This is a petition for a mechanic’s lien tried by a judge
[266]*266On these facts the respondent contends that no exceptions were saved. But we are of opinion that the statement made by the petitioners’ attorney on February 25 was sufficient to save an exception to all the rulings set forth in the judge’s findings of fact. To save an exception no form of words is necessary; it is enough that the judge understands that the party wishes to save an exception. Leyland v. Pingree, 134 Mass. 367, 370. Thwing v. Clifford, 136 Mass. 482. Newton v. Worcester, 169 Mass. 516. Jones v. Newton Street Railway, 186 Mass. 113, 114.
We are also of opinion that the exceptions were saved in time. Where a case is tried without a jury and the judge reserves his decision (there being no rule of court dealing with the matter), an exception must be saved within a reasonable time after the ruling of law excepted to is made. That is settled. The rule is fully explained in the recent cases of Richards v. Appley, 187 Mass. 521, Graves v. Hicks, 194 Mass. 524, and Hurley v. Boston Elevated Railway, 213 Mass. 192. In the case at bar, Saturday, February 22, being a holiday, the exceptions were saved on the second court day next after the attorney received notice of the rulings made. That was within a reasonable time. It follows that the exceptions are properly before us.
We are of opinion that the exceptions must be sustained. It was found by the judge that the petitioners were hired as subcontractors to do and furnish the plumbing and heating for a house being built for the respondent by one Smith as general contractor. Included in the petitioners’ contract was the installation of a range and boiler with connecting pipes. By their contract the petitioners were bound to “furnish the plumbing and heating for the building complete, doing first class work and leaving everything in a first class condition, ready for immediate use.” The judge found that “the petitioners substantially completed their contract in August ” 1910. But that at that time “there was a slight leak in the connecting pipes between the boiler and the range,” and that they had put the hot water disc on the cold [267]*267water faucet and vice versa. At that time although the attention of the petitioners “was called by contractor Smith to this leak in the kitchen, they did not repair the same, thinking, and so informing the contractor, that as time went on the joints would tighten and the leaks would stop.” On September 23,1910, the respondent “wrote a letter to the petitioners calling their attention to the leak and requesting that they go to his house and stop the same and also change the hot and cold discs” already referred to. “On September 28, the petitioners went to the house of the respondent Blunt and drew off the water from the fixtures and proceeded to do the necessary work, taking out the pipes, putting red lead upon the joints of the same, screwing the same tighter, and putting the said work in first class condition. The petitioners also changed the labels on the hot and cold water pipes. . . . After completing these repairs and changes the water was turned on again, the work thoroughly tested, and all this consumed a period of about two hours and one half. . . . The leak was not caused by any use which had been made of the range, the boiler or the piping, but had existed, to a greater or less extent, from the time the work was first done, owing to the fact that the joints were not sufficiently leaded and the pipes were not screwed together in a manner sufficiently tight. . . . Said lien was filed within thirty days thereafter.”
The three rulings made by the judge at the respondent’s request were wrong. By the terms of their contract with Smith the petitioners had not completed the plumbing and heating which they had to do under that contract until "everything [was] in a first class condition, ready for immediate use.” When the petitioners stopped work at the end of August, their work had not been completed. Apparently they expected “that as time went on the joints would tighten and the leaks would stop,” but they did not. Under these circumstances at any rate they had not left "everything in a first class condition, ready for immediate use.” On the facts found by the judge the work was not completed until September 28, and the statement, “being filed within thirty days thereafter,” was seasonably filed. Worthen v. Cleaveland, 129 Mass. 570. Monaghan v. Putney, 161 Mass. 338. Miller v. Wilkinson, 167 Mass. 136. McLean v. Wiley, 176 Mass. 233. Shaughnessy v. Isenberg, 213 Mass. 159. The first decision in Worthen v. Cleaveland, 129 Mass. 570, is strongly relied on by the respondent. But that decision went on the ground that on the evidence then in the case the petitioner’s right to do any work under the contract had come to an end before he did the work on which he relied to bring the filing of his statement within the thirty days. At the second trial of Worthen v. Cleaveland, reported ubi supra, there was evidence to the contrary, and a finding that the statement was seasonably filed was held to be correct. For a case like the first decision in Worthen v. Cleaveland, ubi supra, see O’Driscoll v. Bradford, 171 Mass. 231.
Exceptions sustained.
As stated in the Memoranda on page 303, Mr. Justice Morton resigned on December 15, 1913.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
103 N.E. 478, 216 Mass. 264, 1913 Mass. LEXIS 1390, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thurston-v-blunt-mass-1913.