Farrell v. Lacey

507 P.2d 31, 264 Or. 505, 1973 Ore. LEXIS 483
CourtOregon Supreme Court
DecidedFebruary 23, 1973
StatusPublished
Cited by1 cases

This text of 507 P.2d 31 (Farrell v. Lacey) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farrell v. Lacey, 507 P.2d 31, 264 Or. 505, 1973 Ore. LEXIS 483 (Or. 1973).

Opinion

BRYSON, J.

Plaintiff, a plumbing contractor, brought this suit to foreclose a mechanic’s lien on property situated in Marion County and owned by defendants Lacey. Defendant Basic Builders, Inc., was the building contractor. Defendant Frank Spoor, doing business as Hi-Lo Construction Co., was the subcontractor for excavation, and plaintiff was the subcontractor for plumbing.

Defendants Lacey filed an answer to plaintiff’s complaint, admitting that they executed a construction contract with Allan Hahn, of Basic Builders, and generally denied the remaining allegations of plaintiff’s complaint.

Defendant Spoor filed an answer to plaintiff’s complaint and a separate answer and counterclaim seeking to foreclose his lien against the property for labor performed and materials furnished.

Defendant Basic Builders filed a general denial to plaintiff’s complaint and a separate answer and [508]*508counterclaim alleging completion of its contract to build a residence for defendants Lacey and seeking to foreclose two liens against the property, each of which covered unpaid subcontractors’ claims and 12 percent of the costs and materials, pursuant to its contract with defendants Lacey.

Defendants Lacey filed a reply to defendant Basic Builders’ counterclaim against them and two separate answers by way of counterclaim against Basic Builders, contending they had paid Basic Builders an amount in excess of the contract price and demanding damages for breach of warranty by reason of negligent and unworkmanlike construction on the part of Basic Builders.

Defendants Lacey also filed a reply to defendant Spoor’s counterclaim and defendant Basic Builders filed a reply to defendants Lacey’s two counterclaims.

The case was tried to the court as a suit in equity, and no contention was made against the pleadings.

The trial court’s decree ordered the liens of plaintiff Farrell and defendant Spoor foreclosed and awarded each party $500 attorney fees. The court’s decree reduced the first lien claim of Basic Builders in the amounts of $943.46 and $464, representing the satisfied claims of Farrell and Spoor, respectively, and by the further sum of $439.69, representing a payment received from the Laceys. The court also reduced Basic Builders’ first lien in the amount of $5,160, representing 12 percent of the construction costs, to $1,500. The lien was ordered foreclosed in the amount of $2,093.44, together with $500 attorney fees. On the second lien of Basic Builders the court eliminated the claim for 12 percent of the costs of construction and ordered foreclosure of the lien in the amount of $1,101.91 but made [509]*509no allowance for attorney fees. The counterclaims of the Laceys were dismissed with prejudice.

The Laceys appeal from the adverse decree and contend the court erred “in not finding the completion date of the residence to be November 17,' 1970”; “in finding that the defendants’ [sic] Laceys, were their own contractors”; and in “rewriting the contract between the defendants Basie Builders, Inc., and Laceys.”

Basic Builders, Inc., cross-appeals, contending that the trial court erred in refusing to award attorney fees on the foreclosure of Basic Builders’ second lien and in failing to award Basic Builders 12 percent of its total construction costs.

The record discloses the following facts. Defendants Lacey were the owners of a building site in Salem, Oregon, and decided to build a home thereon if they could obtain approved financing from the Oregon Department of Veterans’ Affairs. They had building plans prepared by Central Planning and Design Services of Salem, Oregon, with no specifications of materials other than minimal provisions on the face of the plans. Laceys obtained two construction bids, $48,000 and $42,000. They then met Mr. Hahn, of defendant Basic Builders. Mr. Lacey testified that Hahn told him that the house could be built for $36,000, including a finished basement. Laceys were to do the outside painting and certain other work. Defendant Basic Builders could not meet the bonding requirements of the Oregon Department of Veterans’ Affairs. To evade this requirement Laceys, at the suggestion of Plahn, wrote to the Department of Veterans’ Affairs, stating that they would be their own contractor. Laceys paid the bills incurred by Basic Builders or Laceys and disbursed the funds from the loan on vouchers provided by the Department of Veterans’ Affairs.

[510]*510On May 18, 1970, the following agreement was-executed.

“I, Allan Hahn, DBA Basic Builders, entered into and [sic] agreement to build and [sic] house according to State G. I. specifications, completion to be in 120 days from start of construction. Owner is to paint outside of the house. This agreement is to comply with cost of materials and labor plus 12% to be paid when finished according to State G. I. specifications.
Builder /s/ Allan Hahn
Owner /s/ James W. Lacey”
This is the sole agreement other than written “ADDITIONS AND CHANGES TO BE MADE ON NEW HOME, LOCATED AT THE CORNER OF ALDER-BROOK AND WINDING COURT S.E. SALEM, OREGON,” which contained 49 additional items or changes not shown on the plans, including:
“ 9. All carpet throughout the house
“21. Kitchen-Aid dishwasher Deluxe model—KDS16
“22. 30" drop in glass oven—self cleaning range— Med. Price
“29. Built in buffet or china closet in dining room
“31. Intercom system—Tranister [sic]—
“32. Electric eye and control on garage door
“38! Dressing table and mirror in Master bedroom
“49. Grade slope of the lawn to comply with the structure of the house.”

Laceys requested permission to move into the house and did so on Saturday, November 21, 1970, as they had sold the home they were living in and wanted to move “as soon as we could because of school.” Five days later, on November 26,1970, the basement flooded, [511]*511necessitating the installation of two sump pumps by plaintiff Farrell.

The Laceys contend that the lienors had substantially completed their work on November 17, 1970, “except for minor repair or rechecking work,” and therefore the liens of plaintiff Farrell and defendants Spoor and Basic Builders filed in March 1971 were filed after the statutory period provided in ORS 87.035.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bethlehem Constr., Inc. v. Portland Gen. Elec. Co.
447 P.3d 18 (Court of Appeals of Oregon, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
507 P.2d 31, 264 Or. 505, 1973 Ore. LEXIS 483, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farrell-v-lacey-or-1973.