FOLEY, J.

In December 1968, plaintiff-contractor entered into a contract with the city of Corvallis for the expansion of its Douglas Taylor Water Treatment Plant. The parties agreed that the work was to be completed by June 15, 1969, but the contract provided for extension of the completion date if the work was delayed by causes beyond the contractor’s control. The contract also contained a liquidated damages provision *377 which provided that the contractor would be liable to the city for $300 per day for each day of non-completion (excluding Sundays and holidays).

On February 2, 1971, plaintiff filed a complaint against the city of Corvallis, alleging substantial completion of the contract on or before April 10, 1970, and demanding payment of the balance due under the contract. The complaint further alleged that the delays in completion were due to circumstances beyond plaintiff’s control and therefore excused under the contract.

Defendant’s answer and counterclaim contended that substantial performance did not occur until September 15, 1970, denied that plaintiff’s delays in performance were excused under the contract, and demanded liquidated damages pursuant to the contract for the period from February 17, 1970, to September 15, 1970, a total of 178 days. The amount claimed by the city by way of liquidated damages exceeded the amount claimed by the contractor to be due under the contract.

The trial court found that the delays occurring through July 9, 1970, were excused pursuant to the terms of the contract, but that the delays in completion from that time forward were occasioned by acts or omissions of the plaintiff. The court further found that substantial performance did not occur until September 15, 1970, as alleged in the city’s answer and counterclaim, and it therefore concluded that the city was entitled to liquidated damages for a period of 46 days between July 9 and September 15 as an offset to the amount due plaintiff under the contract. Both parties have appealed.

The city’s principal assignment of error is that *378 the trial court erred in finding that the delays through July 9,. 1970 were justified under the contract. Plaintiff’s principal assignment on its cross-appeal is that there is no substantial evidence to support the award of liquidated damages from that date to September 15, 1970. With regard to both of these assignments, our inquiry is limited to whether there is any evidence to support the court’s finding. If there is, the finding must be upheld. ORS 17.435.

As to the period up to July 9,1970, the main impediments to expeditious completion of the project were (1) delays in the delivery of certain butterfly valves and (2) problems with the high service pump. The situation was complicated by the fact that the high service pump could not be tested until the butterfly valves were delivered and installed. There were also a number of minor impediments, including the failure of a supplier to deliver the filter medium for the treatment plant’s filter beds and settling tube modules for the sedimentation basins. Finally, significant problems were caused by the fact that part of the plant had to be functioning throughout the construction period to fill the city’s need for water; this meant that plaintiff could not always shift his activities readily from one aspect of the project to another.

The sequence of events was as follows: (1) The crucial butterfly valve was delivered on February 17, 1970, but it had an improper component which made it dysfunctional; (2) the proper component was received on March 25,1970; (3) thereafter, the butterfly valve was installed, and the high service pump was tested on April 8, 1970, but the head pressure on the pump was found to be too high; (4) a relief valve to *379 reduce the pressure was ordered and subsequently installed on July 10, 1970; (5) the pump was retested on July 22, 1970, and was found to be performing acceptably.

The evidence presented at trial indicates that the plaintiff pursued the problem of the late butterfly valves in a resourceful fashion. However, he was hampered in his efforts by various occurrences, including a strike in the industry, a government requisition which took priority over his order, and miscarriage of mail due to unusual weather conditions. As to the problems with the high service pump, the evidence indicates that the engineers retained by the city were at least partly responsible for the delays, since they do not appear to have made their specifications completely clear to the pump manufacturer at the outset or during subsequent contacts. The evidence further indicates that plaintiff was not actively involved in discussions regarding the high service pump, but rather that that aspect of the project was handled between the pump manufacturer and the engineers retained by the city.

After reviewing the record, we are satisfied that there is evidence from which the court as the trier of fact could reasonably have found as it did that the delays up to July 9, 1970 were not the fault of plaintiff and were therefore excused under the contract.

We now turn our attention to the issue raised by plaintiff’s cross-appeal, viz., whether there is evidence in the record to support the trial court’s findings (a) that substantial performance did not occur until September 15,1970, and (b) that the delay from July 9, 1970, to September 15, 1970, was plaintiff’s fault, thereby entitling the city to liquidated damages.

*380 Plaintiff alleged in Ms complaint and contends "before tMs court that substantial performance occurred on or prior to April 10, 1970. He bases this contention on the fact that the city’s engineers concluded that the project was 98.4 per cent complete at that time. This percentage was arrived at by computing the average extent of completion of all aspects of the project, many of which were 100 per cent completed. However, the mere statement of such a percentage figure does not answer the inqrnry in tMs case, since the most essential component of the project, the Mgh service pump, had not yet been tested or approved and was therefore listed at a figure of 90 per cent completion.

The standard for determining substantial performance was stated in Mathis v. Thunderbird Village, Inc., 236 Or 425, 438-39, 389 P2d 343 (1964), as follows:

“* * * Substantial performance is accomplished although the contract is not completely performed if the omissions and deviations from the performance required by the contract are inadvertent and unintentional, do not impair the structure as a whole, can be easily remedied, and may be paid for by deductions from the contract price. Pippy v. Winslow, 62 Or 219, 222-223, 125 P 298 (1912).”

See also 13 Am Jur 2d 46-47, Building and Construction Contracts § 43, where it is stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LTR Rental Co. v. Simmons
595 P.2d 1283 (Court of Appeals of Oregon, 1979)
Layton Manufacturing Co. v. Dulien Steel, Inc.
560 P.2d 1058 (Oregon Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
510 P.2d 579, 13 Or. App. 375, 1973 Ore. App. LEXIS 1171, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heinkel-v-city-of-corvallis-orctapp-1973.