Pro Excavating, Inc. v. Ziebart

939 P.2d 1187, 148 Or. App. 436, 1997 Ore. App. LEXIS 766
CourtCourt of Appeals of Oregon
DecidedJune 11, 1997
Docket95C-11868; CA A92784
StatusPublished
Cited by2 cases

This text of 939 P.2d 1187 (Pro Excavating, Inc. v. Ziebart) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pro Excavating, Inc. v. Ziebart, 939 P.2d 1187, 148 Or. App. 436, 1997 Ore. App. LEXIS 766 (Or. Ct. App. 1997).

Opinion

*438 ARMSTRONG, J.

Plaintiff appeals a summary judgment for defendants in an action to foreclose a construction lien. We reverse and remand.

Plaintiff is a licensed excavating contractor that contracted with a developer to install street, storm drain, sanitary sewer and domestic water improvements for a new subdivision. The site preparation contract between plaintiff and the developer provided:

“The term ‘Engineer’ wherever used in this contract shall be Multi/Tech Engineering Services, Inc., or [its] duly authorized representative. * * * The Engineer shall have full authority to interpret the plans and specifications and Rep shall determine the amount, quality, and acceptance of the work and supplies to be paid for under this contract and every question relative to the fulfillment of the terms and provisions therein.”

On January 26,1995, plaintiff completed the paving for the subdivision and removed its equipment. In February, plaintiff asked the project engineer to approve its billings for payment. On February 14, Grenz, acting for the engineer, responded by letter in which he detailed objections to plaintiff s payment demand, including that

“[a]s of [February 14, plaintiff] has not completed all of the work covered within [its] contract for this project. There are several items remaining that must be completed prior to the City of Salem making an inspection to determine the work items that are unacceptable or incomplete. Until these items are completed, the final inspection completed by the City of Salem and a letter denoting the acceptance of the work completed to date received from the City of Salem, Ziebart Development cannot get a single building permit, which makes the work, completed to that point, worthless.”

On March 21, plaintiff erected street signs and barricades, which were the items that, according to the letter, plaintiff had to complete. The cost of that work was approximately $2,500. The cost of the entire contract exceeded $400,000. In May, Grenz approved plaintiffs billings. When payment did not follow, plaintiff recorded a lien on May 18 *439 and filed this action to foreclose its lien in June. Defendants responded that plaintiffs lien claim was untimely because plaintiff had “substantially completed” its work on January 26 and had not filed its lien within 75 days of that date, as required by ORS 87.035(1).

Under ORS 87.035(1), a person must perfect a construction lien no later than 75 days “after the person has ceased to provide labor, [to] rent equipment or [to] furnish materials.” For purposes of that provision, the date on which the 75-day period begins to run is the date on which the person’s contribution to the project is “substantially complete.” See, e.g., Dallas Lbr. & Supply v. Phillips, 249 Or 58, 436 P2d 739 (1968); Avery v. Butler, 30 Or 287, 293, 47 P 706 (1897). At the hearing on defendants’ motion for summary judgment, plaintiff argued that there was a genuine issue of fact as to the substantial completion date. The trial court disagreed, concluding that plaintiffs work was substantially complete on January 26 and that its additional work in erecting the signs and barricades was “inconsequential” and did not extend the time to file the lien. After the trial court had issued its letter opinion on the motion, plaintiff moved for leave to file an amended pleading that raised estoppel as an issue in the case. The court denied the motion.

Plaintiff assigns error to both rulings. Summary judgment is appropriate under ORCP 47 if there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. We review the record in the light most favorable to plaintiff, the nonmoving party, to determine whether there is evidence in it that shows that there are genuine issues for trial. Carl v. Oregon Automobile Ins. Co., 141 Or App 515, 520, 918 P2d 861 (1996). Plaintiff argues that the evidence shows that there was a material issue of fact as to the substantial completion date of its work. Defendants argue that their evidence established that the completion date was January 26, and that plaintiff did not rebut that evidence.

Relying on the contractual provision quoted above, defendants argue that the contract gave the project engineer the “exclusive authority” to resolve all questions related to *440 fulfillment of the contract. They contend that the determination of the substantial completion date involves the resolution of such a question, and, therefore, that Grenz, acting for the engineer, had the exclusive authority to determine that date. At summary judgment, defendants offered the affidavit of Grenz in which he stated that “[t]he construction was substantially completed on January 26,1995.” Therefore, defendants argue, there is no triable issue with respect to that date.

Defendants are operating from a false premise, because the contract gives the “Rep,” whoever that is, the authority to determine all “question [s] relative to the fulfillment of the terms and provisions” of the contract. 1 It does not give that authority to the engineer.

Moreover, even if the contract gave the engineer the authority that defendants claim it does, the evidence from the engineer is self-contradictory. Defendants rely on Grenz’s affidavit in which he states that plaintiff substantially completed its work on January 26. However, in his February 14 letter, Grenz stated that plaintiffs failure to complete all the work covered by the contract rendered plaintiffs work “worthless.” Far from resolving the date of “substantial completion,” Grenz’s statements create an issue of fact.

Defendants argue, however, that plaintiffs work erecting signs and barricades was “inconsequential” to the project and, therefore, did not extend the time in which to file a lien. The trial court accepted that argument:

“[I]t is this Court’s opinion that substantial completion was done on 26 January 1995 and that the placing of the barricades and the signs was inconsequential and did not extend the time. [The] costs for the signs and the barricade were less than $2,500.00 and could not be considered anything but insignificant in light of this contract which exceeds $400,000.00.”

*441 A contractor does not extend the time to file a lien by returning to a job to perform “some trifling work or a few odds and ends” after apparently completing the job and removing its equipment. Christenson v. Behrens, 231 Or 458, 467, 372 P2d 494 (1962). However, cost alone does not determine if work is “trifling.” Christenson is instructive as to the applicable analysis.

In Christenson, the defendants had paid their general contractor for extensive alterations to a building in which they conducted a mercantile business.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bethlehem Constr., Inc. v. Portland Gen. Elec. Co.
447 P.3d 18 (Court of Appeals of Oregon, 2019)
Ken Hood Construction Co. v. Pacific Coast Construction, Inc.
120 P.3d 6 (Court of Appeals of Oregon, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
939 P.2d 1187, 148 Or. App. 436, 1997 Ore. App. LEXIS 766, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pro-excavating-inc-v-ziebart-orctapp-1997.