in that upon one side it had not been covered with cedar siding, and that it had been but partially painted.

The Mechanic’s Lien Law of Alaska is adopted from the lien law of Oregon, and before its adoption the Supreme Court of Oregon had held, in Avery v. Butler, 30 Or. 287, 47 P. 706, that: “When work demanded by the terms of the original contract has been omitted, the final completion of the structure dates from the time such omissions are sup[157]*157plied by the builder at the request of the owner, although in the meantime the latter may have taken possession of the property, and that, while there is anything to do which it is the duty of the builder to perform under the terms of the contract, the work upon which he is engaged is not completed until this obligation is accomplished.”

And in Crane Co. v. Ellis, 58 Or. 299, 114 P. 475, in a case where the building contract provided that the building should be completed by December 1, 1906, and the work of construction was completed in February, 1907, except for the laying of a cement floor in the basement which, on account of the dampness of the ground was not put in until August, 1907, the date of the laying of the cement floor was taken by the court as the date of the completion of the building.

But the appellee contends that, if the building was not completed when the lien notice was filed, the notice was ineffective and void for the reason that it was filed prematurely and not within 30 days after the completion of the building, and cites decisions of courts which so hold. We are not disposed to follow those decisions, based as they are upon a narrow and technical construction of the lien law. There is no prejudice to any substantial right of the owner of the building in the filing of a lien at any time after the material is furnished, and before the completion of the building. In Wills v. Zanello, 59 Or. 291, 117 P. 291, it was held that this may be done, and that a lien filed before the completion of the building is not filed prematurely. The same was held by the Supreme Court of Nevada in Self & Sellman Mill & Bldg. Co. v. Savage, 123 P. 333. The Supreme Court of Oregon has repeatedly ruled that the Mechanic’s Lien Law should be liberally construed, and this court, in Russell v. Hayner, 130 F. 90, 64 C.C.A. 424, expressly affirmed that doctrine in construing the Mechanic’s Lien Law of Alaska. In Hooven, Owens & Rentschler Co. v. John Featherstone Sons, 111 F. 81, 49 C.C.A. 229, Judge Sanborn said: “Labor and material once bestowed lose all"their value to the laborer or materialman. He cannot take them back. They enhance the value of the property upon which they are placed, and its owner and those who take under him receive all the benefits of the labor and of [158]*158the material. In such circumstances the lien of the laborer or materialman should be maintained to the full extent to which the statutes give it.”

We hold that the lien notice in the case at bar was filed in due time.

Assuming, as found by the court below, that within three days from the commencement of the building Borden posted a notice in a conspicuous place thereon that he would not be responsible for any material or work furnished in the construction thereof, the question remains whether he thereby defeated the appellant’s claim of lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilger Enterprises, Inc. v. Broadway Vista Partners
2005 NMCA 088 (New Mexico Court of Appeals, 2005)
Brand v. First Federal Savings & Loan Ass'n of Fairbanks
478 P.2d 829 (Alaska Supreme Court, 1970)
American Islam Society, Inc. v. Bob Ulrich Decorating Inc.
132 N.E.2d 620 (Indiana Court of Appeals, 1956)
Skidmore v. Eby
1953 NMSC 098 (New Mexico Supreme Court, 1953)
Merithew v. Bennett
20 N.W.2d 860 (Michigan Supreme Court, 1945)
Arkansas Natural Gas Corporation v. Pierson
84 F.2d 468 (Eighth Circuit, 1936)
Stowers v. Wheat
78 F.2d 25 (Fifth Circuit, 1935)
Mancourt v. Wissel
146 N.E. 911 (Indiana Court of Appeals, 1925)
Wilson v. Gevurtz
163 P. 86 (Oregon Supreme Court, 1917)
Verdi Lumber Co. v. Bartlett
161 P. 933 (Nevada Supreme Court, 1916)
Lewers & Cooke, Ltd. v. Wong Wong
22 Haw. 765 (Hawaii Supreme Court, 1915)
Oregon Lumber & Fuel Co. v. Nolan
143 P. 935 (Oregon Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
211 F. 50, 127 C.C.A. 486, 4 Alaska Fed. 151, 1914 U.S. App. LEXIS 1712, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arctic-lumber-co-v-borden-ca9-1914.