Bethlehem Constr., Inc. v. Portland Gen. Elec. Co.

447 P.3d 18, 298 Or. App. 348
CourtCourt of Appeals of Oregon
DecidedJune 26, 2019
DocketA164486
StatusPublished
Cited by1 cases

This text of 447 P.3d 18 (Bethlehem Constr., Inc. v. Portland Gen. Elec. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bethlehem Constr., Inc. v. Portland Gen. Elec. Co., 447 P.3d 18, 298 Or. App. 348 (Or. Ct. App. 2019).

Opinion

POWERS, J.

*350In this case involving a construction lien, Portland General Electric Company (PGE) appeals from a limited judgment in favor of Bethlehem Construction, Inc., which the trial court entered after granting summary judgment for Bethlehem on its lien foreclosure claim.1 PGE contends that the trial court erred in granting summary judgment to Bethlehem and denying it to PGE because the lien was not recorded within 75 days after Bethlehem "ceased to provide labor, rent equipment or furnish materials," as required by ORS 87.035(1). We conclude that the trial court did not err and, accordingly, affirm.

The facts are undisputed. PGE contracted with Abeinsa Abener Teyma General Partnership (Abeinsa) for construction of a power plant in Boardman, Oregon, known as the Carty Generating Station. Abeinsa subcontracted with Bethlehem by entering into a purchase order in which Bethlehem agreed to produce and deliver precast concrete panels *20to be used as part of the generation building. The contract price was $122,851. Bethlehem produced and delivered the panels, completing the work required by the purchase order in April 2015 and submitting its final billing to Abeinsa.

In December 2015, Abeinsa contacted Bethlehem by email with a request for additional work. Another contractor had drilled through a prestressed strand in one of the concrete panels, and Abeinsa requested an engineering opinion on whether the damage compromised the panel's ability to bear the necessary load. The parties agreed to a change order to the original contract; the cost for the additional work was $578.13. The next day, December 15, 2015, Bethlehem provided the engineering opinion.

PGE terminated its contract with Abeinsa on December 18, 2015. On January 11, 2016, Bethlehem recorded its lien, which covers both the original contract for the fabrication of the concrete panels and the change order for the *351engineering analysis. Abeinsa did not pay Bethlehem the final payment due under the original contract or the amount due under the change order.

In February 2016, PGE, now acting as its own general contractor, contacted Bethlehem for an engineering opinion about a design change affecting the concrete panels. PGE and Bethlehem agreed to a second change order, Bethlehem provided the engineering opinion, and PGE paid Bethlehem the amount due under the second change order.

Bethlehem filed this action, asserting, among other things, a lien foreclosure claim, and the parties filed cross motions for summary judgment on that claim. The trial court concluded that Bethlehem did not cease to provide labor or furnish materials within the meaning of ORS 87.035(1) until it performed the additional work requested by Abeinsa in December 2015, pursuant to the first change order. Accordingly, the court concluded that Bethlehem's lien, recorded in January 2016, was timely, and the court granted summary judgment for Bethlehem and denied summary judgment for PGE.

On appeal, PGE contends that the trial court erred in concluding that Bethlehem's additional work in December renewed its lien rights as to the work it undertook earlier in the year. PGE's argument is twofold: First, it contends that the December work could not revive Bethlehem's lien rights because the work under the original contract was complete in April; it asserts that the earlier work and the later work took place under separate contracts, as a matter of law. Second, PGE asserts that the December work was trivial or trifling and, consequently, under Oregon case law, was insufficient to revive the lien claim.

On appeal of a judgment disposing of cross motions for summary judgment, we review "to determine whether there are any disputed issues of material fact and whether either party was entitled to judgment as a matter of law." Hynix Semiconductor Mfg. America v. EWEB , 276 Or. App. 228, 230-31, 367 P.3d 927 (2016) (internal quotation marks omitted); see also ORCP 47 C (providing standards for summary judgment).

*352ORS 87.035(1) requires a construction lien claimant like Bethlehem to record the lien "not later than 75 days after the person has ceased to provide labor, rent equipment or furnish materials or 75 days after completion of construction, whichever is earlier." Here, as noted above, the only question is when Bethlehem ceased to provide labor or furnish materials.2 To answer that question, we consult the substantial body of case law addressing it. See Pro Excavating, Inc. v. Ziebart , 148 Or. App. 436, 439, 939 P.2d 1187 (1997) (answering the same question by reference to case law).

"For purposes of [ ORS 87.035(1) ], the date on which the 75-day period begins to run is the date on which the person's contribution to the project is 'substantially complete.' " Id. We and the Supreme Court have frequently considered the effect on construction lien rights when a contractor performs all or nearly all of the work required under a *21contract, stops work for a period of time sufficient for lien rights to lapse, and later performs some more work and files a lien for all of the work. Bethlehem points out that, in Avery v. Butler , 30 Or. 287, 293, 47 P. 706 (1897), the Supreme Court held that, "when the builder, after a substantial completion of the structure, at the request of the owner, makes additions to it which are useful or necessary to its enjoyment, the final completion dates from the time such additions are made." See also Farrell v. Lacey , 264 Or. 505, 511, 507 P.2d 31

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Khosroabadi v. North Clackamas Parks and Rec. Dist.
347 Or. App. 465 (Court of Appeals of Oregon, 2026)
Bo and Lia Holdings LLC v. 2021 Morrison LLC
501 P.3d 1109 (Court of Appeals of Oregon, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
447 P.3d 18, 298 Or. App. 348, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bethlehem-constr-inc-v-portland-gen-elec-co-orctapp-2019.