Carter v. Commonwealth

194 N.E. 915, 290 Mass. 97, 1935 Mass. LEXIS 1068
CourtMassachusetts Supreme Judicial Court
DecidedMarch 4, 1935
StatusPublished
Cited by7 cases

This text of 194 N.E. 915 (Carter v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carter v. Commonwealth, 194 N.E. 915, 290 Mass. 97, 1935 Mass. LEXIS 1068 (Mass. 1935).

Opinion

Crosby, J.

This is a petition brought by the petitioner under the provisions of G. L. (Ter. Ed.) c. 30, § 39, to establish his claim for labor and materials furnished the [99]*99respondents Rooney and Cenedella, copartners doing business as John F. Rooney and Company (who will hereafter be referred to as Rooney and Company), on a State construction project, and to obtain the benefit of certain security, comprised of moneys retained by the Commonwealth under its contract with the respondent Rooney and Company and of the obligation of the respondent Maryland Casualty Company as surety upon the general contractor’s bond. The case was referred to a master. It is before this court on the appeals of the respondents Rooney and Company and Maryland Casualty Company from an interlocutory decree confirming the master’s report and from a final decree in favor of the intervening petitioners DiPietro and Quincy Lumber Company and others.

The master found that on February 2, 1932, a contract was executed between the respondents Rooney and Company and the Commonwealth of Massachusetts for the construction of a section of State highway. This was a public work, and a performance bond as required by G. L. (Ter. Ed.) c. 30, § 39, in the amount of $231,000 was executed by the respondent Rooney and Company as principal and the respondent Maryland Casualty Company as surety. . The Commonwealth has in its hands $53,829.72 remaining due to Rooney and Company, being, with the bond, the security required by the statute. The project has been completed and was accepted by the Commonwealth on February 14, 1933, as of February 2, 1933.

The claims of numerous interveners were dealt with in the master’s report in accordance with the alphabetical order of their names. As to the claim of DiPietro the master found as follows: On March 31, 1932, DiPietro entered into a contract with Rooney and Company to perform certain work required by the contract with the Commonwealth in laying drainage pipes. In pursuance of this contract he furnished labor at prices totalling $9,024.82, which were agreed to by the parties. The work provided by the contract with Rooney and Company was that he should “furnish and lay all side drains including all material and labor” and that he should “lay” certain sizes of drain [100]*100pipe and “do all trench excavation.” His contract further recited that he “agrees to do the above work ... in accordance with the Massachusetts Standard Specifications and to the satisfaction of the State Engineers” and “is to comply with all the terms and conditions of said Contract between Commonwealth of Massachusetts and” Rooney and Company. Rooney and Company’s contract with the Commonwealth provided that the entire work should be completed to the satisfaction of the engineers. The last payment to DiPietro was made on February 8, 1933, leaving a balance owed to him of $1,919.12. He filed his sworn statement of claim under G. L. (Ter. Ed.) c. 30, § 39, with the proper State officer on February 7, 1933. Whether this sworn statement of claim was filed within the sixty days specified by the statute depends upon certain work done by DiPietro in the latter part of January, 1933. He finished laying the pipes and side drains sometime in September, 1932. Thereafter the only work he did was on a short pipe carrying surface water from a piece of low ground beside the road into the main longitudinal drain. This pipe “was originally laid by DiPietro under the constant supervision of the State engineer and to his satisfaction.” Early in January, 1933, as the whole work was nearing completion, the assistant State engineer, who was at that time through with his work on the project and was employed in the maintenance department of the Commonwealth, noticed that the pipe was plugged up so that surface water was not running through it. He informed DiPietro that there was something wrong although he did not know the cause of the trouble; that he could not order him to go back because that was a matter to be decided by Rooney and Company; and that he was telling DiPietro because he could not see Rooney and Company. Without consulting anyone connected with Rooney and Company, and without the latter’s knowledge of the trouble, DiPietro on January 27, 1933, examined the pipe and found that it had settled in the middle, and with two of his men he dug up three sections — about ten feet — placed gravel underneath to bring the line of the pipe back to the proper pitch, ce[101]*101mented the sections together, backfilled the trench and tamped the earth down, leaving the whole in a condition satisfactory to the State engineer, the work taking about a day. The sagging of the pipe was due to the settlement, either of the gravel placed by DiPietro under the pipe in the trench which he had previously dug, or of the earth placed by Rooney and Company as the base for the new road. The master states: “It is impossible to find which was the cause.” DiPietro repaired the pipe without regard to whose fault it was because it was a piece of work previously done by him under his contract with Rooney and Company, and he made no extra charge and expected no payment therefor. Whether or not in the above circumstances January 27 is the day when the claimant last furnished labor on this work under ’ his contract, and accordingly whether his sworn statement of claim was filed within the specified sixty days, presents a question of law.

In Peerless Unit Ventilation Co. Inc. v. D’Amore Construction Co. 283 Mass. 121, 124, 125, it was said: “Work actually called for by the contract or continuing employment, performed in good faith with the intention of completing the job, though done with the ulterior purpose of saving the hen and postponed until long after the bulk of the work has been completed, will permit the filing of the statement within sixty days after the doing of the last work. . . . But ... a gratuitous performance of work not contracted for, does not set the time running so as to preserve a Hen for the earlier work.” Besides, work done to correct defects or to make substitution for previous faulty performance is equally effective to renew the period for filing the claim for a lien. Such correction is as much needed to furnish a complete and proper performance of the contract as work done to finish a previously unfinished detail of the work. In either case the contract obligation is unfulfilled pending the performance of such additional work. See Winer v. Rosen, 231 Mass. 418; McLean v. Wiley, 176 Mass. 233, 234. “Work done to remedy defects may be considered in deciding whether a claim is filed in time.” Dolben v. Duncan Construction Co. 276 Mass. 242, 251.

[102]*102The question is, Was the work done by DiPietro necessary under his contract? The pipe involved was originally called for by the contract. If DiPietro did the work in a faulty or unworkmanlike manner, he would not thereby have completely performed the work under the contract, Thurston v. Blunt, 216 Mass. 264, 268, and work done in remedying the defect would have been work required by the contract.

The appellants contend that for two reasons all contract obligations of DiPietro had ceased when the pipe was originally laid, and hence that any work thereafter done could not have been work called for by the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C&I Steel, LLC v. Peabody Construction Co.
22 Mass. L. Rptr. 402 (Massachusetts Superior Court, 2007)
Interstate Electrical Services Corp. v. Cummings Properties, LLC
825 N.E.2d 1059 (Massachusetts Appeals Court, 2005)
Otis Elevator Co. v. Westchester Fire Insurance
741 N.E.2d 80 (Massachusetts Appeals Court, 2001)
Ross v. Planet Insurance
279 N.E.2d 690 (Massachusetts Supreme Judicial Court, 1972)
International Telephone & Telegraph Corp. v. Hartford Accident & Indemnity Co.
257 N.E.2d 787 (Massachusetts Supreme Judicial Court, 1970)
Armco Drainage & Metal Products, Inc. v. Town of Framingham
123 N.E.2d 471 (Massachusetts Supreme Judicial Court, 1954)
Mario Pandolf Co. v. Commonwealth
21 N.E.2d 221 (Massachusetts Supreme Judicial Court, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
194 N.E. 915, 290 Mass. 97, 1935 Mass. LEXIS 1068, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carter-v-commonwealth-mass-1935.