Avery v. Butler

47 P. 706, 30 Or. 287, 1897 Ore. LEXIS 135
Oregon Supreme Court·Decided January 18, 1897·Published·Cited by 12 cases

Opinion

[288] Opinion by

Mr. Chief Justice Moore.

This is a suit to foreclose a mechanics’ lien upon a house and lot at Piedmont, Multnomah County, the property of the defendant the Investment Company, a corporation, but which it had agreed to sell and convey to the defendant Ben C. Irwin. The material facts are that on August 8, 1892, the Investment Company entered into a contract with the defendants Butler & Dill, by which the latter agreed to furnish the material and erect a house on said lot in consideration of $2,312, $1,500 to be paid as the work progressed, $406 when the house was entirely completed and accepted, and $406 thirty-five days after such final acceptance and surrender of the building to the owner. The contract, in referring to the manner and effect of such payments, contained the following stipulation: “It is also provided that in each of said cases a certificate be obtained and signed by the said F. Manson White, architect, none of which payments, except the final one, shall be considered as or understood to be an acceptance of any part or portion of the works herein agreed for.” On November 28, 1892, Butler & Dill, claiming to have complied with the terms of the contract, quit working on the building, and on the 8th of the next month the architect, deeming it completed in accordance with the terms of the agreement, executed to the contractors a certificate for $406, whereupon Irwin with his family took possession, and thereafter continued to occupy the house. The architect, in preparing the plans and specifications, omitted the window blinds, and, at his own expense, agreed to procure them, and, having done so, Butler & Dill, on December 13, returned and hung them, completing the work on the 19th of that month. The finishing lumber used in the building having begun to shrink, the architect, on December 18, wrote to the [289] contractors as follows: “I hereby notify you that I have rejected much of the mill work on the residence you are building at Piedmont for the Investment Company. All the doors, with one exception, are cracked and checked. The windows do not fit, and the trim has opened at all joinings. The work must be rectified at once, or it will be done at your expense.” Thereafter he gave them a list of the imperfect material which he rejected, and notified them that the work must be made good before he could accept it, and on January 16, 1893, sent them the following notice: “You are hereby notified to proceed and complete the work on the residence you are building for the Investment Company at Piedmont. If this notice is not complied with within three days, we will, as agreed in contract, have the work done ourselves, and have the same charged to you.” Butler & Dill, upon the receipt of these notices, thereafter removed the defective and supplied other and better material, completing the repairs on April 30, 1893. The plaintiffs allege that they furnished to Butler & Dill certain material to be used in the construction of said house, and, having perfected a lien thereon, commenced this suit for its foreclosure, alleging in their complaint that the defendant, the Builders’ Sash & Door Manufacturing Company, a corporation, claimed some lien upon the premises, to which said company made answer in the nature of a cross-bill, alleging that it furnished to the contractors certain material to be used in the erection of the house, and to secure the payment of the amount due therefor, on May 26, 1893, and within thirty days from the completion of the building, filed its claim of lien in the proper office, and prayed that the same might be foreclosed. The Investment Company and Irwin, after denying the material allegations of the cross-bill, for further answer thereto, allege that the material so furnished by the Builders’ Sash & Door Manufacturing [290] Company did not comply with the plans and specifications; that, after expending large sums in placing said material in the building, they were obliged to and did remove it therefrom, and replace it with other and suitable material; and that, having been compelled to do so, they had been damaged thereby in the sum of $500, for which they prayed a decree. A reply having put in issue the allegations of new matter contained in the answer, a trial was had, at which the court, upon stipulation, dismissed the plaintiff’s suit, and the cross-bills of some other lien claimants, and, having found that the cost of making the changes was greater than the amount claimed by the Builders’ Sash & Door Manufacturing Company, decreed a dismissal of its cross-bill also, from which it appeals.

Free access — add to your briefcase to read the full text and ask questions with AI

Avery v. Butler, 47 P. 706, 30 Or. 287, 1897 Ore. LEXIS 135 (Or. 1897).

47 P. 706 (Avery v. Butler) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bethlehem Constr., Inc. v. Portland Gen. Elec. Co.
447 P.3d 18 (Court of Appeals of Oregon, 2019)
Pro Excavating, Inc. v. Ziebart
939 P.2d 1187 (Court of Appeals of Oregon, 1997)
Farrell v. Lacey
507 P.2d 31 (Oregon Supreme Court, 1973)
Dallas Lumber & Supply Co. v. Phillips
436 P.2d 739 (Oregon Supreme Court, 1968)
Birkemeier v. Knobel
40 P.2d 694 (Oregon Supreme Court, 1934)
Stark-Davis Co. v. Wilson
248 P. 1095 (Oregon Supreme Court, 1926)
Holmes v. S. H. Kress & Co.
1924 OK 25 (Supreme Court of Oklahoma, 1924)
Fox & Co. v. Roman Catholic Bishop
215 P. 178 (Oregon Supreme Court, 1923)
Craig v. Crystal Realty Co.
173 P. 322 (Oregon Supreme Court, 1918)
Pierce Arrow Co. v. Irwin
169 P. 129 (Oregon Supreme Court, 1917)
Arctic Lumber Co. v. Borden
211 F. 50 (Ninth Circuit, 1914)
Hobkirk v. Portland Baseball Club
76 P. 776 (Oregon Supreme Court, 1904)