Mathis v. Thunderbird Village, Inc.

389 P.2d 343, 236 Or. 425, 1964 Ore. LEXIS 300
CourtOregon Supreme Court
DecidedFebruary 13, 1964
StatusPublished
Cited by25 cases

This text of 389 P.2d 343 (Mathis v. Thunderbird Village, Inc.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mathis v. Thunderbird Village, Inc., 389 P.2d 343, 236 Or. 425, 1964 Ore. LEXIS 300 (Or. 1964).

Opinion

DENECKE, J.

Plaintiff builder contracted to build a supermarket for the defendant Thunderbird Village, Inc., hereinafter called owner; the defendant life insurance company is the lender. The contract price was cost-plus 10 per cent. The owner paid the plaintiff $231,-000; the plaintiff claimed an additional $42,000, filed a claim of mechanics lien therefor, and brought this suit to foreclose his lien. The trial court awarded plaintiff $41,000 and foreclosed the lien.

Defendants assert'that the complaint filed by the *428 plaintiff is fatally defective because it does not specifically allege a date of completion of the contract.

■ The Oregon Mechanics Lien statute, OES 87.035, provides:

“Every original contractor, within 60 days after the completion of his contract * * * shall file for recording * * * a claim containing a true statement of his demand * *

The plaintiff alleged in his complaint generally that he was a general contractor and that he entered into contracts with the defendant owner to construct a building and a parking lot. He further alleged:

“VI
“Pursuant to said contracts and agreements the plaintiff did, between the 30th day of June, 1960 and March 2,1961, perform labor upon and furnish material for use in, to be used in, and which was used, in the construction of said- building and parking lot above described and did in a workmanlike manner provide and perform all the labor and materials necessary for said construction and erection of said building in accordance with the drawings, specifications and plans provided therefore [sic], as corrected and changed from time to time, and that plaintiff performed all the terms and conditions of the contracts and agreements on his part to be performed, except as changed or modified by the owner during the progress of said work.
“VIII
“That plaintiff, on the 13th day of April,, 1961, and within 60 days after the completion of his contract, filed with the County Clerk of Jackson County, State of Oregon, a claim of lien * *

The defendants rely upon Anderson v. Chambliss, 199 Or 400, 262 P2d 298 (1953), in support of their *429 contention that the complaint does not state a cause of suit because it does not allege a date of completion of the contract. In that case the plaintiff alleged work was performed between September 7, 1949, and March 8, 1950, and that the lien was filed May 1, 1950. The court commented:

“* * * Nowhere in the complaint is it alleged affirmatively, either directly or indirectly, that the contract was completed, giving the date of such completion, nor is it alleged therein that the contract was not completed, and stating a valid reason for such failure to complete it.
“Under the provisions of § 67-105, OCLA [ORS 87.035], supra, in order to perfect a valid lien, it is mandatory that an original contractor file his claim within 60 days ‘after the completion of his contract’. In a complaint to foreclose such a lien, it is necessary to charge that the contract was completed and to give the date of such completion, or if, for just cause, it was not completed, the reason therefor and the date on which the last labor or materials were furnished. In other words, it must affirmatively appear from the allegations contained in the complaint itself that the lien notice was filed within the 60-day period as required by the statute. A complaint that does not contain such essential allegation (or allegations equivalent thereto) fails to state a cause of suit and is fatally defective. * * *” (Emphasis added.) (199 Or at 406)

We hold that in order to state a cause of suit it is not necessary literally to state that the contract was completed on a certain date. We hold it is sufficient to state that the contract has been completed and the claim of lien has been filed on a certain date, naming it, and within 60 days after completion of the contract.

*430 This is in accord with the decision of Birkemeier v. Knobel, 149 Or 292, 40 P2d 694 (1935). This court there stated: ■

“* * * Defendants argne that the complaint does not allege performance of the contract on the part of the plaintiff, and that if it does it fails to allege that the plaintiff filed the lien notice within 60 days of completion of performance. The amended complaint repeatedly uses the term ‘the construction of said building’, stating in one place that the house was constructed ‘in accordance with plaintiff’s contract with defendants, dated August 5, 1932, for the construction of said building’. This often employed term, in our opinion, denotes the complete erection of the dwelling house; in other words, it states, by inference' at least, that the plaintiff completed performance of his contract. The complaint also alleges: ‘Between August 1, 1932, and January 15, 1933, plaintiff herein, at the special instance - and request' of the defendants, furnished material and labor necessary to the construction of, and which was used in the construction of, said building.’ It also álleges: ‘Plaintiff herein, on March 1, 1933, and within 60 days from the completion of his furnishing material and labor in the construction of said building, filed’ the lien notice. The lien notice attached to the complaint states: ‘Said materials were furnished, and said labor was' performed between the dates of August 1, 1932, and January 15, 1933.’ These averments, in our opinion, state the facts which the defendants believe are missing. The language is ill adapted to the purpose, and certainly does not meet the standards of a skillful pleader-; but the absence of fine technique, alone is not fatal.” (149 Or at 312-313)

The defendants next assert that the suit should have been dismissed because the claim of lien was not timely filed. The plaintiff, being an “original” *431 contractor, had 60 days “after the completion of his contract” within which to file his claim of lien. His lien claim was filed April 13, 1961. The trial court’s finding that the work was completed within 60 days preceding this date is affirmed.

Defendants admit some work was performed on February 16, a date within the 60-day period. Their contention is that such work was too trivial to be considered as extending the time of completion. They rely upon Christenson v. Behrens, 231 Or 458, 372 P2d 494 (1962), and eases cited therein. Applying the principles set forth in the Christenson case, the plaintiff’s work, performed for him by a subcontractor, correctly can be considered completion of the contract. The work done by the subcontractor was a contract obligation of plaintiff; it was requested by the owner’s representative after an inspection of the building; the labor and materials for the work, insulating ducts, cost $500; and it took two men several days to complete. In addition, as we pointed out in Christenson v. Behrens,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Esquire Investments, Inc. v. Firestone
341 Or. App. 510 (Court of Appeals of Oregon, 2025)
Fostveit v. Poplin
301 P.3d 915 (Court of Appeals of Oregon, 2013)
Forsberg v. Bovis Lend Lease, Inc.
2008 UT App 146 (Court of Appeals of Utah, 2008)
A.D. Powers v. Miller
1999 NMCA 080 (New Mexico Court of Appeals, 1999)
Grant v. Wester
679 So. 2d 1301 (District Court of Appeal of Florida, 1996)
S.K. Drywall, Inc. v. Developers Financial Group, Inc.
819 P.2d 931 (Arizona Supreme Court, 1991)
UNITED STATES NAT. BANK OF OR. v. Caldwell
655 P.2d 180 (Court of Appeals of Oregon, 1982)
Webber v. Smith
632 P.2d 998 (Court of Appeals of Arizona, 1981)
Ralph Allen, Inc. v. Lumpkin
566 P.2d 872 (Oregon Supreme Court, 1977)
Pacific County v. Sherwood Pacific, Inc.
567 P.2d 642 (Court of Appeals of Washington, 1977)
Lichty v. Merzenich
563 P.2d 690 (Oregon Supreme Court, 1977)
Carr v. Hopkin
556 P.2d 221 (Wyoming Supreme Court, 1976)
Pio v. Adcco, Inc.
517 P.2d 1189 (Oregon Supreme Court, 1974)
Heinkel v. City of Corvallis
510 P.2d 579 (Court of Appeals of Oregon, 1973)
Farrell v. Lacey
507 P.2d 31 (Oregon Supreme Court, 1973)
Mail-Well Envelope Company v. Saley
497 P.2d 364 (Oregon Supreme Court, 1972)
American Motor Inns of Fla., Inc. v. Bell Electric Co.
260 So. 2d 276 (District Court of Appeal of Florida, 1972)
Wilson v. Clark
464 P.2d 683 (Oregon Supreme Court, 1970)
Farris v. McCracken
453 P.2d 932 (Oregon Supreme Court, 1969)
Robison v. Thatcher
451 P.2d 863 (Oregon Supreme Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
389 P.2d 343, 236 Or. 425, 1964 Ore. LEXIS 300, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mathis-v-thunderbird-village-inc-or-1964.