Worthen v. Cleaveland

129 Mass. 570, 1880 Mass. LEXIS 299
CourtMassachusetts Supreme Judicial Court
DecidedOctober 22, 1880
StatusPublished
Cited by13 cases

This text of 129 Mass. 570 (Worthen v. Cleaveland) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Worthen v. Cleaveland, 129 Mass. 570, 1880 Mass. LEXIS 299 (Mass. 1880).

Opinion

Soule, J.

The suit for enforcing a mechanic’s lien for labor or materials done or furnished in the erection or alteration of a building may be begun by filing a petition in court, in term, or in the clerk’s office in vacation; Gen. Sts. c. 150, § 8; or by inserting the petition in a writ to be served, returned and entered as are writs in other cases. § 9. ' When the suit is begun by petition not inserted in a writ, “ the court in which the petition is entered, or the clerk thereof in vacation, shall order notice to be given to th<? owner of the building or structure, that he may appear and answer thereto at a certain day in the same term, or at the next term, by serving him with an attested copy of the petition with the order of the court or clerk thereon, fourteen days at least before the time assigned for the hearing.” St. 1871, c. 78. This statute differs from the Gen. Sts. c. 150, § 14, for which section it was substituted, only in giving authority to the clerk to issue the orders named in it in vacation. The same provision was in the Rev. Sts. e. 117, § 7, as in the Gen. Sts. c. 150, § 14. It has been repeatedly held that those statutes did not require the order of notice to be issued during the term at which the petition was entered, nor to be returnable at that term or at the next term. The court gets jurisdiction of the petition by virtue of the entry, and has a discretion to assign a time for hearing whenever in its judgment it may be most beneficial for the parties to have the time fixed. The notices to the parties are in season if given after the assignment is made, and are in other respects in conformity to the requirements of the [573]*573statutes. Rockwood v. Walcott, 3 Allen, 458. Donnell v. The Starlight, 103 Mass. 227. The objection of the respondent to the proceedings, that the petitioner had not any rights by reason of the delay in obtaining the order of notice, was properly overruled.

The petitioner did not perform labor on the respondept’s land under any agreement with him. He did certain work in building a cellar wall in the fall of the year 1875, under a contract with Canfield, by which contract he warranted that the wall should stand. The wall was completed in November. Canfield caused the wall to be built pursuant to a contract with the respondent, which contemplated the erection of a building by Canfield on the premises before January 1, 1876, as a condition precedent to the conveyance of the premises .to Canfield; another condition being that Canfield should repay to the respondent all moneys advanced by him for the erection of the building. The time of performance was afterward extended to April 1, 1876. If the petition had been filed within the time required by statute after the petitioner ceased working in November, the relations of Canfield to the respondent under their contract were such as to enable the petitioner to maintain a lien for whatever might be due him for his labor. Hilton v. Merrill, 106 Mass. 528. Canfield at that time had authority to erect a building on the premises, and an implied consent from the respondent to the employment of the petitioner to aid in the work. This implied consent grew out of the contract, and when the time specified in the contract, as extended, had elapsed without fulfilment by Canfield of his duty under the contract, so that he no longer had the right to erect a building or to call on the respondent for advances of money for the building, or to require of him a conveyance of the land, the implied consent that Canfield should employ others to aid in erecting the building had ceased to exist. The work done by the petitioner in the month of April was in the nature of repairs, for the purpose of making good his warranty of the stability of what he did in the previous October and November, and cannot be regarded as consented to by the respondent by reason of the authority conferred on Canfield under a contract which had expired. Rockwood v. Walcott, ubi supra. There is nothing in the case of Hilton [574]*574v. Merrill, ubi supra, which conflicts with the views here expressed. In that case, the owner of the land had contracted to convey it to Potier whenever he should pay a certain price for the land, and all moneys advanced for building the house, with interest, so that, though the work for which the plaintiff sought to maintain a lien was done after the time when by the contract the house was to be completed, it was done while Potier still had the right to build and to call for a conveyance.

The learned judge who tried the case in the Superior Court erred, therefore, in refusing to rule, as requested by the respondent, that the contract of the petitioner was completed in November 1875, and that the alleged warranty of the wall would not entitle him to keep his lien alive by any subsequent labor on it. For, although the language of the prayer may be capable of another construction, it must have been understood to ask a ruling that, the petitioner having built the entire wall called for by his contract in November 1875, the alleged warranty would not entitle him to keep his lien alive by subsequent labor on it in the spring months of 1876.

The finding of the learned judge, that the petitioner filed his claim in season, is apparently a finding of fact, and it is well settled that a finding of fact by a judge in the trial of a cause without a jury cannot be reviewed by this court. Turner v. Wentworth, 119 Mass. 459. But this so-called finding of fact is the answer to a question framed for the purpose of having the reply indicate whether, in the opinion of the judge, the work done in the month of April 1876 was done under such circumstances that a lien could be maintained by virtue of it. This was the only question in dispute. There was no controversy between the parties as to the date of ceasing to work in April and that of filing the certificate. As the answer to the question depended wholly on the view of the law taken by the judge on a point on which a ruling was asked, and was adverse to the ruling asked,- the whole matter is open to the examination of this court on the bill of exceptions. Exceptions sustained.

Upon a second trial in the Superior Court, without a jury, before Gardner, J., the petitioner offered evidence tending to [575]*575show that the contract between himself and Canfield was made by the respondent personally with the petitioner, the respondent acting as the agent of Canfield; that, in April, the respondent complained to the petitioner that the cellar was falling down, and requested the petitioner to see to it; that, in March, the petitioner asked the respondent for money upon his contract for building the cellar, and the respondent answered, “As soon as you have got your job finished, we will try and get you some money;” and that the respondent knew of the work being done in April, at the time the same was done. All this evidence was controverted by the respondent.

There was also evidence that, in November, the petitioner left off work upon the cellar, and that, if the wall stood, it was completed; that, from the exposure of the cellar, the work done upon it in April could not have been properly done at an earlier date.

The respondent requested the judge to rule as follows : “ 1. Any work which the petitioner did, required in consequence of the action of the frost, is in the nature of repairs, and will not operate to keep alive his lien. 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Surety Co. v. Price
172 S.W. 1072 (Court of Appeals of Kentucky, 1915)
Huntington Plumbing & Supply Co. v. McGuffin
83 S.E. 194 (West Virginia Supreme Court, 1914)
Thurston v. Blunt
103 N.E. 478 (Massachusetts Supreme Judicial Court, 1913)
Maynard v. Royal Worcester Corset Co.
85 N.E. 877 (Massachusetts Supreme Judicial Court, 1908)
Brown v. Haddock
85 N.E. 573 (Massachusetts Supreme Judicial Court, 1908)
General Fire Extinguisher Co. v. Schwartz Bros. Commission
65 S.W. 318 (Supreme Court of Missouri, 1901)
Shaw v. Fjellman
75 N.W. 705 (Supreme Court of Minnesota, 1898)
O'Driscoll v. Bradford
50 N.E. 628 (Massachusetts Supreme Judicial Court, 1898)
Avery v. Butler
47 P. 706 (Oregon Supreme Court, 1897)
Conlee v. Clark
42 N.E. 762 (Indiana Court of Appeals, 1896)
Scheible v. Schickler
65 N.W. 920 (Supreme Court of Minnesota, 1896)
McCue v. Whitwell
30 N.E. 1134 (Massachusetts Supreme Judicial Court, 1892)
Schendel v. Stevenson
26 N.E. 689 (Massachusetts Supreme Judicial Court, 1891)

Cite This Page — Counsel Stack

Bluebook (online)
129 Mass. 570, 1880 Mass. LEXIS 299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/worthen-v-cleaveland-mass-1880.